14
Crooked Spring Reservation

Presentation to Con-Com on Crooked Spring −9/2013

Embed Size (px)

DESCRIPTION

Photos used in this presentation are by Chelmsford Open Space Stewardship. The work parties were all COSS work parties and funded by COSS.

Citation preview

Page 1: Presentation to Con-Com on Crooked Spring −9/2013

Crooked Spring Reservation

Page 2: Presentation to Con-Com on Crooked Spring −9/2013

Selected History - Crooked Spring Dam •Constructed 1930’s Napachi Gun Club •Reservation purchased 1965 – 37.44 acres •Site Assessment in 1971-1972 •Reconstructed in 1973 •Last engineering inspection February 2007

•Mass Hazard Code – “Significant -high hazard” •Fair condition •Failed riser replaced March 2010 •Declassified with MA DCR •Scheduled for re-inspection in 2012

Page 3: Presentation to Con-Com on Crooked Spring −9/2013

Crooked Spring – Dam Design •120-lf earthen dam (NGVD 119.5’) • 30-lf long & 12-ft high vertical steel sheet spillway weir (NGVD 117’) •Stone riprap lined stilling basin below weir •Flood prevention riser 12” half-round CMP and 24” CMP conveyance to tailrace •Stop-log controlled

Page 4: Presentation to Con-Com on Crooked Spring −9/2013

Crooked Spring Dam - Hydrology • Pond capacity 9.3

acre-feet • 0.88 m2 (560 acres)

watershed • Pond surface 1.5 acre

at OHW • Maximum pond 3.6

acre area • Winter flow 80 GPM

at 1 FPS • Dam can pass 96% of

inflow (305 cfs) from a 100-year storm event (320 cfs) estimated at 6.5 inches over 24 hours

• Crooked Spring Road culvert capacity 62 CFS

Page 5: Presentation to Con-Com on Crooked Spring −9/2013

Crooked Spring Reservation • Draft Master Plan by Zuelke, Larson & Freitus Landscape Architects

Page 6: Presentation to Con-Com on Crooked Spring −9/2013

Crooked Spring Dam - Problem

1974 USDA SCS Overview Plan

2010 Riser Replacement

• Failure of flood control conveyance pipe below the NE portion of the earthen dam • Pond draining via leak below dam (NGVD 110’) AND board leakage through riser (≤ NGVD 117’)

12’ half riser replaced in 2010

Page 7: Presentation to Con-Com on Crooked Spring −9/2013

Crooked Spring Dam - Result CURRENT CONDITION

• Dewatered

• Run-of-river operation w/o storage (inflow=outflow) @ < NGVD 110’ (LLO pipe invert elev.)

• Functions as a stream during low flows

• Debris plugs will function as low-head impoundment immediately after moderate or heavy rainfall events (short –term only)

• Erratic water levels

Page 8: Presentation to Con-Com on Crooked Spring −9/2013

Crooked Spring Dam - Problem CURRENT CONDITION

• Untreated stormwater runoff from Graniteville Road Outlet (not the only source) depositing significant silt – sand behind the dam

Page 9: Presentation to Con-Com on Crooked Spring −9/2013

Crooked Spring Dam - Result • Pond water volume storage

capacity mostly eliminated

• Poor water quality from warm water temperature & low oxygen levels in summer

• Does not freeze solid in winter

Page 10: Presentation to Con-Com on Crooked Spring −9/2013

Crooked Spring Dam - Problem CONDITION PRIOR TO LOWER LEVEL OUTLET FAILURE

• Noxious or invasive pond weed dominating open water area when ponded

Page 11: Presentation to Con-Com on Crooked Spring −9/2013

Crooked Spring Dam - Result • Annual dieback and decomposition of noxious weed contributing to additional

silt deposits & shallow environment with poor water quality

• Eliminating plant diversity (type of plants) – degrading the habitat

Page 12: Presentation to Con-Com on Crooked Spring −9/2013

Crooked Spring Dam - Alternatives SHORT-TERM • Replace failed CMP – rebuild earthen dam ($$S)

Benefit – maintains pond condition in short-term for aesthetics Detriment – Costly for a band-aid fix – restores noxious vegetation

• Decommission duplicative flood-prevention low level outlet & maintain stream run-of-river at current spillway elevation (0 $) Benefit – Allows complete structural assessment of dam to fill in

gaps of the 2007 survey Benefit – $ that would be spent on short-term repair of unnecessary

feature could be used to assess condition and/or used toward a permanent solution

Benefit – Temporary control of noxious vegetation (not permanent solution)

Detriment – Alters view-shed Detriment - May allow other invasive plants to colonize dewatered

area

Page 13: Presentation to Con-Com on Crooked Spring −9/2013

Crooked Spring Dam - Considerations

INTERIM STEPS

• Engineer re-evaluate condition of dam & identify cost to maintain and/or to remove

• Eliminate unnecessary discharges contributing to silt and sand deposits in pond

• Identify sustainable management regime for ecosystem and passive recreational use – Reservation Baseline Assessment and revised Reservation Master Plan

• Investigate options and funding sources (grants) to remove accumulated silt and restore depth of lower pond to open water

Page 14: Presentation to Con-Com on Crooked Spring −9/2013

Crooked Spring Dam - Alternatives LONG-TERM • Dredge Lower Pond then Remove Dam • Dredge Lower Pond then Repair Dam @ existing elevation

(NGVD 117’) • Dredge Lower Pond, Notch Dam @ lower elevation and

restablish low-flow stream channel • Repair Dam without removal of sediment in impoundment

– Ecological succession to eliminate pond

Dredging requires assessment of source of funding, quality of

sediment and probable disposal options and jurisdiction for permits from both state and federal regulatory agencies