Corona Transit CenterProject Update

Riverside Transit Agency

Board of Directors

January 28, 2010

Page 2: 2010-RTA Corona Transit Center Update

• 2.1 acres

• 8 bus bays

• 26 parking stalls

• Covered pedestrian plaza

• Elevator/bridge connection to Metrolink

Page 3: 2010-RTA Corona Transit Center Update

Pedestrian Bridge

Page 4: 2010-RTA Corona Transit Center Update
Page 5: 2010-RTA Corona Transit Center Update
Page 6: 2010-RTA Corona Transit Center Update
Page 7: 2010-RTA Corona Transit Center Update

Corona Transit Center

• Groundbreaking November 20, 2009

• Construction began on November 23, 2009

• To date 2,500 man-hours on the project

• Communication with the City and the Railroad is good

• Completion in August 2010

Page 8: 2010-RTA Corona Transit Center Update

Construction Site• Debris removal

• 1,500 feet of fence• 300 feet of a rail spur• Approximately 2 acres of buried asphalt• One 1,300 sq-foot loading dock

• Grading• Required to raise the site 4-6 feet• Imported 11,500 cubic yards of soil, 895

truckloads of dirt

Page 9: 2010-RTA Corona Transit Center Update
Page 10: 2010-RTA Corona Transit Center Update
Page 11: 2010-RTA Corona Transit Center Update

North Retaining Wall

• 210 cubic yards of concrete in wall

• 238 cubic yards of concrete in footing

• 9’ tall, 708’ long, 1’ thick

Page 12: 2010-RTA Corona Transit Center Update
Page 13: 2010-RTA Corona Transit Center Update
Page 14: 2010-RTA Corona Transit Center Update

Note the change in elevation

Page 15: 2010-RTA Corona Transit Center Update

Cast in place wall (CIP)

Saves time & money and is just as strong

Page 16: 2010-RTA Corona Transit Center Update
Page 17: 2010-RTA Corona Transit Center Update
Page 18: 2010-RTA Corona Transit Center Update
Page 19: 2010-RTA Corona Transit Center Update
Page 20: 2010-RTA Corona Transit Center Update
Page 21: 2010-RTA Corona Transit Center Update
Page 22: 2010-RTA Corona Transit Center Update
Page 23: 2010-RTA Corona Transit Center Update

Rain

•To date there have been 12 rain days

•1 million gallons of runoff went through the site without catastrophic results

Page 24: 2010-RTA Corona Transit Center Update

Next Steps

• Tower foundations

• South retaining wall construction

• Solar panels for powering center