Co-processing of Waste in Kuwait in local Cement Industry -Sustainable option ALEXANDER KOSHI Cement consultant 16/4/2014

Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

Embed Size (px)

DESCRIPTION

A Presentation on how to solve Menace of landfalls in Kuwait

Citation preview

Page 1: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

Co-processing of Waste in Kuwait in local Cement

Industry -Sustainable option

ALEXANDER KOSHICement consultant 16/4/2014

Page 2: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

MENANCEOFLANDFILLSIN KUWAIT&TYPESOF WASTE

PRESENT PROPOSAL FOR DISPOSAL COPROCESSINGOF WASTE AS AFR

RESOURCES IN LOCAL CEMENT INDUSTRY GLOBAL &UAE ACTUAL ACSE STUSDIES OF

WASTE IN CEMENT INDUSTRY BENEFITS TO COUNTRY

CONTENTS

Page 3: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

WASTES IN KUWAIT MUNICIPAL INDUSTRIAL AGRICULTRAL WASTE All above wastes are dumped at 14 landfills

have been closed for more than 20 years due to operational problems and proximity to new residential, commercial, industrial areas

Daily 5000tons of waste unsorted and dumped. Occupying scarce land area with oil extraction resources and future environmental

TYPESOF WASTE IN KUWAIT

Page 4: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

KUWAIT GENERTAES 2MILLION TONNES PER CAPITA 1.5 KG ALL WASTE DUMPED WITH IN LAND FILLS 14 CLOSE LAND

FILLS &4 OPEN LAND FILLS LAND FILLS OCCUPY 180SQKM –LARGE FOR SMALL

COUNTRY WHERE 70% OF THE LAND ALLOCATION FOR KOCWITH 30%FOR DEVELOPMENT

OVER THE YEARS MOST OF DUMPING GROUNDS SURROUNDED BY RESIDENTIAL &COMMERCIAL AREAS DUE TO URBAN DEVELOPMENTS.

DUMPSITES BREDDING GROUND FOR FOR TOXICGASES AND SUDDEN FIRE ENDANGERING THE LIVESOF THEPEOPLE

ANNUAL COST OF WATSE MANGEMENT 29 MILLION KWD

MENANCE OFLANDFILLS &TYPESOFWASTESIN KUWAIT

Page 5: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

LANDFILL

AREA FROM TO TOTAL

1 QUARAIN 1 SQ. M 1975 1985 5000000M3

2 SULAIBA 3 SQ. M 1980 2000 10000000M3

3 JEEP-ALSHOUK

6 SQ.M 1970 1993 20000000M3

MENANCE OFLAND FILLS IN KUWAIT

Page 6: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

Over the years most of the dump sites in Kuwait have been surrounded by residential commercial areas due to urban development.

Dump sites become breeding ground or toxic gases and spontaneous firesendangering the lives of people.

      CONSTRUCTION &DEMOLITION WASTES Construction waste are used for rehabilitation purposes making aggregates in by EPIC

(Environment Preservation Industrial Co) avoiding land for dumping Kuwait led other countries in building and operating plant for to recycle construction waste

in 2004 under BOT. USED TYRES Used tyre about 7 million are accumulated in RAHYA 5 kms from new Jahra city.In April,

there was massive fire with emission of toxic gases Carbon monoxide (CO), Sulphur dioxide (SO2) oxides of nitrogen (NO)

Use of land-fills to store used tyres will be time bomb waiting to explode. Cause pollution on par with oilfields burning in 1990 with dengue epidemic

Municipality has decided disposal of tyres are to be as per resolution 75/5646 by a ministerial committee that emphasized avoiding land fill for used tyres and disposing in environ mentally sound methods .

TYPES OF WASTE IN KUWAIT

Page 7: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

• Fire in tyre mountains & stockpiles. • Danger to life• Destruction of the built environment • Toxic smoke• Pyrolytic contamination of ground water

Environmental hazards

The Tyre Problem

Copyright Symphony Recycling Technologies Ltd

Page 8: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

• Scrap tyres act as breeding grounds for mosquitoes and other vermin.

• Works with other solutions to reduce malaria, dengue, filariasis, West Nile Fever, etc.

• Break the tyre – break the cycle

Health issues

The Tyre Problem

Copyright Symphony Recycling Technologies Ltd

Page 9: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

HAZARDOUS WASTES Since 1999 all public authority for industry instructed all hazardous waste to be disposed in

specially prepared waste disposal site in Al-Shuiba area. But this is not environmentally preferable option due to long term adverse effects and

health impact.Extensive studies around world indicate links between cancer and exposure to hazardous waste.

SEWAGESLUDGE Kuwait consumes 132 gallons per capita with a population of 3.6 million There are 6 waste water treatment plants in Kuwait currently treating 750,000m3 of waste

water with converting waste to reusable water but producing residue called sewage sludge 125 tons with 30% moisture per day which will go up to 250TPD in 2015Presently, sewage

sludge are used as manure for gardenand desert soil stabilization. This will create future problem as sewage sludge must be((Class –A)) requirement prior to discharge and if land filled produce harmful gases

Usage of sewage sludge as fuel in cement plant utilizing waste heat from cement kiln for drying is a Environmental friendly service to Public and governments in Switzerland, Nether lands,Germany, China, Turkey are investing in machinery in local cement plants paying gate fee to cement plant to dispose sewage sludge offering environment service to cement industry’s WIN –WIN situation for government andCitizens

Contaminated sand drilling mud oil sludge from oil industry The Gulf war in 1991 due to oil spillage 300 oil lakes covering area of 50 sq. kms KOC is doing remediation projects for oil lakes damaged terrestrial resources category 70.

TYPESOF WASTE KUWAIT

Page 10: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

PRESENT PROPOSAL - MUNICIPAL WASTE- At present Kuwait is in process of reorganizing waste

management as per world bank guide lines to produce electricity under BOT,under Partnership Technical Bureau utilizing the latest technologies to treat municipal solid waste in Kuwait .The Project aims to protect the environment and land resources and to generate alternate power sources electricity to be repurchased by ministry of electricity and water.

The project is located at KUBD 25 kms from Kuwait city.At area of 50000m2sorting treatment using incinerators for production electricity and land filling ashes from incinerator. The land filling waste will be 5 % of the feed municipal waste fed to sorting. A 30 year contract with winning investor with time frame 2years for installation.

PRESENT WASTE DISPOSAL

Page 11: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 12: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 13: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

Vision for Waste management hierarchy

Page 14: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 15: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 16: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 17: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

Input

grinding,Drying

grinding,Drying Water

1.Sorting1.Sorting Fe, NF, Plastic

2. Sorting2. Sorting Glass, Sand,….

3. Sorting3. Sorting RDF IRDF II

Page 18: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 19: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 20: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 21: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

Alternate Fuel forKuwait Cement Company

Sewage Sludge 1 ton = 0.4tons of PetCoke

Tyres 1 ton = 1.2 ton of Coal

RDF from Municipal waste 1 ton = 0.5 ton of Coal

Page 22: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 23: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 24: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 25: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 26: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 27: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

COUNTRY WASTE CEMENTPLANT

QUANTITY OF WASTE

Bahrain Second world war-open pond stored oil since 1940 ..1990

Gulf cement Rasalkhaimah

300000 tonsStored open pond oil (1940…1990)

Cleared landfill now Ad-Gas plant adjacent to Bapco

UAE Used Tyres 120mm Dia

National cement Dubai

Shredded tyrechips Star cement Ras alkhaiman

Daily 120 tons of shredded tyres

China Sewage sludge Heidel berg-Guangzhou

20000 tons of sewage sludge

50.000tons of Co2

Indonesia Hazardous waste,used tyres

Ctereupp&Cireboncement plant

40000tons of waste

100000tons of co2

ACTUAL CASE STUDIES OF USING WASTE IN GLOBAL &UAE CEMENT INDUSTRY

Page 28: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 29: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 30: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 31: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 32: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

UPGRADES WASTE MANAGEMENT WITHIN HIERARCHY-FROM DISPOSAL TORECOVERY

AVOID LAND FILLING AREA FOR BETTER RESOURCESREDUCESPROBLEM WITH LANDFILLINGENVIRIONMENTAL IMAPCTS DISPOSAL HAZARDOUS WASTES IN SUTAINABLEMANNER AS BEST ENVIRIONMENTAL OPTION

REHABLITATION OF CLOSED LAND FILLS ANNUAL COST REDUCTION

WASTEMANAGEMENT

BENEFITS TO COUNTRY

Page 33: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

BENEFITS TO GOVERNMENT CAPEX COST FOR INCINERATOR AND

ELECTRICITY PRODUCTION AND BUY BACK ELECTRICITY AT HIGHER COST FROM BIDDERS CARBON FOOT PRINT IMPROVEMENT AND CO2

EMISSION REDUCTION ADHERE TO DOHA CLIMATIC CONVENTION –

KYOTOPROTOCOLAND UN PROTOCOL ON WASTE CO-PROCESSSING TO KUWAIT IS A SIGNATORY

CO-PROCESSINGOF WASTE IN CEMENT KILN ASPER WORLDBANK UN BASEL CONVENTION UNITEDNATIONS AND UNEP

Page 34: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 35: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 36: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

GREEN HOUSE GAS REDUCTION POTENTIAL GHS REDUCTION IN CO-PROCESSING WASTE

IN CEMENT KILN IS EXTREMLY HIGH . THERMAL SUSBTITUTION OF WASTE IN

CEMENT INDUSTRY CAN REDUCE CO2 EMISSIONS WITH OVERALL REDUCTION IN COUNTRYS EMISSIONS WHICH IS SUBSTANTIALLY IN NATIONAL INTERST

Page 37: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

ANNUALCEMENT CLINKER PRODUCTION

5,000,000 TONS

ANNUAL FOSSIL FUEL IMPORTED COAL USAGE

533200 TONS

CO2 EMISSION PERTON OF CLINKER

1TON CO2PERTON CLINKER

ANNUAL CO2 EMISSION 5,000,000TONS

CO2 EMIISION REDCUCTION 7 %TO 20 % REDUCTION

CO2EMISSION FROM KUWAIT CEMENT INDUSTRY

Page 38: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc
Page 39: Coprocesing of waste in kuwait in local cement acer-pc-toshiba-pc

ECONOMIC GROWTH AT ALL COSTS IS ALWAYS NOT GOOD –A FOCUS ON SUSTAINABLE AND BALANCED DEVELOPMENT

AND HIGH QUALITY OF LIFE

PLANET IS A NOT AGIFT TO OUR CHILDREN BUT A LOAN TAKEN FROM OUR GREAT GRAND CHILDREN AND WE OWE TO PRESERVE IT