Upload
delight-homes-kenya
View
25
Download
0
Embed Size (px)
Citation preview
Golf CourseArea Status: Progress: Next Step
Golf Course Holes10,11,12,13,14,15,16, 17 & 18
• Continuous maintenance of the back nine holes ongoing• Construction of golf cart ramp outstanding; to be completed by Lexis on resuming works
•Continuous maintenance•Complete construction of hole 14 golf cart ramp on return of the boundary wall contractor on site.
Boundary Wall
Area Status: Progress: Next Step
Entrance Walling Clear View•Walling at 99% complete; painting of grille outstanding
Double Masonry Wall•Construction Complete; backfilling almost done to the ngurunga gate
Mitini & Ngurunga WallingConstruction complete only tieing to the main boundary
•Fixing of the sliding gates to the clear view wall
Status: Progress Summary
A. Entrance Walling: Clear View and Double Masonry Walling Dashboard
• Actual Progress – 97% Complete
Double MasonaryWall
Clear View Wall
LEGEND
Boundary WallArea Status: Progress: Next Step
Entrance Walling
Sentry Box•Construction of sentry box on going; internal plaster & fixing of windows completeGuard House•Construction ongoing; 70% complete – plastering of internal walls and fixing of windows complete.•Construction of the turnstile houses ongoingGatesErection of the gates along the wall ongoing; works at 90% complete
•Fixing of windows and doors to sentry boxes and guard house•Finishes to sentry box and guard house
Road Works
Area Status: Progress: Next Step
RoadA100
1+741
• Overall completion – 96% •Snagging and construction of culvert headwalls and storm water drainage manholes•Clearing/cleaning up and repairs of defective works ongoing
•Sectional Handover
Kerbs & Channels
Hardcore
LEGEND
Earthworks
Area Status: Progress Summary
Phase 1 Summary
•Actual Progress – 96% Complete
Road WorksArea Status: Progress: Next Step
Road D1001+467
• Overall Completion – 70% •Earthworks to subgrade levels complete;•Construction of culvert crossings complete•Hand packing of hard core 50% complete
• Finish laying and hunching of kerbs and channels•Storm water drains construction•Hand packing of hard core
Road Works
Area Status: Progress: Next Step
Road D1011+156 M
•Overall Construction – 60 %• Earthworks 97% complete; pending section at the main dam crossing•Laying of kerbs and channels 45% complete•Construction of culvert crossings complete; storm water drains construction ongoing
•Laying and hunching of kerbs and channels• Stone pitching for storm water drains
Bulk Earthworks ongoing
LEGEND
Road Works
Area Status: Progress: Next Step
Road D102, D103, D104, D105
1+216 M
• Overall Construction – 60 %• Earthworks 85% complete; pending section at the box culvert crossing•Construction of box culvert next to hole 14 ongoing•Laying of kerbs and channels 40% complete•Construction of culvert crossings complete; storm water drains construction ongoing
•Completion of Earthworks•Laying and hunching of kerbs and channels•Stone pitching for storm water drains
Bulk Earthworks ongoing
LEGEND
Electric FenceStatus: Progress Summary
A. Electric Fence: Southern Boundary & Northern Boundary Dashboard
• Actual Progress – 90% Complete
Southern BoundaryNorthern Boundary
Mitini Scapes
LEGEND
Electric FenceArea Status: Progress: Next Step
Section 1: Southern Boundary & Mitini Section
Overall Progress – 98% against projected progress of 100%•Clearance and restraining of the fence line complete• Laying of power cables for powering the line complete; Energizing complete
•Testing and commissioning of fence•Continuous maintenance of the fence line
Section 2:Northern Boundary
Overall Progress – 95% against projected progress of 100%•Erection of the poles and wiring complete on the northern side – 100% complete; •Erection of solar panel complete and energizers delivered to site•Powering to be done on completion of the northern sentry box
•Energizing the fence
Section 3: Along MoruRidge
Progress – 95% •Erection of the poles and wiring – 100% complete; •Erection of solar panel complete; powering of fence to be done on completion of the corner sentry in hole 14
• Energizing of the fence
Water SupplyArea Status: Progress: Next Step
Water Reticulation –Phase 1
•Overall Progress – 85% against projected progress of 100% Completion•Excavation of 21 Km of the pipe line (110mm, 80mm & 63mm) complete - along road A100,D100, D200, D300, D400, D500, D600, D601, C100; E200,•Laying of pipes ongoing subsequent with the trenching; 18 Km HDPE pipes laid
•Trenching for water lines and laying of water lines
Infrastructure UpdateArea Status: Progress: Next Step
Golf Course Irrigation Pump
•Pump already delivered to the irrigation contractor, installation to commence on completion of the pump house construction•Working with the irrigation contractor to construct the pump house
•Pump house construction
Sewer Treatment Plant
•Sewer treatment plant already delivered to site; Part installation complete; awaiting fixing of control panel•Construction of the control room to commence on agreement with the lexis international
• Complete installation of the plant control panel•Testing and commissioning of plant
Power Supply • Power supply to sewer treatment plant complete together with installation of the distribution board• Power supply works to plot G722 ongoing; erection and pulling of LV lines complete; •Installation of transformer complete, request for quotation from Mehta electrical to install a high mast security light along the northern boundary
•Installation of security light along northern boundary
Wadi Degla• We are pleased to inform you that Migaa has entered into a partnership
with the Egyptian conglomerate Wadi Degla Holdings through their local subsidiary Wadi Degla Investment (K) ltd.
• The agreement between Migaa and Wadi Degla involves development of the remaining front nine holes of Migaa 18 hole championship golf course, Sports Facilities, Club House and management of the golf course to serve the residents of Migaa.
• Each Migaa plot owner or unit owner will get a free Wadi Degla membership and will have a chance to reciprocate to any other Wadi Degla branches both locally and abroad and shall have rights to the facilities managed by Wadi Degla anywhere in the world.
• Wadi Degla is expected to complete construction within 12 months after commencement.
MITINI SCAPES
• The completed Phase 1 comprises of 82 units; 12 cottages and 70 apartments and sits on approximately 6 acres.
• Currently we have 4 residents who are already residing.
PROGRESS UPDATE
Contemporary Chic Modern
CONSTRUCTION UPDATEOverall Project Progress 42%Projected completion date 31st December 2016
Block 4•Internal Plaster for ground ,1st , 2nd & 3rd Floor 85% Complete while 4th , 5th & 6th Floor 75% Complete.•External Cladding 75% Complete.•Roofing Works 70% Complete.
PROGRESS UPDATE
Contemporary Chic Modern
Block 1(IPL Block)• 7th Slab Complete.•Internal Plaster for ground ,1st , 2nd & 3rd
Floor 85% Complete while 4th & 5th is at 50% Complete.•External Plaster 70% Complete.
PROGRESS UPDATE
Contemporary Chic Modern
Block 2• 7th floor slab complete.•Internal Plaster for ground, 1st & 2nd
floor 65% Complete.•External Plaster 50% Complete
PROGRESS UPDATE
Contemporary Chic Modern
Block 3•4th Floor Slab 60% Complete.•Internal Plaster works in ground floor 80% Complete.