Corona California Tranist Center Construction Update. January 2010
Citation preview
Corona Transit CenterProject Update
Riverside Transit Agency
Board of Directors
January 28, 2010
• 2.1 acres
• 8 bus bays
• 26 parking stalls
• Covered pedestrian plaza
• Elevator/bridge connection to Metrolink
Pedestrian Bridge
Corona Transit Center
• Groundbreaking November 20, 2009
• Construction began on November 23, 2009
• To date 2,500 man-hours on the project
• Communication with the City and the Railroad is good
• Completion in August 2010
Construction Site• Debris removal
• 1,500 feet of fence• 300 feet of a rail spur• Approximately 2 acres of buried asphalt• One 1,300 sq-foot loading dock
• Grading• Required to raise the site 4-6 feet• Imported 11,500 cubic yards of soil, 895
truckloads of dirt
North Retaining Wall
• 210 cubic yards of concrete in wall
• 238 cubic yards of concrete in footing
• 9’ tall, 708’ long, 1’ thick
Note the change in elevation
Cast in place wall (CIP)
Saves time & money and is just as strong
Rain
•To date there have been 12 rain days
•1 million gallons of runoff went through the site without catastrophic results
Next Steps
• Tower foundations
• South retaining wall construction
• Solar panels for powering center