S2S Cycleway & Footway Interim Works - Bull Road to Causeway Road
North Central Area Committee Meeting 18th May 2015
S2S Cycleway & Footway Interim Works
Proposed Works
Western Carriageway (St. Anne’s Park/Properties side) • Kerb realignment and footpath works on the western side.
Eastern Carriageway (Seaward Side) • 2km of cycle and pedestrians facilities on the eastern side of the existing carriageway (4.0m
wide two-way cycle track and 2m wide concrete footpath) .
• Improved flood defences along route and two new sections of retaining wall and works to improve existing seawall.
• Proposed services include improved drainage system, watermain and public lighting supplies.
Overall • Streetscape improvement – all new road surface, footpaths, traffic signals and public lighting
throughout the scheme.
• Estimated Program Duration: 16 months.
• Missing link in an overall 8km cycle track around North Dublin Bay.
• DCC received Part 8 Planning Approval for an Interim scheme in May 2013.
Proposed Works Watermill Road to Mount Prospect Avenue
• Site compound located within St. Annes Park Car Park– Car park currently closed.
• Works commencing at northern end of scheme in May 2015.
• Works zones will move in a southerly direction.
• Western side of carriageway works commencing first with little disruption.
• Retaining Wall/Eastern Carriageway Works more disruptive in nature.
New Retaining Wall – June/July/August 2015
Western Footpath Works May/June/July 2015
East Carriageway Works July to Oct 2015
Proposed Works
Mount Prospect Avenue to Wooden Bridge
• Western footpath works will continue south in sections (150m approx.) with two way traffic and access to properties maintained.
• Retaining Wall/Eastern Carriageway Works more disruptive in nature.
New Retaining Wall – September/October 2015
Western Footpath Works August to December 2015
East Carriageway Works Nov 2015 – May 2016
Traffic Management
Western Footpath
Western Footpath – Works on the western footpath will commence just south of the site compound.
– Works zones will be in sections of approximately 150m.
– Each section will take approximately 3 weeks to complete.
– 2 way traffic will be maintained through this section with a 6m carriageway.
Eastern Footpath / Seaward Side Retaining Wall & Utilities – Works will then continue south along the existing seaward wall to construct the
retaining wall and utilities. – The Contractor is currently proposing a single lane traffic shuttle system (Stop/Go) for
this section of the Works. – The footpath works on the western side will continue further south in parallel with these
works so the works on the opposite side will not clash. – Currently reviewing options to reduce extent of single lane working.
Traffic Management
East Carriageway
S2S Cycleway & Footway Interim Works
Parking Provisions
Dollymount Ave – Mt. Prospect Ave: Removal of 6 Spaces
Dollymount Park - Dollymount Ave: Additional 8 Spaces
Seafield Rd East - Dollymount Park: Additional 3 Spaces
Kincora Road - Seafield Rd East : Removal of 6 Spaces