CELBLOX: Pre-Pour Checklist

Embed Size (px)

Citation preview

Page 1: CELBLOX: Pre-Pour Checklist

PRE-POURCHECKLIST

Page 2: CELBLOX: Pre-Pour Checklist

SQUARE, PLUMB, & LEVEL

• Are walls & corners square, plumb & level?

• Is top of wall level?• Are all bucks square,

plumb & level?• Is diagonal buck bracing

in place to maintain square during pour?

• Are bucks securely connected to block?

Page 3: CELBLOX: Pre-Pour Checklist

PLANNING & REBARPLANNINGDoes layout match the plans?Are all inspections and approvals complete?Is enough manpower scheduled for pour date?Is pump ordered and scheduled?Is concrete ordered and quantity verified?Is there space for pump, trucks, & crew?Is position of anchor bolts or straps planned?

REBARAre all verticals & horizontal s installed and tied as required?Dowel ready to insert if adding another level?

Page 4: CELBLOX: Pre-Pour Checklist

STRAPPING

STRAPPINGAre all outside corners strapped?Are cut block and potential weak spots

strapped from both sides?Are jobsite manufactured angles

strapped from both sides?Are T-walls and/or pilasters properly

strapped?Are lintels properly strapped?Is top of wall protected if adding

another level?

Page 5: CELBLOX: Pre-Pour Checklist

PENETRATIONS & SUPPLIES

PENETRATIONSAre beam pockets installed and strapped?Are mechanical penetrations in place and secured?Are brackets or anchor bolts for interior walls in place?Are ledger or ledger connections in place and fastened?Are weld plates, as specified on plan, in place?

SUPPLIESIs scrap OSB or lumber and drills & screws on hand if

needed during pour?Are anchor bolts or straps on hand for top of wall?Is laser level or enough string ready to plumb the wall?Is concrete vibrator ready to consolidate walls?