Nelson D. NelsonPublic Works DirectorLocal Project UpdatesCity Council MeetingApril 20, 2016
#
#
Southwest Quadrant of Grand Boulevard Waterline Project Phase 1Construction continues through May
#
2015-2016 CDBG Sidewalk ImprovementsConstruction continues through June
#
7
SR-91 CLOSURES2-WEEK LOOK AHEAD AT A GLANCE
#
Westbound SR-91: 2-Week Look Ahead8
#
Eastbound SR-91: 2-Week Look Ahead9
#
#
Complete by end of May of MaySubstantially
#
Substantially Complete by end of July
#
Complete by end of JulySubstantially
#Anne Mayer- RCTCsr91project.info877-770-9191@sr91project [email protected]
#Multiple ways to stay connected with the project; if you have a question or request, please let us know so that we can take appropriate next steps to address or mitigate items.11