13
A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! S. Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration Contract No. CN15402011 Project No. WW-000024-002 Mason District December 15, 2015

South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration January 2016

Embed Size (px)

Citation preview

Page 1: South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration January 2016

A Fairfax County, VA, publication

Department of Public Works and Environmental Services

Working for You!

S. Van Dorn Sanitary Sewer Emergency Replacement and Stream RestorationContract No. CN15402011Project No. WW-000024-002

Mason District

December 15, 2015

Page 2: South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration January 2016

S. Van Dorn Sanitary Sewer Emergency Replacement and Stream RestorationPost Construction

Capital Facilities/Utilities Design and Construction Division/Wastewater Design and Construction Branch

Page 3: South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration January 2016

Project DetailsS. Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration

Capital Facilities/Utilities Design and Construction Division/Wastewater Design and Construction Branch

Project Overview:• Installation of 1000 feet of emergency bypass pumping• Replacement of approximately 120-feet of 20-inch DIP sewer pipe• Installation of large boulder riffle core and placement of surrounding class III riprap• Stream bank restoration

Project Team:• Utilities Design and Construction Division – Brendan Schillo, Jennifer Arias• Wastewater Collection Division – Bobby White, Jonathan Okafor• Stormwater Planning – Justin Pistore

Description:The S. Van Dorn Sanitary Sewer Emergency Replacement and Stream RestorationProject consisted of the emergency replacement of a ruptured sanitary sewer that crosses Backlick Run. To protect the new pipe crossing, an environmentally friendly approach was implemented using large boulder riffle core surrounded by class III riprap. Additional riprap was used to restore the eroding stream banks of this section of Backlick Run. This project was substantially completed on November 6, 2015.

Page 4: South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration January 2016

S. Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration

Capital Facilities/Utilities Design and Construction Division/Wastewater Design and Construction Branch

Mason District – Tax Map No. 81-1 and 81-2

Page 5: South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration January 2016

S. Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration

Capital Facilities/Utilities Design and Construction Division/Wastewater Design and Construction Branch

Emergency Sewer Bypass Pumping System

Page 6: South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration January 2016

S. Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration

Capital Facilities/Utilities Design and Construction Division/Wastewater Design and Construction Branch

Installation of Stream Bypass Culvert

Page 7: South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration January 2016

S. Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration

Capital Facilities/Utilities Design and Construction Division/Wastewater Design and Construction Branch

Removal of Broken Sanitary Sewer Pipe

Page 8: South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration January 2016

S. Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration

Capital Facilities/Utilities Design and Construction Division/Wastewater Design and Construction Branch

Installation of Boulder Riffle Core Pipe Protection

Page 9: South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration January 2016

S. Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration

Capital Facilities/Utilities Design and Construction Division/Wastewater Design and Construction Branch

Sewer Pipe Installation and Concrete Encasement

Page 10: South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration January 2016

S. Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration

Capital Facilities/Utilities Design and Construction Division/Wastewater Design and Construction Branch

Protection of Stream Bank with Class III Rip Rap

Page 11: South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration January 2016

S. Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration

Capital Facilities/Utilities Design and Construction Division/Wastewater Design and Construction Branch

Finished Product with Stream Flow

Page 12: South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration January 2016

Before After

S. Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration

Capital Facilities/Utilities Design and Construction Division/Wastewater Design and Construction Branch

Page 13: South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration January 2016

Additional Information

For additional Information, please call

www.fairfaxcounty.gov/dpwes

S. Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration

Capital Facilities/Utilities Design and Construction Division/Wastewater Design and Construction Branch

Irene Haske Public Information Officer

703-324-5821, TTY [email protected]