Upload
support-for-improvement-in-governance-and-management-sigma-oecd
View
84
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Presentation given by Erkan Ozdemir of the Turkey PPA at the 7th Regional Public Procurement Conference held in Vlora on 9-10 Sept 2014.
Citation preview
THE REPUBLIC OF TURKEY
1
Review and Remedies Procedures in
Turkey
7th IPA Regional Public Procurement Conference
9 – 10 September 2014 Vlora, Albania
ERKAN OZDEMIR
Public Procurement Specialist
Regulation Department
Public Procurement Authority [email protected]
Who Can File a Complaint?
The Turkish legislative framework on remedies is provided
for by PPL No.4734 and its complementary secondary
legislation. The PPL contains detailed rules for review and
complaint procedures.
Who can file a complaint?
The PPL limited locus standi to actual or potential
tenderers and candidates who claim that they have
suffered a loss of right or damage or are likely to suffer a
loss of right or damage due to unlawful procedures or
actions within the process of the tender.
(In order to become a potential tenderer, tender or pre-qualification documents
must be purchased)
2
Stages of Complaint Review System in
Turkey
The PPL establishes a three-tier system for reviewing
complaints lodged by disgruntled economic operators.
3
Complaint
application to the
Contracting
Authority In the first stage a complaint
must be submitted to the
contracting authority itself
within 10 days (5 days in the
case of emergency contracts)
running from the date when the
decision being challenged was
sent or published or in any
event ten days running from
the notification of the
contracting authority’s decision.
Appeal application
to the Public
Procurement
Authority A complainant who is
dissatisfied with the
decision of the contracting
authority may, as a second
step, appeal this decision
to the PPA within 10 days.
Appeal to the
Administrative
Courts The final decision on
the appeal made by the
PPA is then subject to
the jurisdiction of the
administrative courts
within a period of 60
days.
Standstill Period and Automatic
Suspensison
4
In December 2008 an extensive amendment to the PPL
was adopted, notably to strengthen the review procedure.
Two important steps have been taken in order to ensure
that the Turkish review system meets the requirements of
EU law.
1- The minumum standstill period between notification of the
award decision and conclusion of the contract and,
2- Automatic suspension of the possibility to conclude the
contract upon complaint,
were introduced to the PPL through this amendment.
Standstill Period and Automatic
Suspension
5
Pursuant to Art.41 of the PPL the contract may not be
signed,
Unless ten days have passed in general,
and unless five days have passed in the case of
emergency contracts specified in article 21(b) and (c)
of the PPL.
following the notification of all the tenderers about the
tender result.
Standstill Period and Automatic
Suspensison
6
Furthermore, where an economic operator challenges the
tender result before the contracting authority within the
designated period (10 or 5 days), the suspension of the
conclusion of the contract will continue till the notification
date of the authority’s decision and where sequential
appeal is made to the PPA within ten days following the
decision by the contracting authority, suspension will
continue till the decision on appeal has been taken by the
PPA.
7
Ineffectiveness
With regard to the concept of ineffectiveness, there is no explicit
provision in the PPL.
However, Art.56 of the PPL provides that conclusion of the
contract without complying with the standstill periods and
procedures set out in the PPL does not constitute an obstacle
for the PPA to review the application and take one of the
decisions stated in Art.54 of the PPL. (i.e. setting aside,
corrective action and rejection of the application).
8
Ineffectiveness
It is established practice that if the failure to apply the
standstill period is combined with an infringement of the
substantive rules, the PPA can set aside the award decision
which ultimately results in the termination of the concluded
contract by the contracting authority itself, as the legal basis
of the contract has been removed.
Turkish system on ineffectiveness is partially in line with the
Art.2d of the Remedies Directive, which states that under
certain cases specified therein a signed contract must be
considered ineffective by a review body or its
ineffectiveness must be the result of the decision of such a
review body.
9
Alternative Penealties
Although the sanction of ineffectiveness implicitly exists in
the Turkish remedies system, unfortunately the PPL does
not provide any provisions on alternative penalties which
review bodies (PPA or administrative courts) may impose on
contracting authorities such as the shortening of the
duration of the contract and/or the payment of a fine.
In this respect Turkish remedies system seems to conflict
with the Remedies Directive and so further legaslative
initiatives are required to meet the requirements of the Art
2e of the Remedies Directive.
Specific Remedies 10
Upon application the PPA shall take the final decision
within 20 days in general,
within 10 working days for the appeals against tenders
conducted in urgent cases and against actions taken by
the contracting authority to cancel the tender upon a
complaint or appeal.
Specific Remedies 11
The PPL provides two specific remedies to be made available to
disappointed economic operators in actions against contracting
authorities, as follows:
i.the corrective action ii.the annulment of the procurement
proceedings
Therefore the PPL gives one of the powers to the PPA specified in
Art.2(1) (b) of the Remedies Directive. (i.e. setting aside of contracting
decisions)
in cases where the
infringement may be
remedied through
correction and where
it is not necessary to
interrupt the
procurement process
where the infringement would
constitute an obstacle for the
continuation of the tender proceeding
and which cannot be remedied by
taking corrective measures
Specific Remedies 12
However, there is no provision for interim measures and
compensation for damages in the PPL.
As indicated above, in cases of the initiation of review
proceedings against any contracting decisions, the
contract cannot be concluded until the PPA has taken its
decision.
Since contracting authorities cannot conclude the contract
before the PPA has made a decision on the merits of the
case, this automatic suspension of the possibility to
conclude the contract seems to obviate the existence of
interim measures with regard to procurement process
within the Turkish review system.
Damages 13
There is no provision in the PPL regarding the award of
damages; the PPA is not given the power to grant compensation
for damages.
Nonetheless damages can always be claimed before the
administrative courts pursuant to Art.125 of the Turkish
Constitution and Art.2 of the Procedure of Administrative Justice
Law.
Since the Remedies Directive allows the Member States latitude
to assign different tasks concerning the remedy procedure to
separate bodies responsible for different aspects of the review
procedure, the fact that under the Turkish review system the
award of damages to persons harmed by an infringement is a
matter for the administrative courts should not be seen to
contravene the Remedies Directive.
Main Figures on Complaint
applications to PPA in 2013 14
Procurement
type
No.of
complaints
No.of
Procurements*
Share in Total
Goods 854 45.781 1,87
Services 3.034 25.227 4,78
Works 1.205 45.921 6,66
Total 5093 116.929 4,36
*Exceptions are not included.
Further Developments 15
Turkey, as an EU candidate country, needs to bring its national review system on public procurement to full compliance with EU legislation before accession. In the last decade, Turkey has taken some important steps towards this objective.
Although these developments have enhanced its compliance with the Remedies Directive, there are still some steps that need to be taken to ensure that the Turkish review system meets the requirements of EU law. For this purpose, further legislative initiatives will be introduced before accession.
16
THANK YOU FOR YOUR
ATTENTION