INFRASTRUCTURE PROJECTS UPDATE

Migaa progress update september 2016-1

Embed Size (px)

Citation preview

INFRASTRUCTURE PROJECTS UPDATE

Golf CourseArea Status: Progress: Next Step

Golf Course Holes10,11,12,13,14,15,16, 17 & 18

• Continuous maintenance of the back nine holes ongoing• Construction of golf cart ramp outstanding; to be completed by Lexis on resuming works

•Continuous maintenance•Complete construction of hole 14 golf cart ramp on return of the boundary wall contractor on site.

Boundary Wall

Area Status: Progress: Next Step

Entrance Walling Clear View•Walling at 99% complete; painting of grille outstanding

Double Masonry Wall•Construction Complete; backfilling almost done to the ngurunga gate

Mitini & Ngurunga WallingConstruction complete only tieing to the main boundary

•Fixing of the sliding gates to the clear view wall

Status: Progress Summary

A. Entrance Walling: Clear View and Double Masonry Walling Dashboard

• Actual Progress – 97% Complete

Double MasonaryWall

Clear View Wall

LEGEND

Boundary WallArea Status: Progress: Next Step

Entrance Walling

Sentry Box•Construction of sentry box on going; internal plaster & fixing of windows completeGuard House•Construction ongoing; 70% complete – plastering of internal walls and fixing of windows complete.•Construction of the turnstile houses ongoingGatesErection of the gates along the wall ongoing; works at 90% complete

•Fixing of windows and doors to sentry boxes and guard house•Finishes to sentry box and guard house

Road Works

Area Status: Progress: Next Step

RoadA100

1+741

• Overall completion – 96% •Snagging and construction of culvert headwalls and storm water drainage manholes•Clearing/cleaning up and repairs of defective works ongoing

•Sectional Handover

Kerbs & Channels

Hardcore

LEGEND

Earthworks

Area Status: Progress Summary

Phase 1 Summary

•Actual Progress – 96% Complete

Road Works

Road WorksArea Status: Progress: Next Step

Road D1001+467

• Overall Completion – 70% •Earthworks to subgrade levels complete;•Construction of culvert crossings complete•Hand packing of hard core 50% complete

• Finish laying and hunching of kerbs and channels•Storm water drains construction•Hand packing of hard core

Road Works

Area Status: Progress: Next Step

Road D1011+156 M

•Overall Construction – 60 %• Earthworks 97% complete; pending section at the main dam crossing•Laying of kerbs and channels 45% complete•Construction of culvert crossings complete; storm water drains construction ongoing

•Laying and hunching of kerbs and channels• Stone pitching for storm water drains

Bulk Earthworks ongoing

LEGEND

Road Works

Area Status: Progress: Next Step

Road D102, D103, D104, D105

1+216 M

• Overall Construction – 60 %• Earthworks 85% complete; pending section at the box culvert crossing•Construction of box culvert next to hole 14 ongoing•Laying of kerbs and channels 40% complete•Construction of culvert crossings complete; storm water drains construction ongoing

•Completion of Earthworks•Laying and hunching of kerbs and channels•Stone pitching for storm water drains

Bulk Earthworks ongoing

LEGEND

Electric FenceStatus: Progress Summary

A. Electric Fence: Southern Boundary & Northern Boundary Dashboard

• Actual Progress – 90% Complete

Southern BoundaryNorthern Boundary

Mitini Scapes

LEGEND

Electric FenceArea Status: Progress: Next Step

Section 1: Southern Boundary & Mitini Section

Overall Progress – 98% against projected progress of 100%•Clearance and restraining of the fence line complete• Laying of power cables for powering the line complete; Energizing complete

•Testing and commissioning of fence•Continuous maintenance of the fence line

Section 2:Northern Boundary

Overall Progress – 95% against projected progress of 100%•Erection of the poles and wiring complete on the northern side – 100% complete; •Erection of solar panel complete and energizers delivered to site•Powering to be done on completion of the northern sentry box

•Energizing the fence

Section 3: Along MoruRidge

Progress – 95% •Erection of the poles and wiring – 100% complete; •Erection of solar panel complete; powering of fence to be done on completion of the corner sentry in hole 14

• Energizing of the fence

Electric Fence

Water SupplyArea Status: Progress: Next Step

Water Reticulation –Phase 1

•Overall Progress – 85% against projected progress of 100% Completion•Excavation of 21 Km of the pipe line (110mm, 80mm & 63mm) complete - along road A100,D100, D200, D300, D400, D500, D600, D601, C100; E200,•Laying of pipes ongoing subsequent with the trenching; 18 Km HDPE pipes laid

•Trenching for water lines and laying of water lines

Water Supply

Remaining Water Lines

Trenched Water Lines

LEGEND

Infrastructure UpdateArea Status: Progress: Next Step

Golf Course Irrigation Pump

•Pump already delivered to the irrigation contractor, installation to commence on completion of the pump house construction•Working with the irrigation contractor to construct the pump house

•Pump house construction

Sewer Treatment Plant

•Sewer treatment plant already delivered to site; Part installation complete; awaiting fixing of control panel•Construction of the control room to commence on agreement with the lexis international

• Complete installation of the plant control panel•Testing and commissioning of plant

Power Supply • Power supply to sewer treatment plant complete together with installation of the distribution board• Power supply works to plot G722 ongoing; erection and pulling of LV lines complete; •Installation of transformer complete, request for quotation from Mehta electrical to install a high mast security light along the northern boundary

•Installation of security light along northern boundary

Cabbro sample 40sqm to specification

Wadi Degla• We are pleased to inform you that Migaa has entered into a partnership

with the Egyptian conglomerate Wadi Degla Holdings through their local subsidiary Wadi Degla Investment (K) ltd.

• The agreement between Migaa and Wadi Degla involves development of the remaining front nine holes of Migaa 18 hole championship golf course, Sports Facilities, Club House and management of the golf course to serve the residents of Migaa.

• Each Migaa plot owner or unit owner will get a free Wadi Degla membership and will have a chance to reciprocate to any other Wadi Degla branches both locally and abroad and shall have rights to the facilities managed by Wadi Degla anywhere in the world.

• Wadi Degla is expected to complete construction within 12 months after commencement.

Wadi Degla• Proposed Club House Phase 1

Wadi Degla• Proposed Club House Phase 2

Wadi Degla• Proposed Sports Facilities

MITINI SCAPES

• The completed Phase 1 comprises of 82 units; 12 cottages and 70 apartments and sits on approximately 6 acres.

• Currently we have 4 residents who are already residing.

Progress

Update

PROGRESS UPDATE

Contemporary Chic Modern

CONSTRUCTION UPDATEOverall Project Progress 42%Projected completion date 31st December 2016

Block 4•Internal Plaster for ground ,1st , 2nd & 3rd Floor 85% Complete while 4th , 5th & 6th Floor 75% Complete.•External Cladding 75% Complete.•Roofing Works 70% Complete.

PROGRESS UPDATE

Contemporary Chic Modern

Block 1(IPL Block)• 7th Slab Complete.•Internal Plaster for ground ,1st , 2nd & 3rd

Floor 85% Complete while 4th & 5th is at 50% Complete.•External Plaster 70% Complete.

PROGRESS UPDATE

Contemporary Chic Modern

Block 2• 7th floor slab complete.•Internal Plaster for ground, 1st & 2nd

floor 65% Complete.•External Plaster 50% Complete

PROGRESS UPDATE

Contemporary Chic Modern

Block 3•4th Floor Slab 60% Complete.•Internal Plaster works in ground floor 80% Complete.

SHOW APARTMENT PROGRESS PHOTOS

Contemporary Chic Modern

Show Apartment Remaining Items• (OS & E) Operating Supplies and

Equipments and (FF& E) Furniture Fixtures and Equipments.