Alphecca Management Resources
Total Cost ModelingBest Practices in Project Management
1
You just got an email from your boss with a lot of capitalized
words, exclamation points and some phrases normally not
used in polite company.
The cost of the new product being developed by your team
is now projected to be 35% over target.
What happened?
Alphecca Management Resources
Total Cost ModelingBest Practices in Project Management
2
Total Cost Modeling for Superior Product Development Outcomes• Concepts & Definitions• Examples• Comprehensive Work Breakdown Structures • Improved Risk
Management• Better Reporting and
Control
Alphecca Management Resources
Total Cost ModelingBest Practices in Project Management
Lets go back to the beginning . . .
Your project’s goal is to develop a communications module for a piece of industrial equipment.
During the project’s kick-off meeting the projected cost for the new hardware was flashed on the big screen.
Everyone at the table nodded and said “Don’t worry, we’ve got this.”
3
Alphecca Management Resources
Total Cost ModelingBest Practices in Project Management
Six months later the hardware’s estimated cost is 35% over the original projection.
There are lots of excuses for missing a product cost target – none good.
What our hypothetical project manager likely did not do was use a Total Cost
Model, or TCM, to guide project planning, risk management and tracking.
Now he’s toast . . .
VagueSpecificati
on
PoorCommunicati
ons
Inadequate
Manpower
Wrong Staff Mix
Conflicting
Priorities
4
Contractor
ProblemsInadequat
eFunding
Poor Risk Managem
ent
Alphecca Management Resources
Total Cost ModelingBest Practices in Project Management
MaterialsCertainty of
Internal P/N Description Qty Cost Extended Cost Estimate422-654-627 Housing - Series C 200 mm 1 $1.25 $1.25 100%322-652-108 Socket Head Cap Screw - SS - No. 3 6 $0.10 $0.60 100%
125-350-600K USB Port Assembly Kit 1 $1.09 $1.09 100%TBD CE Certified 3V Power Supply 1 $4.75 $4.75 80%TBD Power Supply Adapter 1 $2.00 $2.00 80%
125-200-127K Board Mounting Kit 1 $2.14 $2.14 100%TBD Cellular/WiFi Communications Board 1 $85.00 $85.00 70%TBD Shipping Box and Packaging Kit 1 $2.00 $2.00 90%
Materials $98.83 73%
DL (Direct Labor)Certainty of
Labor Grade Activity Hours Rate Extended Cost EstimateAssembler 2 Assemble Unit 0.5 $19.50 $9.75 75%
Test Technican 1 Test and Document 0.5 $24.00 $12.00 60%Shipping Clerk 2 Package & Label 0.2 $18.00 $3.60 90%
DL (Direct Labor) 1.2 $25.35 70%
Overhead AllocationCertainty of
Description Hours Rate Extended Cost EstimateFactory Direct Labor Allocation 1.2 $135.00 $162.00 70%
Target Cost of Goods Sold $286.18 71%
What’s a Total Cost Model?A TCM is a spreadsheet consisting of:
A projected, detailed bill of materials
for the hardware.
Estimated direct labor to make the product.
Estimated indirect costs (overhead) that will be allocated to
the product.The TCM exactly replicates how the product's
total cost of goods sold will be calculated and used in the
organization's enterprise system.
NG3 Communications Module
5
Alphecca Management Resources
Total Cost ModelingBest Practices in Project Management
MaterialsCertainty of
Internal P/N Description Qty Cost Extended Cost Estimate422-654-627 Housing - Series C 200 mm 1 $1.25 $1.25 100%322-652-108 Socket Head Cap Screw - SS - No. 3 6 $0.10 $0.60 100%
125-350-600K USB Port Assembly Kit 1 $1.09 $1.09 100%TBD CE Certified 3V Power Supply 1 $4.75 $4.75 80%TBD Power Supply Adapter 1 $2.00 $2.00 80%
125-200-127K Board Mounting Kit 1 $2.14 $2.14 100%TBD Cellular/WiFi Communications Board 1 $85.00 $85.00 70%TBD Shipping Box and Packaging Kit 1 $2.00 $2.00 90%
Materials $98.83 73%
DL (Direct Labor)Certainty of
Labor Grade Activity Hours Rate Extended Cost EstimateAssembler 2 Assemble Unit 0.5 $19.50 $9.75 75%
Test Technican 1 Test and Document 0.5 $24.00 $12.00 60%Shipping Clerk 2 Package & Label 0.2 $18.00 $3.60 90%
DL (Direct Labor) 1.2 $25.35 70%
Overhead AllocationCertainty of
Description Hours Rate Extended Cost EstimateFactory Direct Labor Allocation 1.2 $135.00 $162.00 70%
Target Cost of Goods Sold $286.18 71%
NG3 Communications Module
Here’s a TCM example.It shows the target cost for an
industrial equipment communications module made in
low volume Line items with part numbers are
existing parts and assemblies. Those marked TBD must be developed.
Direct labor estimates cover assembly, test, and packaging.
Factory overhead is allocated to the final product as a function of direct labor hours.
6
Alphecca Management Resources
Total Cost ModelingBest Practices in Project Management
MaterialsCertainty of
Internal P/N Description Qty Cost Extended Cost Estimate422-654-627 Housing - Series C 200 mm 1 $1.25 $1.25 100%322-652-108 Socket Head Cap Screw - SS - No. 3 6 $0.10 $0.60 100%
125-350-600K USB Port Assembly Kit 1 $1.09 $1.09 100%TBD CE Certified 3V Power Supply 1 $4.75 $4.75 80%TBD Power Supply Adapter 1 $2.00 $2.00 80%
125-200-127K Board Mounting Kit 1 $2.14 $2.14 100%TBD Cellular/WiFi Communications Board 1 $85.00 $85.00 70%TBD Shipping Box and Packaging Kit 1 $2.00 $2.00 90%
Materials $98.83 73%
DL (Direct Labor)Certainty of
Labor Grade Activity Hours Rate Extended Cost EstimateAssembler 2 Assemble Unit 0.5 $19.50 $9.75 75%
Test Technican 1 Test and Document 0.5 $24.00 $12.00 60%Shipping Clerk 2 Package & Label 0.2 $18.00 $3.60 90%
DL (Direct Labor) 1.2 $25.35 70%
Overhead AllocationCertainty of
Description Hours Rate Extended Cost EstimateFactory Direct Labor Allocation 1.2 $135.00 $162.00 70%
Target Cost of Goods Sold $286.18 71%
NG3 Communications Module
What is “Certainty of Estimate”?
CoE (certainty of estimate) measures the accuracy of the projected cost.
100% CoE: the cost is known with certainty.
75% CoE: the value could vary +/- 25%.
CoE values are estimated by subject matter experts during project pre-
planning.
Weighted averages are used to calculate CoE for cost categories and the entire
assembly. 7
Alphecca Management Resources
Total Cost ModelingBest Practices in Project Management
Business Case
Feasibility
Overall Design
Detailed Design
Prototype & Test
Production Validation & Launch
Project Planning
ProjectActivity
A Typical Stage-Gate Process
When should a TCM be prepared?
A Total Cost Model should be prepared before major resources are committed
to the product development project.
In organizations that use stage gate processes, the TCM should be part of
the Feasibility study that develops the Business Case for the project.
8
Alphecca Management Resources
Total Cost ModelingBest Practices in Project Management
It illustrates critical, top-level tasks that must be completed.
It identifies the areas of greatest cost risk.
It generates tasks early in the project plan to mitigate these risks
or pursue parallel development paths.
How does a TCM impact the WBS (Work Breakdown Structure) and
project risk management?
9
Alphecca Management Resources
Total Cost ModelingBest Practices in Project Management10
MaterialsCertainty of
Internal P/N Description Qty Cost Extended Cost Estimate422-654-627 Housing - Series C 200 mm 1 $1.25 $1.25 100%322-652-108 Socket Head Cap Screw - SS - No. 3 6 $0.10 $0.60 100%
125-350-600K USB Port Assembly Kit 1 $1.09 $1.09 100%TBD CE Certified 3V Power Supply 1 $4.75 $4.75 80%TBD Power Supply Adapter 1 $2.00 $2.00 80%
125-200-127K Board Mounting Kit 1 $2.14 $2.14 100%TBD Cellular/WiFi Communications Board 1 $85.00 $85.00 70%TBD Shipping Box and Packaging Kit 1 $2.00 $2.00 90%
Materials $98.83 73%
DL (Direct Labor)Certainty of
Labor Grade Activity Hours Rate Extended Cost EstimateAssembler 2 Assemble Unit 0.5 $19.50 $9.75 75%
Test Technican 1 Test and Document 0.5 $24.00 $12.00 60%Shipping Clerk 2 Package & Label 0.2 $18.00 $3.60 90%
DL (Direct Labor) 1.2 $25.35 70%
Overhead AllocationCertainty of
Description Hours Rate Extended Cost EstimateFactory Direct Labor Allocation 1.2 $135.00 $162.00 70%
Target Cost of Goods Sold $286.18 71%
NG3 Communications Module
Example: How a TCM Identifies Tasks and
RisksIt identifies tasks – for example, the project plan must include steps to specify, procure and test this
power supply.
It highlights important cost risks – with a CoE of only 70%, the new Communications Board could
be as much as $ 25.50 over target cost.
More important, with an only 70%average CoE on labor, there could be as much as .36 hours of
added Direct Labor. In turn, that adds $ 48.60 in overhead allocations!
This increases overall cost by 20%.
Alphecca Management Resources
Total Cost ModelingBest Practices in Project Management11
It identifies tasks – for example, the project plan must include steps to
specify, procure and test this power supply.
It highlights important cost risks – with a CoE of only 70%, the new
Communications Board could be as much as $ 25.50 over target cost.
More important, with an only 70% average CoE on labor, there could be as
much as .36 hours of added Direct Labor. In turn, that adds $ 48.60 in
overhead allocations! This increases overall cost by 20%!
Adds specific tasks to the project plan – assures that every individual item on the bill of material is properly specified, procured and tested.
Highlights Communications Board Risk – project plan modified to pull forward board procurement activities; early engineering tasks added to look at alternate, lower cost approaches to achieve the design objectives.
Highlights Direct Labor Risk – project plan changed to undertake early evaluation and validation of direct labor estimates.
Example: How a TCM Changes the Work Breakdown
Structure
Alphecca Management Resources
Total Cost ModelingBest Practices in Project Management12
How TCM Improves Project Reporting and Control
Update the TCM weekly, using inputs from those assigned ownership of each task.
Have project contributors brief the entire team on important updates and changes.
Summarize the TCM in periodic updates to management, stakeholders and sponsors.
If one set of costs start to drift above target, work
with the team to see if other costs can be reduced.
Project teams using a TCM find themselves focusing on total cost.
In turn, team members take ownership of both their individual
tasks and the entire project.
Alphecca Management Resources
Total Cost ModelingBest Practices in Project Management13
Total Cost Models Deliver Bottom LineProject Management Success
Create realistic, validated product cost estimates before project work begins.
Identify critical project tasks.
Identify hidden cost risks and create effective risk management plans.
Identify, respond & correct cost overruns.
Keep management informed – built team focus and cohesion.
Alphecca Management Resources
Total Cost ModelingBest Practices in Project Management14
For more information on Alphecca Management resources, go to:www.alphecca-management.com