Project Progress – 31 th Oct 2013

Abhra Status report as on 31.10.2013

Embed Size (px)

DESCRIPTION

Abhra Status report as on 31.10.2013

Citation preview

Page 1: Abhra Status report as on 31.10.2013

Project Progress – 31th Oct 2013

Page 2: Abhra Status report as on 31.10.2013

STATUS REPORT OF MY HOME ABHRA Tower-”A” As On 31.10.13

1.10th Floor Slab : Completed2.11th Floor Slab : Flat No 1 & 2,4 & 5 flat Bar Bending work In Progress 3rd flat Columns work In Progress

Page 3: Abhra Status report as on 31.10.2013

STATUS REPORT OF MY HOME ABHRA Tower-”B” As On 31.10.13

1.10th Floor Slab : Completed2.11th Floor Slab : Flat No 1 & 2 slab Planning Today,4 & 5 Shuttering work in progress,3rd flat Columns Steel

Work In Progress

Page 4: Abhra Status report as on 31.10.2013

STATUS REPORT OF MY HOME ABHRA Tower-”C” As On 31.10.13

1.8th Floor Slab : Flat No 01 Slab Completed ,Flat No 02 Planning Today

Page 5: Abhra Status report as on 31.10.2013

STATUS REPORT OF MY HOME ABHRA Tower-”D” As On 31.10.13

1.10th Floor Slab : Completed2.11th Floor Slab : Flat No 1 and 2 Completed,4 and 5 flat Bar Bending Work Progress,3rd Flat Columns work In

Progress

Page 6: Abhra Status report as on 31.10.2013

STATUS REPORT OF MY HOME ABHRA Tower-”E” As On 31.10.13

1.10th Floor Slab : Completed2.11th Floor Slab : Flat No 1 & 2 Slab Completed ,4 & 5 flats Slab Planning Today ,3rd Flat Slab bar

Bending Completed