What can we do? What can we do? against inefficient budget executionagainst inefficient budget execution

May. 6, 2014

Seongbak WiMinistry of Strategy and Finance, Korea Secondee to Inter-American Development Bank

Page 2: What we can do - Seongbak Wi

2

Ⅰ Raising an issue

Contents

Ⅱ M&E in Korea and strengthening the method

Ⅲ Challenges and remarks

Page 3: What we can do - Seongbak Wi

3

I. Raising an issue

Page 4: What we can do - Seongbak Wi

4

세계경제 전망 (%)

Object of budget

Budget a bridge and no output

No monitoring, no sanction

1. Raising an issue

Ⅰ. Raising an issue

Page 5: What we can do - Seongbak Wi

5

세계경제 전망 (%)

Request a building construction

Cost : US$9 -> US$15 -> US$ 30

1. Raising an issue

Ⅰ. Raising an issue

Page 6: What we can do - Seongbak Wi

6

세계경제 전망 (%)

1. Raising an issue

M&E helps projects implemented as planned and budgeted.

- Line ministries and executing entities have desire to increase the scale

of projects or to use money for personal purpose

For M&E to be effective, we need some strong methods, such as

sanctions against bad executions.

Ⅰ. Raising an issue

Page 7: What we can do - Seongbak Wi

7

Ⅱ. M&E in Korea and strengthening the method

Page 8: What we can do - Seongbak Wi

8

세계경제 전망 (%)

1. External supervision of project Execution

Ⅱ. M&E in Korea and strengthening the method

▶ Project execution is supervised by government

- payment will be done after checking the process and proof.

▶ Administration of Audit and Inspection :

- fire-off, cut in salary, warning, …

▶ Prosecutors ,

- imprisonment, fine

▶ Parliament and people’s monitoring

Page 9: What we can do - Seongbak Wi

9

세계경제 전망 (%)

Ⅱ . M&E in Korea and strengthening the method

▶ Existence of output

vs

▶Feasibility and Efficiency

Page 10: What we can do - Seongbak Wi

10

세계경제 전망 (%)

2. Re-assessment of Feasibil i ty

Ⅱ. . M&E in Korea and strengthening the method

▶ Projects start after feasibility test,

However, their feasibilities can change after the initiation

▶ Re-assess of Feasibility will be done

   - If TPC has increased by more than 20%

      - If new demand forecast is smaller by 30% than the initial one

▶ What if a project appears not to be feasible by reassessment?

Page 11: What we can do - Seongbak Wi

11

세계경제 전망 (%)

2. Re-assessment of Feasibility

Ⅱ. . M&E in Korea and strengthening the method

▶ Sanctions by Re-assessment of Feasibility (1)

   : Example of stopped projects which completed detailed design

        - Janghowon~Jumdong national road(BC=0.24)

        - Bukmyun~Bugok natinal road(BC-0.26)

        - Sungnam~Janghown natinal road(BC-0.83)

        - Imchun~Kanhkyung  local road(BC=43)

        - Boryung new harbour (BC=0.24)

Page 12: What we can do - Seongbak Wi

12

세계경제 전망 (%)

2. Re-assessment of Feasibility

  ▶ Counter action by re-assessment of feasibility (2) : adjustment of total costs

year # of Proj.

Init ial TPC(A)

Reqest(B)

B/A(%)

Adjust(C)

C/A(%)

2010 (36) 8,783 15,829 80.2 13,826 57.4

2011 (22) 10,627 14,264 34.2 13,012 22.4

Ⅱ. . M&E in Korea and strengthening the method

Page 13: What we can do - Seongbak Wi

13

세계경제 전망 (%)

3. Total Project Cost Management

Ⅱ. . M&E in Korea and strengthening the method

▶ MOSF watch the execution of projects to prevent excessive increase in total

cost induced by modification of construction size or design .

▶ TPC rule

- Line ministries should report to MOSF and get approval

- difference between designed project cost and the cost in bidding

- changes in total project cost

Page 14: What we can do - Seongbak Wi

14

세계경제 전망 (%)

3. Total Project Cost Management

Ⅱ . M&E in Korea and strengthening the method

▶ what if an entity violate TPC rule?

- execution of projects without report of changes project cost

▶ Sanctions, introduced in 2000

- Cut in supplementary expenses of projects

- Cut in operational expenditures of the relevant line ministry

- No budgeting the unapproved increment

Page 15: What we can do - Seongbak Wi

15

세계경제 전망 (%)

3. Total Project Cost Management

Ⅱ. . M&E in Korea and strengthening the method

▣ Effect of Introducing Sanctions to TPC Management

TPC requested TPC Adjusted

Before introducing sanctions (1996~1999)

26.4% 11.1%

After introducing sanctions (2000~2003)

4.4% 1.0%

Page 16: What we can do - Seongbak Wi

16

세계경제 전망 (%)

4. Budget Waste Reporting System

▶ Concept : On-line monitoring system open to the public

- operating 309 portal sites : 50 in central governments,

246 in local governments, 13 in state-owned enterprises

- Number of reported projects by people are increasing

(2009) 1,390 -> (2012) 3,474

Ⅱ. . M&E in Korea and strengthening the method

Page 17: What we can do - Seongbak Wi

17

세계경제 전망 (%)

4. Budget Waste Reporting System

▶ Following actions

- MOSF reviews reported issues,

- reassess feasibility, in-depth evaluation

▶ Possible sanctions

- cut in the project cost, cut in the budget, stop the project

.

Ⅱ. . M&E in Korea and strengthening the method

Page 18: What we can do - Seongbak Wi

18

세계경제 전망 (%)

4. Budget Waste Reporting System

Ⅱ. . M&E in Korea and strengthening the method

▶ Case : Reconstruction of national road between Yoju-

Yangpyung

   - Projects : from 2 lanes to 4 lanes,

- reported issue :

another road is being built.

- Reassessment of feasibility

- cut in TPC, straightening the lanes

$117 mil. → $ 60 mil.

Page 19: What we can do - Seongbak Wi

19

세계경제 전망 (%)

5. Performance Evaluation

Ⅱ. . M&E in Korea and strengthening the method

1. Self- evaluation

▶ concept

        - MOSF gives check lists for line ministries to evaluate projects

   - Line ministries assess performance of programs

- Considers for the next year’s budgeting

▶ counteractions

- cut in the next year’s budget in case of poor performance

Page 20: What we can do - Seongbak Wi

20

Linkage between Self Evaluation and Budgeting

Year 

Budget change of Projects(%)

Projects (No.) Poor performance

Projects (No.) Good performance

2008 70 Δ6.8 19 6.7

2009 133 Δ12.5 27 6.32010 132 Δ10.0 33 8.4

Ⅱ. . M&E in Korea and strengthening the method

5. Performance Evaluation

Page 21: What we can do - Seongbak Wi

21

세계경제 전망 (%)

5. Performance Evaluation

Ⅱ. . M&E in Korea and strengthening the method

2. In-depth Evaluation

▶ concept

  - Evaluate appropriateness, effectiveness, sustainability

- in-depth evaluation on some selected projects

▶ counteractions

- Some cases, if some problems were found, are sent to Reassessment of feasibility test

- cut in the project cost, cut in the next year’s budget, stopping the project

Page 22: What we can do - Seongbak Wi

22

Ⅲ. Challenges and remarks

Page 23: What we can do - Seongbak Wi

23

세계경제 전망 (%)

Challenges in M&E

Ⅲ. Challenges and remarks

Difficulty in monitoringTetrapod for breakwater

Page 24: What we can do - Seongbak Wi

24

세계경제 전망 (%)

Challenges in Sanctions

Ⅲ Challenges and remarks

▶ Limitation on effectiveness

- Once a project was launched, it is hard to stop it.

- it is also hard to restore to the initial condition

▶ Reluctance to sanction

- People want to give favor to someone rather than sanction

▶ Is Restriction always desirable?

Page 25: What we can do - Seongbak Wi

25

세계경제 전망 (%)

Concluding Remarks

Ⅲ. Challenges and remarks

▶ Effective M&E is as important as planning and budgeting.

- to secure a project to be realized as planned

▶ M&E requires counteractions to be effective

- Strong counteractions, sanctions, will help feedback and

launching a new efficient project