Upload
informa-australia
View
494
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Matthew Cobbett, Executive General Manager, Fluor Australia Pty Ltd delivered this presentation at the Mining the Pilbara 2013 conference. The conference aims to promote the sustainable development of mineral resources and the Pilbara region. For more information, visit http://www.informa.com.au/miningthepilbara
Citation preview
Mining The Pilbara
Modularisation for the Pilbara Region 17 July 2013
Matthew Cobbett Executive General Manager Cory Fisher Project Manager
Agenda
Safety - Potential for Improvement with Modularisation
Who is Fluor?
What is Modularisation?
The Reason for Modularisation
1st Generation Modules in the Pilbara
2nd Generation Modules in the Pilbara
Conclusions and Recommendations
GV20130655001.pptx 2
Safety Improvement with Modularisation
GV20130655001.pptx 3
Typical Pilbara Site TRIFR = 7.5
2nd Gen Fabrication Yard 3.25 Million Man-hours – 2 First Aid Treatment
Fluor Corporation
Industry leader – One of the world’s leading publicly traded EPCM and project management companies; #110 on FORTUNE 500 list in 2013
Global reach – Over 1,000 projects annually, serving more than 600 clients in 79 different countries
Worldwide presence – Offices in 29 countries on 6 continents
Depth of resources – 41,000 employees globally
Celebrated 100 years in 2012
60 Years in Australia
GV20130655001.pptx 4
Fluor Corporate Headquarters
Dallas, Texas
2012 Financial Performance
Revenue: $27.6 billion
New awards: $27.1 billion
Backlog: $38.2 billion
Fluor Corporation is rated at investment grade levels:
• Long-term Ratings: Standard & Poors “A-” Moody’s “A3” Fitch “A-”
• Short-term Ratings: Standard & Poors “A-2” Moody’s “P-2” Fitch “F-2”
• Outlook: Standard & Poors - Stable Moody’s - Stable Fitch - Stable
GV20130655001.pptx 5
Fluor Corporation
56 Years on NYSE
Fluor Australia: Current Projects
GV20130655001.pptx 6
*
* Note: Executed as part of FAST JV
What is Modularisation?
“What is?”
• Modularisation is an execution approach for design, procurement, contracting and construction that shifts construction hours away from the site
• Assemblies of process plant components
• Assembled at one location (fabricator) and transported to another (jobsite)
• Made up of structure, equipment, piping, electrical, and instrumentation
• Made in a variety of sizes
GV20130655001.pptx 7
Prefabrication Preassembly
Process Modules Offsite Fabrication
Why Modularise ?
Project drivers for modularisation (pre-assembly, configuration, and fabrication location)
• Safer controlled construction – avoids onsite work at heights and temporary handrails, and utilises fab yard overhead craneage, transporters
• Reduce (unproductive) work hours onsite and reduce camp size
• Value – grating and handrail can be incorporated, platework, liners, and piping can be included in assembly
• Schedule benefits – parallel activities with earthworks/concrete and offsite fabrication
• Labour availability
• Risk management
8 GV20130655001.pptx
Why Modularise ?
Project considerations
• Schedule acceleration requirement
• Engineering design safety factors
• Need early vendor design information
• Design software for engineering and shop drawings
• Transportation to remote locations
• Skilled labor shortages and/or low labor productivity
• Industrial Relations challenges
• HSE challenges
• Risk mitigation: final cost and schedule certainty
Recent modularisation project results
• Allowed for more productive work in shop environment from experienced craft (almost 2:1)
• Reduced field workforce, congestion, travel time, remote location impacts, overtime, and created more work fronts
• Facilitated more ground level work, less preparation, and scaffolding
• Broke job into smaller, more manageable pieces
• Facilitated less dependency on weather, remoteness, or site conditions
• Reduced strain on the availability of experienced site craft and supervision
GV20130655001.pptx 9
1st Generation Modules in the Pilbara
GV20130655001.pptx 10
Case Study – 2nd Generation Modules
Key Lessons Learned (1st Generation to 2nd Generation)
More structures could/should be modularised – stair towers, transfer stations, and train load out facility
Screening building screen support Modules, bins, and hopper Modules worked well – replicate
Maximum of 4 lift points better suited fab yard, ship, and site crane/lifting requirements
Use of lifting trunnions where possible – safer/easier than lifting lugs and shackles
GV20130655001.pptx 12
Key Lessons and Differences (1st Generation to 2nd Generation)
Distance Port Hedland to Site = 350 kilometres (1st Generation)
Distance Port Hedland to Site = 500 kilometres (2nd Generation)
More structures modularised – stair towers, transfer stations, and train load out facility. Max Module weight kept to approximately 200 tonnes due to increased distance and uncertainty of bridge limits during design. Decreased bridge inspection requirements, faster convoys.
Screening building screen support Modules, bins, and hopper Modules worked well – replicated (3 PS Screen Support Modules installed in 1 day).
2nd Generation – Modularisation of Stockyard Transfer Stations proved very effective for site install and access (4 Modules installed in 3 days).
Engaged Chinese Fabricator with more “Offshore” Modularisation experience and better safety culture (Australian scaffold standard essential).
GV20130655001.pptx 13
Shop Detailing – Strategy from Lessons Learned on 1st Generation
The Chinese fabrication facilities can utilise their own in-house shop detailing capability however they will not be familiar with WA and other associated standards, especially mechanical platework detailing, and would require extensive in-house supervision. This issue was experienced on 1st Generation.
Execution strategy was for shop detailing undertaken by WA contractor, and issued directly to the nominated fabricator. Providing shop detail drawings by Perth based shop detailers, allows schedule gains to engineering progress by the early release of drawings.
Detailing of grillage was effectively completed by Chinese Fabricator – simple detailing.
GV20130655001.pptx 14
Summary of Fabrication Strategy
China Based Fabrication
• Drivers No mechanical or electrical
equipment to be shipped overseas for fit out of Modules
Remove work hours offsite Reduced cost (improved value) and
improved schedule Larger transport envelope. EPCM efforts to be concentrated in
one location and maintain a level of tonnages that will be attractive to the larger fabrication workshops
• Scope Modularisation of inflow, OHP, and
outflow building steelwork Shuttle trusses and GTU drive
towers, transfer stations, and TLO bins
Australian Based Fabrication
• Drivers Install equipment – pulleys, idlers,
etc. Optimise local fabrication content
(IR local content) Locally fabricate and deliver early
steel to site to enable early mobilisation of SMP contractor
• Scope Conveyor steelwork COS hoppers and chutes Dust collection structures. Train load out smart Module (PAM)
GV20130655001.pptx 15
Total Tonnes = 15,000 Total Tonnes = 5,200
Offshore versus Onshore Fabrication and Pre-assembly of Modules/Trusses
Fabrication, pre-assembly, shipping, and transport to site
• Offshore fabrication = 15,300 tonnes
• Onshore fabrication = 5,296 tonnes
Schedule comparison – tonnes per month from award to completion in fab yard
• Offshore fabrication output 850% more tonnes per month compared to
onshore fabrication
GV20130655001.pptx 16
Modularisation – Safety
Key requirement in selection process/criteria for fab yards as well as tender presentations and evaluations.
Almost 3.25 million work hours were recorded on the Offshore Fabrication project, with no lost time injury and 2 first aid cases
Safety culture during the life of the project changed due to supervision and the introduction of the hazard card system
Hazard cards – encouraged increased management focus on close out of action items
GV20130655001.pptx 17
Traffic Management Plan – Overall Philosophy
Objective was to minimise police and pilot resources and to reduce the number of disruptions
Night time movements down Great Northern Highway to minimise community impact
MRWA approval was required, requested, and granted for Project
GV20130655001.pptx 18
Night Time Movements Study
A report that quantitatively analysed the impact of night time movements of oversize load operations between Port Hedland and the mine site compared to day time was commissioned
30 kilometers/hour average speed – 9:00 A.M. Port Hedland departure:
• A scenario in which oversize load operations are conducted across three days. Two campsites are utilised in route. Operations commence at 09:00 on each day.
30 kilometers/hour Average Speed – 9:00 P.M. PH departure:
• As above, except that operations commence at 21:00 on each day.
As illustrated in the figure to the right, switching to night time operations results in a 91% reduction in the number of light vehicles delayed, and a 76% reduction in the number of heavy vehicles delayed. Total delay, as quantified by vehicle hours expected to reduce by 85%.
Scenario
9 A.M. 9 P.M. Change
Vehicles
Delayed
Light 454 39 -91%
Heavy 348 84 -76%
Total Delay 269 hours 39 hours -85%
GV20130655001.pptx 19
0
50
100
150
200
250
300
Ho
urs
Total Delay
0
200
400
600
800
1000
Ve
hic
les
Vehicles Delayed
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
9AM:Heavy 9AM:Light 9PM:Heavy 9PM:Light
Divisible Loads – Optimisation
Approximately 19 off loads (stacked flat packs)
• 70% reduction of police
escorts
• 70% reduction of road
closures for passing
Approximately 63 off loads (disassembled flat packs)
• Unachievable police
escort requests
• Significant other road user
interface issues
GV20130655001.pptx 20
Transport with Approval for Night Time Moves and More Than 2 Loads/Convoy
Night time Module movements – 3 nights travel to site rolling road block
136 Modules moved over 27 night time convoys
Total = 81 nights of rolling road blocks
GV20130655001.pptx 21
Transport Without Approval for Night Time Moves and Greater Than 2 Modules per Convoy
Day time travel (refer impact on traffic on GNH) 3 days
136 Modules would have been moved more than 68 convoys
Resulting in total = 204 days of rolling road blocks, compared to 81 nights
GV20130655001.pptx 22
Transport Envelope from Port Hedland for Offshore Fab
GV20130655001.pptx 23
Transport Envelope from Perth for Onshore Fab
GV20130655001.pptx 24
Incentive for using Freight Forwarder – Module Shipping and Transport
Total Transport Solution – Door-to-door solution i.e. ex-China organise origin transportation/export clearance/marine warranty surveying/pre AQIS compliance/sea freight/customs clearance/ discharge/craneage/haulage to site and offloading at site
Cost Effective – a multinational freight forwarder, with the ability to negotiate in the market place with shipping companies, airlines, and heavy haulage without sole sourcing
3 Site SMP install contracts meant site was the obvious interface for Module handover
GV20130655001.pptx 25
Project Photos Critical Path Ship 7 – Product Screen Support Modules
GV20130655001.pptx 26
Project Photos Critical Path Ship 7 – Product Screen Support Modules
GV20130655001.pptx 27
Modular Construction Recommendations
• The decision to modularise is a program execution decision NOT one that is made in construction
• To be successful it is a detailed process of --- What, When, How, and Why --- to modularise
• Need a commitment to move engineering forward to support the decision
• Need a commitment from the owner’s approval process to support all earlier execution requirements
• Understanding of the early work sequences must be built into the fabricator's organisation
• Fabricator selection process provides a clear understanding of the fabricator's internal work processes and sequences. Shop drawings, nesting plans, weld maps, QC documents, and erection mark drawings
• Ensure that engineering requirements matches the material grades and component configurations available within the fabricators market
• Designing with rolled sections produced within that country
• Have the original engineering drawings translated into the local language
• Ensure Engineering Platform matches the fabricator’s
• An advantage to Module Fabrication in a major shop is the ability to work double or triple shifts, coupled with a larger permanent workforce
GV20130655001.pptx 28
Modular Construction Recommendations
Ensure route survey and transport corridors are understood
Detailed planning for Module moves
Understand the critical path
Recognise that Risk exists and manage that risk
It’s a cultural change
Modularisation can accelerate schedule and firms up cost certainty
Modularisation can deliver cost savings, but expectations must be tempered by shipping costs
Modularisation can lead to higher quality
3rd Generation – “Smart Module” Maximisation
Use someone who has done it before – make use of the “lessons learned”
GV20130655001.pptx 29