10
1 1 LOCAL PROJECT UPDATES CITY COUNCIL MEETING Nelson D. Nelson Public Works Director March 16, 2016

Local projects update, 03 16-2016

Embed Size (px)

Citation preview

Page 1: Local projects update, 03 16-2016

11

LOCAL PROJECT UPDATESCITY COUNCIL MEETING

Nelson D. NelsonPublic Works Director

March 16, 2016

Page 2: Local projects update, 03 16-2016

2GREEN RIVER WIDENING PROJECT

• Paving complete – striping next week

• New traffic signal at Palisades• Landscaping medians &

parkway• Anticipate completion end of

March

Page 3: Local projects update, 03 16-2016

3FOOTHILL PARKWAY WIDENING W/O I-15

• SCE and Gas utilities to be relocated • Traffic signal at Bedford Canyon to be relocated• Traffic switched to other side of median to complete construction of

south side• Anticipate completion in June

Page 4: Local projects update, 03 16-2016

4MAPLE STREET BRIDGE WORK DETOUR

NORTH BOUND ONLY THROUGH JULY

Only 2 northbound lanes over the Maple

Street bridge

Southbound travel must use detour

Page 5: Local projects update, 03 16-2016

5SERFAS CLUB ROADWAY LOWERING SOUTH SIDE

55-HOUR CLOSURE, MARCH 18 - 21

Page 6: Local projects update, 03 16-2016

6SERFAS CLUB ROADWAY LOWERING MIDDLE

9-DAY CLOSURE, MARCH 25 – APRIL 4

Page 7: Local projects update, 03 16-2016

7

Second Street will be open, but with occasional flagging operation

BUENA VISTA BRIDGE WORK

2-DAY CLOSURE DURING SPRING BREAK (MARCH 25 – APRIL 4)

Page 8: Local projects update, 03 16-2016

8SHERMAN AVENUE CLOSED 7AM TO 9PM THROUGH MARCH 25

Page 9: Local projects update, 03 16-2016

9POMONA ROAD ONE-LANE WB ONLY DURING DAY MARCH 21 THROUGH MAY

15CLOSED NIGHTLY 10 PM TO 4 AM

Page 10: Local projects update, 03 16-2016

10DAVID THOMAS - RCTC

sr91project.info

877-770-9191

@sr91project

sr91project.com

[email protected]