County of Fairfax, Virginia
Department of Transportation
Implementation of HB 2 (2014) and HB 1887 (2015)
Board Transportation CommitteeJuly 14, 2015
Noelle Dominguez, Legislative LiaisonDepartment of Transportation
County of Fairfax, Virginia
In the past two years, significant changes have been made to the way that transportation projects are funded in Virginia. Presentation will provide information on the changes to State Code and the new processes for related state and federal funding: • Legislative and Funding Background• Project Eligibility and Screening• Evaluation Criteria• Project Costs• Application Process• Project Scoring• Annual HB 2 Application Cycle• CTB Prioritization and Programming• Changes in Project Scope, Schedule, and/or Cost
Department of Transportation 2
Recent Changes to the State Transportation Funding Processes
County of Fairfax, Virginia
Department of Transportation 3
HB 2 Summary• HB 2 (2014) provides for the development of a prioritization process for projects funded by the
Commonwealth Transportation Board (CTB). The bill: – Directs the CTB to develop and implement the prioritization process for roadway, transit,
rail, technology operation improvements, and transportation demand management strategies that must be used for the development of the Six-Year Improvement Program (SYIP), starting July 1, 2016.• The process must consider: congestion mitigation, economic development,
accessibility, safety, and environmental quality. • The CTB will weight these factors for each of the Commonwealth’s transportation
districts, and the CTB assigned different weights to the factors based on location and other factors.
• Congestion mitigation must be weighted highest in Northern Virginia and Hampton Roads.
– Excludes maintenance, federal programs, including Congestion Mitigation and Air Quality (CMAQ), Highway Safety Improvement Program, Transportation Alternatives, and Regional Surface Transportation Program; and several state programs, including urban and secondary road program funds, and revenue sharing.
County of Fairfax, Virginia
Department of Transportation 4
HB 1887 Summary• In 2015, the General Assembly approved HB 1887, which replaces the old 40-30-30
(primary – secondary – urban) roadway funding formula with a new formula. Under the old system, secondary and urban funds were allocated to projects by the localities. HB 1887 changes the old formula to the following:– 45% of the funding to state of good repair, (rehabilitation of structurally deficient
bridges and deteriorating pavement) - allocated by CTB– 27.5% of the funding to the statewide high-priority projects program (projects of
statewide importance to be competed under HB 2) - allocated by CTB– 27.5% of the funding to highway construction district grant programs (localities
would compete for funds under a regional version of HB 2) - allocated by CTB• Also provided that any un-programmed funds in FY 2016-2020 in the SYIP would be
split 50-50 between the high-priority projects program and the highway construction district grant programs.
County of Fairfax, Virginia
Historical Funding Formula
Department of Transportation 5
Revenue Source
Transportation Trust Fund(New Highway Construction)
Set Asides
CMAQ, RSTP,
Revenue Sharing, etc.
Interstate Projects
Federal Match
Revenue Source
Revenue Source
Revenue Source
Allocated by CTB
40% Primary System
Allocated by CTB
30% Secondary
System
30% Urban System
County Board Sets Priorities,
without restrictions
City/Town Council; Sets
Priorities, without
restrictions
County of Fairfax, Virginia
2012-2015 Funding Formula
Department of Transportation 6
Transportation Trust Fund(New Highway Construction)
Interstate Projects
Federal Match
Revenue Source
Allocated by CTB
40% Primary System
Allocated by CTB
Revenue Source
Revenue Source
Revenue Source
$500 Million/ CTB Formula
Allocated by CTB
25% - Bridge Reconstruction and Rehabilitation
25% - High Priority Projects 25% - Interstate, Primary, and
Urban Primary Reconstruction 15% - PPTA Projects 5% - Unpaved Roads 5% - Technology Projects
(CTB has discretion to adjust percentages)
Up to 10% for rail projects that reduce road
construction
Allocated by CTB
Set AsidesCMAQ, RSTP, Revenue
Sharing, etc.
30% Primary System
County Board Sets Priorities, without
restrictions
30% Urban SystemCity/Town
Council; Sets Priorities, without
restrictions
County of Fairfax, Virginia
New Funding Formula
Department of Transportation 7
Transportation Trust Fund(New Highway Construction)
Set AsidesCMAQ, RSTP, Revenue
Sharing, etc. *
45% - State of Good Repair
Pavements and Bridges
27.5% - High Priority Projects Program: Projects and Strategies that address a
need identified for a corridor of statewide significance or regional
network.
27.5% - Highway Construction District Grant Program
Funding available to districts based on allocations pursuant to formulas
contained in historical 40-30-30 formula, so each district receives
identical proportional share of what they would have previously
received.Projects and strategies must address
a need in the Statewide Transportation Plan
Revenue Source
Revenue Source
Allocated by CTB Using Criteria
Allocated by CTB using HB 2 criteria. Local governments, regional
agencies, or transit agencies can apply.
Allocated by CTB using HB 2 criteria.
Local governments can apply.* new $10M set aside for County safety and
operational improvements - allocated based on population and land area
County of Fairfax, Virginia
Implementation of HB 2 and HB 1887
• On March 18, 2015, a draft HB 2 Implementation Policy Guide was released for Public Comment. Comments were accepted in March and April. – The Board of Supervisors endorsed comments at its April 28, 2016, meeting.
• Following some modifications, the CTB adopted the policy on Wednesday, June 17, 2015.
Department of Transportation 8
County of Fairfax, Virginia
HB 1887 Eligibility and Screening• Projects must meet a need identified in VTrans 2040 (Virginia Multimodal Transportation
Plan) for a Corridor of Statewide Significance (COSS), Regional Network or Urban Development Area (UDA) to be considered for the Programs. The screening criteria for each type of project are: – COSS – key multimodal travel corridors that move
people and goods within and through Virginia, servingprimarily long-distance / interregional travel.• Corridors in our region are the Northern Virginia
Corridor (I-66), Seminole Corridor (Route 29), Washington to NC Corridor (I-95), and North-South Corridor.
– Regional Networks – multimodal networks that facilitate intraregional travel within urbanized areas
– Urban Development Areas (UDA) – areas where jurisdictions intend to concentrate future population growth and development consistent with the UDA section within the Code of Virginia. Tysons is currently Fairfax County’s only UDA. UDA’s must be designated by September 30, 2015 for this round of funding.
– Transportation Safety Needs – statewide safety needs identified in VTrans2040
Department of Transportation 9
County of Fairfax, Virginia
HB 1887 Eligibility
Department of Transportation 10
Project Type Statewide High Priority Projects Program District Grant Program
Capacity Need on COSS Yes Yes
Capacity Need on Regional Networks Yes Yes
Improvement to Support UDAs No Yes
Addressing a Safety need Identified in VTrans No Yes
• Applicants will need to identify which of these best fit their candidate project. • Not all types of projects are eligible for both grant programs:
• Projects found to be eligible through the screening process will be forwarded to VDOT and DRPT for evaluation according to the HB 2 factors and measures.
County of Fairfax, Virginia
Eligibility to Submit Projects• Only projects submitted by localities are eligible for the District Grant Program. • Regional entities, localities, and public transit agencies are eligible to submit projects
to the High-Priority Projects Program, but may be limited in project type:
Department of Transportation 11
Project Type Regional Entity (MPOs, PDCs, NVTA) Locality Public Transit
Agencies
COSS Yes Yes, with resolution of support from relevant regional entity
Yes, with resolution of support from relevant regional entity
Regional Network Yes Yes Yes, with resolution of support from relevant entity
UDA No Yes No
County of Fairfax, Virginia
Eligibility to Submit Projects (cont.)• Project must be located within the boundary of the relevant qualifying
entity.• Local governments may submit a joint application for projects that cross
the boundary of a single local government. • The CTB may also choose to submit up to 2 projects for consideration
through the High Priority Projects Program for each application cycle, for the entire Commonwealth.
Department of Transportation 12
County of Fairfax, Virginia
Factors and Evaluation MeasuresThe Policy Guide provides general evaluation measures for each HB 2 factor. Specific definitions are also included.•Congestion Mitigation:
– 50% - Expected Reduction in Person Hours of Delay up to Posted Speed Limit– 50% - Expected Increase in Person Throughput in the Corridor
•Safety: – 50% - Expected Reduction in Total Fatalities and Severe Injuries on the Facility*– 50% - Expected Reduction in the Rate of Fatalities and Several Injuries per 100 Million
Vehicle Miles Traveled on the Facility•Accessibility:
– 60% - Cumulative Increase in Job Accessibility (within 45 minutes by Automobile and 60 minutes for Transit)
– 20% - Cumulative Increase in Job Accessibility for Disadvantaged Populations (within 45 minutes by Automobile and 60 minutes by Transit)
– 20% - Increase in Access to Multimodal Choices* 100% for transit projects
Department of Transportation 13
County of Fairfax, Virginia
Factors and Evaluation Measures (cont.) • Environmental Quality
– 50% - Degree to Which the Project is Expected to Reduce Air Emissions and Greenhouse Gases
– 50% - Potential impact to Natural, Cultural, and Historic Resources from the Project
• Economic Development: – 60% - Support for Economic Development Plans– 20% - Expected Improvements to Travel Time Reliability of the Facility– 20% - Improved Intermodal Access and Efficiency
• Land Use Coordination (only for areas with population over 200,000): – 100% - Support of Transportation Efficient Land Use Patterns
Details of each measure are important.
Department of Transportation 14
County of Fairfax, Virginia
Factor Weighting• The guide includes four categories for Factor Weighting throughout the Commonwealth.
– Category A - primarily includes urban regions (Northern Virginia, Hampton Roads, Fredericksburg).
– Category B - combination of high anticipated growth and above average travel demand with high density in some areas and low density in others.
– Category C - median population growth, and diverse outcomes on travel demand and existing density.
– Category D - below average population growth, travel demand and existing density. • Weighting schemes for each Category are:
Department of Transportation 15
Congestion Mitigation
Economic Development
Accessibility Safety Environmental Quality
Land Use
Category A 45% 5% 15% 5% 10% 20%
Category B 15% 20% 25% 20% 10% 10%
Category C 15% 25% 25% 25% 10%
Category D 10% 35% 15% 30% 10%
County of Fairfax, Virginia
Project Cost• HB 2 requires that the prioritization process be based on the factors
relative to the cost of the project. • For HB 2 project scoring, project benefits will be calculated relative
to HB2-funded costs only. The calculation of scores based on total cost will be provided to the CTB for comparison purposes.
– Regional stakeholders, included the County and NVTA, commented that the funds that the Authority and its member jurisdictions allocate should not be considered in any statewide cost-benefit analysis.
Department of Transportation 16
County of Fairfax, Virginia
Application Process• Project sponsors will need to coordinate with VDOT and DRPT early in the process
to share information on prospective applications. – This will allow project descriptions, cost estimates, and potential benefits to be
developed and refined, and will facilitate the application and evaluation process. • If an applicant submits more than one project for consideration, must rank their
submitted projects in priority order. VDOT and DRPT will evaluate projects in priority order.
• The application, currently being finalized, is expected to be “simple and straightforward.” Specific information on projects, including data for certain measures must be provided by the applicant.
Department of Transportation 17
County of Fairfax, Virginia
Application Process (cont.)• HB2 project applications must include the following information:
– Scope - limits of the project, its physical and operational characteristics, and physical and/or operational footprint.
– Schedule - the expected process for further project development including key milestones, work activities, related activities, approvals/approval timelines. The schedule should be realistic and reflect the complexity of the project, and identify durations for project phases
– Cost –be realistic and account for applicable risk and contingencies based on the size and complexity of the project.
• Projects that are based on conceptual planning-level recommendations, or have not been formally scoped or defined, may require additional planning/ pre-scoping before their benefits can be adequately assessed through HB 2.
Department of Transportation 18
County of Fairfax, Virginia
Application Process (cont.)• Cost Estimates:
– For VDOT administered projects, VDOT to provide the applicant with a cost estimate. If the applicant has provided an estimate, it must be validated by VDOT.
– For locally administered projects and for all DRPT oversight projects, the applicant may provide a cost estimate for each project application, however it must be validated by VDOT and/or DRPT.
– If there is disagreement concerning the estimate that cannot be resolved between the applicant and the VDOT/DRPT local contact, the applicant may request resolution from the VDOT District Engineer/Administrator or the DRPT Director.
Department of Transportation 19
County of Fairfax, Virginia
Project Scoring
Department of Transportation 20
• Each project will be scored by: – Calculating values for each of the evaluation measures– Converting those values into a score for each factor– Then by weighting the factor scores according to one of several potential weighting
frameworks approved by the CTB. • The best project within each measure dictates scores for all projects:
VDOT HB 2 Presentation Document - July 9, 2015
County of Fairfax, Virginia
Project Scoring (cont.)
Department of Transportation 21
Apply Measure Weights: Once each measure’s score has been assigned, the weighting is applied. The sum of weighted measure scores will produce the raw factor score.
Apply Factor Weights. The raw factor score is multiplied by the assigned weighting percentage.
Project Score. All weighted factor scores are added together to provide the project score.
Calculate Cost-Effectiveness. The project score is divided by the HB2-funded cost of the project (in $10 millions).
• For example with a project, with a total score of $30 million scores 61.5: o If the project is requesting $15 million in HB2 funds, the cost-
effectiveness index would be 41 per $ 10 million dollars of HB2 funds invested.
o If the total project costs were used, the cost-effectiveness index would be 21 per $ 10 million dollars of cost.
County of Fairfax, Virginia
Project Scoring Example
Department of Transportation 22
Project "A" - located in Typology A
Congestion Safety Accessibility Environ. Econ. Dev. Land Use
Throughput Delay
F &SI Crash
es
F &SI Crash Rate
Access to Jobs
Access to Jobs
(Dis. Pop.)
Multimoda
l Choic
es
Air Qualit
y
Natural & Cult.
Resources
Economic
Developme
nt
Goods Movement
Travel Tim
Reliability
Trans. Efficie
nt Land Use
Measure Score 62 48 20 32 10 20 10 38 28 30 20 20 17
Measure Weight 50% 50% 50% 50% 60% 20% 20% 50% 50% 60% 20% 20% 100%
Weighted Measure Score 31 24 10 16 6 4 2 19 14 18 4 4 17
Raw Factor Score 55 26 12 33.0 26.0 17
Factor Weighting (Typ. A) 45% 5% 15% 10% 5% 20%
Weighted Factor Score 24.8 1.3 1.8 3.3 1.3 3.4
Project Score 35.9Total Project Cost $20,000,000 Score Divided by Total Cost 18.0HB2 Cost $10,000,000Score Divided by HB2 Cost 35.9VDOT HB 2 Presentation Document - July 9, 2015
County of Fairfax, Virginia
Annual HB 2 Cycle
Department of Transportation 23
Final HB 2 Implementation Policy Guide
County of Fairfax, Virginia
Funding Available for HB 2 Process(subject to revisions)
HB 2 Percentage Amount Available(in Millions)
District Grant Programs $500.1
- Bristol 7.1 35.3
- Culpeper 6.2 31.1
- Fredericksburg 6.9 34.3
- Hampton Roads 20.2 100.8
- Lynchburg 7.1 35.7
- Northern Virginia 20.7 103.7
- Richmond 14.4 72.2
- Salem 9.6 48.1
- Staunton 7.8 39.0
Statewide High-Priority Projects Program 500.1
Total 100.00 1,000.2
Department of Transportation 24
County of Fairfax, Virginia
CTB Prioritization and Programming• The HB2 review teams will present the screening and scoring results to the
CTB and the public. • The CTB will give guidance on program development, and begin to narrow
down their funding decisions for projects that will be funded in the draft SYIP.
• After the draft SYIP is presented, VDOT and DRPT will hold a public comment period that will allow eligible entities to comment on the process, screening decisions, and scoring of individual projects.
• CTB will take into account public comments on the draft SYIP, ultimately approving the final SYIP for implementation in June.
Department of Transportation 25
County of Fairfax, Virginia
CTB Prioritization and Programming (cont.)• Prioritization process does not require the CTB to funds projects in order
of their scoring or to select the highest scoring project. • Additional consideration may be used to develop the SYIP, such as:
– Public feedback from Fall Transportation Meetings;– Overall availability of funding and eligible uses of such funding;– Leveraging of outside funding sources – Maximizing the use of Federal funds;– Project development considerations – timeframe and extent of
Federally required location studies;– Project segmentation – starting the next phase of a multi-segment
roadway improvement.
Department of Transportation 26
County of Fairfax, Virginia
Changes in Project Scope/ Schedule/ Costs Following Project Selection
• Projects that have been selected for funding must be rescored if:– A change in the scope of the project significant enough to impact the
anticipated benefits or to require the location decision, the environmental review process, or public hearing to be revisited; OR
– Significant reduction in the locally/regionally leveraged funds available for the project.
– An estimate increase over certain thresholds, prior to contract award, unless local or other exempt funding is identified to support the increase.
Department of Transportation 27
County of Fairfax, Virginia
Changes in Project Costs• Projects must be re-scored when, based on the total project cost and the increase in the
cost:– Total Cost Estimate <$5 million: 20% increase prior to award of the construction
contract– Total Cost Estimate $5 million to $10 million: $1 million or greater increase prior to
award of the construction contract – Total Cost Estimate > $10 million: 10% increase, with a $5 million maximum, prior to
the award of the construction contract • To cover cost increases, funds will be reprogrammed from projects with surplus
allocations due to estimate decreases, contract award savings, schedule changes, etc. or from the lowest priority project with eligible funds.
• If a project is selected for funding in an approved SYIP, intent is to keep that project as a priority in subsequent SYIPs even if constraints require temporarily de-funding lower-priority HB2 selected projects beyond the current six-year program.
Department of Transportation 28
County of Fairfax, Virginia
Potential Fairfax County Projects for Submission
(not in priority order)
Department of Transportation 29
• Route 1 Widening from Mt Vernon Memorial Highway to Napper Road• Route 7 Widening from the Dulles Toll Road to Reston Ave• Route 28 Widening from Route Rt. 29 to the Prince William County Line • Fairfax County Parkway Improvements
– Route 123 to Route 29– Popes Head Road Interchange
• I-66 and Route 28 Interchange (Phase II) & I-66 Corridor Improvements (Outside the Beltway)
• I-95 and Fairfax County Parkway/Northbound Flyover• Seven Corners Interchange Improvements• Shirley Gate Road Extension
County of Fairfax, Virginia
Department of Transportation 30
Questions?