Lead Time: What We Know About It And How It Can Help Forecast Your Projects

Agile DC Lead Time

Embed Size (px)

DESCRIPTION

My talk at AgileDC in Washington on October 20, 2014

Citation preview

Page 1: Agile DC Lead Time

Lead Time:What We Know About ItAnd How It Can Help Forecast Your

Projects

Page 2: Agile DC Lead Time

Alexei Zheglov

Page 3: Agile DC Lead Time

@az1#agiledc

Page 4: Agile DC Lead Time

Goodhart’s Law

Page 5: Agile DC Lead Time

Kanban System Lead Time

DeliveredIdeas AnalysisInputQueue

Ready to

Deliver∞325

Development Test

3

Lead Time

The FirstCommitment

Point

AB

C

Discarded

D

Page 6: Agile DC Lead Time

Ask Not

DeliveredIdeas AnalysisInputQueue

Ready to

Deliver∞325

Development Test

3

Lead Time

AB

C

Discarded

D

Not “how long will it take?”

Page 7: Agile DC Lead Time

Do Ask

DeliveredIdeas AnalysisInputQueue

Ready to

Deliver∞325

Development Test

3

Lead Time

AB

C

Discarded

D

When should we start?

When do we need it?

Page 8: Agile DC Lead Time

Decide

DeliveredIdeas AnalysisInputQueue

Ready to

Deliver∞325

Development Test

3

Lead Time

AB

C

Discarded

DOne event

precedes (leads) another one

by this much

One eventprecedes (leads) another

oneby this much

Page 9: Agile DC Lead Time

Why?

DeliveredIdeas AnalysisInputQueue

Ready to

Deliver∞325

Development Test

3

Lead Time

The FirstCommitment

PointAB

C

Discarded

D

Includes the time the work item

spent as an option

Depends on the transaction

costs (external to the system)

Measures the true delivery

capability

Page 10: Agile DC Lead Time

Customer Lead Time

DeliveredIdeas Activity 1InputQueue

Output Buffer

∞???

Activity 2 Activity 3

?

Customer Lead Time

AB

Kanban system(s) lead time

+time spent in the

unlimited buffer(s)

C

Discarded

D

Page 11: Agile DC Lead Time

(Local) Cycle Time

DeliveredIdeas Activity 1InputQueue

Output Buffer

∞???

Activity 2 Activity 3

?

AB

C

Discarded

D

Cycle time is always local

Always qualify where it is from

and to

Often depends mainly on the size of the local

effort

Page 12: Agile DC Lead Time

Discussion 1: Gaming Metrics

Page 13: Agile DC Lead Time

Readyto Test

Flow Efficiency

F

Q E

C A

J

GD

GYBG

DE NP

P1

AB

Customer Lead Time

Wait Wait WorkWork

IdeasReadyto Dev

5IP

Development Testing

Done3 35

UATReady toDeliver

∞ ∞

Work WaitWork

Official training material, used with permission

Page 14: Agile DC Lead Time

Readyto Test

Flow Efficiency

F

Q E

C A

J

GD

GYBG

DE NP

P1

AB

Customer Lead Time

Wait Wait WorkWork

IdeasReadyto Dev

5IP

Development Testing

Done3 35

UATReady toDeliver

∞ ∞

Work WaitWork

Official training material, used with permission

Work is waiting

Work is still waiting!Multitasking creates

hidden queues!

Page 15: Agile DC Lead Time

Readyto Test

Flow Efficiency

F

Q E

C A

J

GD

GYBG

DE NP

P1

AB

Customer Lead Time

Wait Wait WorkWork

IdeasReadyto Dev

5IP

Development Testing

Done3 35

UATReady toDeliver

∞ ∞

Work WaitWork

Official training material, used with permission

%100time elapsed

time touchefficiencyflow

Page 16: Agile DC Lead Time

Readyto Test

Measuring Flow Efficiency

F

Q E

C A

J

GD

GYBG

DE NP

P1

AB

Customer Lead Time

Wait Wait WorkWork

IdeasReadyto Dev

5IP

Development Testing

Done3 35

UATReady toDeliver

∞ ∞

Work WaitWork

Official training material, used with permission

Timesheets arenot

necessary!

Rough approximations (±5%) are often

sufficient

In Aggregate

Sampling

Page 17: Agile DC Lead Time

Readyto Test

Measuring Flow Efficiency

F

Q E

C A

J

GD

GYBG

DE NP

P1

AB

Customer Lead Time

Wait Wait WorkWork

IdeasReadyto Dev

5IP

Development Testing

Done3 35

UATReady toDeliver

∞ ∞

Work WaitWork

The results are often between 1%

and 5%*

*-Zsolt Fabok, Lean Agile Scotland 2012, LKFR12; Hakan Forss, LKFR13

The result is not limited to the number!

What did you decide to do?

Page 18: Agile DC Lead Time

If the Flow Efficiency Is 5%...

If... Before After Improvement

Hire 10x engineers 100 95.5 +4.7%

The task is three times bigger 100 110 -9.1%

The task is three times smaller 100 96.7 +3.4%

Reduce delays by half 100 52.5 +90%

Page 19: Agile DC Lead Time

Consequences of Low Flow Efficiency

Page 20: Agile DC Lead Time

Goodhart’s Law’s Corollary

Page 21: Agile DC Lead Time

Start Measuring?

Page 22: Agile DC Lead Time

Discussion 2: Measuring Lead Time

Page 23: Agile DC Lead Time

Deterministic approachto a probabilistic process?

probabilistic

!!!

Page 24: Agile DC Lead Time

0-4 5-9 10-14 15-19 20-24 25-29 30-34 35-39 40-44 45-49 50-54 55-59 60-64 65-69 70-74 75-79 80-84 85-89 95-99 100-104

0

2

4

6

8

10

12

14

16

18

20

Example

Page 25: Agile DC Lead Time

0-4 5-9 10-14 15-19 20-24 25-29 30-34 35-39 40-44 45-49 50-54 55-59 60-64 65-69 70-74 75-79 80-84 85-89 95-99 100-104

0

2

4

6

8

10

12

14

16

18

20

Example

Best-fit distribution:Weibull with

shape parameter k=1.62

Page 26: Agile DC Lead Time

Heterogeneous Demand

DeliveredIdeas AnalysisInputQueue

Ready to

Deliver∞325

Development Test

3

AB

C

Discarded

D

E

G

F

H

Demand placed upon our system is differentiatedby type of work and risk

Page 27: Agile DC Lead Time

Drill down by project type

0-410-14

20-2430-34

40-4450-54

60-6470-74

80-8495-99

02468

101214161820

0-4 5-9 10-14

15-19

20-24

25-29

30-34

35-39

40-44

45-49

50-54

55-59

60-64

65-69

70-74

75-79

80-84

85-89

95-99

100-104

0

2

4

6

8

10

12

14

16

18

20

Mixed data from different types of

projects

Page 28: Agile DC Lead Time

4 types, 4 different distributions

0-410-14

20-2430-34

40-4450-54

60-6470-74

80-8495-99

02468

101214161820

0-410-14

20-2430-34

40-4450-54

60-6470-74

80-8495-99

02468

101214161820

5-910-14

15-1920-24

25-2930-34

35-3940-44

45-4950-54

55-5960-64

65-6975-79

80-8485-89

100-1040

2

4

6

8

10

12

14

16

18

0-4 5-9 10-14

15-19

20-24

25-29

40-44

55-59

60-64

65-69

70-74

75-79

95-99

0

1

2

3

4

5

6

...

...

Page 29: Agile DC Lead Time

Delivery Expectations

0-410-14

20-2430-34

40-4450-54

60-6470-74

80-8495-99

02468

101214161820

0-410-14

20-2430-34

40-4450-54

60-6470-74

80-8495-99

02468

101214161820

Shape Average In 98%

1.62

1.23

1.65

3.22

In 85% of cases

30 d

35 d

40 d

56 d

<51

<63

<68

<78

<83

<112*

<110*

<99

Page 30: Agile DC Lead Time

Delivery Expectations

0-410-14

20-2430-34

40-4450-54

60-6470-74

80-8495-99

02468

101214161820

0-410-14

20-2430-34

40-4450-54

60-6470-74

80-8495-99

02468

101214161820

Shape Average In 98%

1.62

1.23

1.65

3.22

In 85% of cases

30 d

35 d

40 d

56 d

<51

<63

<68

<78

<83

<112*

<110*

<99

The averages are insufficient

to specify delivery capabilities!

The average says nothing about variability!

Needed:the average and a high percentile (usually 80-

99%)

Page 31: Agile DC Lead Time

Another Example

0-2.5 2.5-5 5-7.5 7.5-10 10-12.5 12.5-15 15-17.5 25-27.50

2

4

6

8

10

12

Development

0-3 3-6 6-9 9-12 12-15 15-180

2

4

6

8

10

12

14

Support

Shape: 1.16 Shape: 0.71

Page 32: Agile DC Lead Time

Weibull DistributionsOccur Frequently

Operations, support (k<1)

New product development (k>1)

Page 33: Agile DC Lead Time

Weibull DistributionsOccur Frequently

Operations, support (k<1)

New product development (k>1)

The unique signature of your

process

The unique signature of your

process

Page 34: Agile DC Lead Time

Bias

Feedback

How to “Read” a Distribution

Scale

Control

Expectations

Forecast

Page 35: Agile DC Lead Time

Mode: how we rememberthe “typical” delivered work

item.Trouble: it’s a very low

percentile.18-28% common.

Page 36: Agile DC Lead Time

Median: 50% more, 50% less.

Perfect for creatingvery short feedback loops

Page 37: Agile DC Lead Time

Average: we need it for Little’s Law

LeadTime

WIPteDeliveryRa

Little’s Law:handle with care

Page 38: Agile DC Lead Time

The 63% percentile isthe best indicator of

scale

Page 39: Agile DC Lead Time

High percentiles (80th-99th):critical to defining

service-level expectations

High percentiles (80th-99th):critical to defining

service-level expectations

Page 40: Agile DC Lead Time

Statistical process control:Sprint duration in iterative

methods,SLAs in Operations, etc.

Page 41: Agile DC Lead Time

Forecasting Cards

Page 42: Agile DC Lead Time

While I Was Preparing This Presentation, Somebody Sent Me This...

Page 43: Agile DC Lead Time

Discussion 3:Probabilistic or Deterministic?

Page 44: Agile DC Lead Time

TestReady

S

RQ

P

ON

F

A Few Words About Projects…

H

E

C

I

G

D

M

DevReady

5Ongoing

Development Testing

Done3 35

UATReleaseReady

∞ ∞

ProjectScope

Official training material, used with permission

Page 45: Agile DC Lead Time

Delivery Rate

Lead Time

WIP=

Applying Little’s Law

From observed capability

Treat as a fixed variable

Targetto

achieve plan

Calculated based on known lead time

capability & required delivery

rate

Determines staffing level

Official training material, used with permission

Page 46: Agile DC Lead Time

Delivery Rate

Lead Time

WIP=

Applying Little’s Law

From observed capability

Treat as a fixed variable

Targetto

achieve plan

Calculated based on known lead time

capability & required delivery

rate

Determines staffing level

Complicating factors here:

Dark matter“Z-curve effect”

Scope creep

Complicating factors here:Variety of work item types and

risks

Page 47: Agile DC Lead Time

Delivery Rate

Lead Time

WIP=

Applying Little’s Law

From observed capability

Treat as a fixed variable

Targetto

achieve plan

Calculated based on known lead time

capability & required delivery

rate

Determines staffing level

Complicating factors here:

Dark matter“Z-curve effect”

Scope creep

Complicating factors here:Variety of work item types and

risks

Page 48: Agile DC Lead Time

TestReady

S

RQ

P

ON

F

A Few Words About Projects…

H

E

C

I

G

D

M

DevReady

5Ongoing

Development Testing

Done3 35

UATReleaseReady

∞ ∞

ProjectScope

Lead time data andobserved/measured delivery

capabilityat the feature/user story level

are critical to forecasting projects

The project initiation phase is a great time to

builda forecasting model and

feedback loops

Page 49: Agile DC Lead Time

New Kanban Book

Mike Burrows

Page 50: Agile DC Lead Time

Influencers

Troy Magennis Dimitar Bakardzhiev David J Anderson

Dan Vacanti Dave White Frank Vega

Page 51: Agile DC Lead Time

Discussion 4: What Now?

Page 52: Agile DC Lead Time

Alexei Zheglov