Slide 1 SELECT COMMITTEE ON LAND AND ENVIRONMENTAL AFFAIRS REPORT ON OVERSIGHT VISITS TO EASTERN CAPE, KWAZULU-NATAL, LIMPOPO AND NORTH WEST Date: 13 November 2012 Venue: Parliament, Cape Town

Land & Environmental Claims Report

Embed Size (px)

Citation preview

Page 1: Land & Environmental Claims Report

Slide 1

SELECT COMMITTEE ON LAND AND ENVIRONMENTAL AFFAIRS

REPORT ON OVERSIGHT VISITS TO EASTERN CAPE, KWAZULU-NATAL, LIMPOPO AND NORTH WEST

Date: 13 November 2012Venue: Parliament, Cape Town

Page 2: Land & Environmental Claims Report

Slide 2

KwaZulu Natal (Umzimkhulu Local Municipality) and Eastern Cape (Port St Johns, Nyandeni and Mnquma Local Municipalities),

dated

Page 3: Land & Environmental Claims Report

Slide 3

KwaZulu Natal: Umzimkhulu Local Municipality Land Claims report

• The national Department of Rural Development and Land Reform must provide the latest statistics with regards to the outstanding land claims and the reasons for the delays in processing the land claims in the Sisonke District and Umzimkhulu local municipality.

• Detailed spreadsheet provided

Page 4: Land & Environmental Claims Report

Slide 4

Eastern Cape: OR Tambo District and Mnquma local municipality.

Land Claims Report • The national Department of Rural Development and Land Reform must

provide the latest statistics with regards to the outstanding land claims and the reasons for the delays in processing the land claims in the OR Tambo District and Mnquma local municipality.

• Detailed spreadsheet provided

Page 5: Land & Environmental Claims Report

Slide 5

Eastern Cape : OR Tambo District and Port St Johns local municipality. Land Claims Report

• The national Department of Rural Development and Land Reform must provide the latest statistics with regards to the outstanding land claims and the reasons for the delays in processing the land claims in the OR Tambo District and Port St Johns local municipality.

• Detailed spreadsheet provided

Page 6: Land & Environmental Claims Report

Slide 6

Eastern Cape cont…

• The national Department of Rural Development and Land Reform must provide a report on the progress made on the Caguba, Mkhanzini, Majola land claims, in the Port St Johns area.

• Caguba claim:Development grants (R17, 5 m) are in the process of being transferred to an account to be established by the Department. The target period for transferring was the first quarter of the 2012/13 FY.

• The transfer of funds will be done in trenches in line with the approved business plan.

• Majola claim: Challenges are related to the non-claimant group that does not recognise the registered CPA. CTH Attorneys are facilitating the appointment of a Mediator and the appointment process should be finalised by end March. About 1500 non claimants claim that they have user rights on the 698 hectares of the settled claim, which then complicates implementation of planned development. Mediation intervention should also address this challenge.

Page 7: Land & Environmental Claims Report

Slide 7

Eastern Cape cont…• Mkhanzini Claim• The department convened a meeting with the CPA and the traditional

leaders regarding financial compensation and land for restoration. An agreement has since been reached between parties that the settlement of the claim will be phased. The first phase will be financial compensation with the second phase being the land restoration.

• • The Section 42 D documents for financial compensation (phase one) was

approved at the Quality Control Committee and are en route to the Minister for approval.

• The office is currently negotiating with the owner of the land identified for restoration, and the outcome of the negotiation will lead to a submission to Quality Control Committee on 22 November 2012.

Page 8: Land & Environmental Claims Report

Slide 8

Additional Interventions in Mnquma Local

Municipality• Erf 1 Ngqamakhwe: Boundary disputes between Mthwaku and Sokapase who have

conflicting claims in the same parcel. A valuer has been requested to identify the boundary and conduct valuation. The report will be submitted in end March.

• R4, 4 million funding to Silulwazi broiler Project for recapitalization and development in the 2012/13 financial year.

• Aspire / Amathole DM is assisting with the development of Local Spatial Development Framework for the urban / rural nodes of Mnquma LM. Reprioritisation was done and Mbhashe LM is being assisted with the revitalisation of urban / rural nodes.

• Animal and Veld Management programme is being implemented (Fencing of arable land in Mhlahlane village – 80km (R5.2 million)

Page 9: Land & Environmental Claims Report

Slide 9

SELECT COMMITTEE ON LAND AND ENVIRONMENTAL AFFAIRS ON THE OVERSIGHT VISIT TO THE BOJANALA DISTRICT AND MADIBENG LOCAL MUNICIPALITIES IN THE NORTH WEST PROVINCE, DATED 25 OCTOBER 2011

Page 10: Land & Environmental Claims Report

Slide 10

North West: Infrastructure ProjectsRecommendation Response

The Department of Rural Development and Land Reform to provide a progress report on the VIP toilet project within three months of adoption of the report.

Sanitation projects for 300 pit latrines , contracts is on hold as DRDLR is still in discussion with DoHS.

The Department of Rural Development to provide a report on the completion of the water reservoir, within one month of adoption of the report.

Water connection and construction of water tank completed, 1.5m reservoir erected and awaiting confirmation of connection with Magalies water before PPC open line to test reservoir.

Page 11: Land & Environmental Claims Report

Slide 11

Additional Interventions: Moses Kotane (Matlametlong,Mokgalwaneng, Disake)

• 30 High mast lights installed and awaiting Eskom to open power line

• 10 Trainers identified to do further training which will benefit 50 learners through the APPDP.

• 7 Cooperatives registered.• In collaboration with the Department of Agriculture, acquired

8 top quality bulls.• 25 Household gardens established through the APPDP

training.

Page 12: Land & Environmental Claims Report

Slide 12

OVERSIGHT VISIT TO THE INTSIKA YETHU MUNICIPALITY, CHRIS HANI DISTRICT, EASTERN CAPE, DATED 13 MAY 2010

Page 13: Land & Environmental Claims Report

Slide 13

EC: Irrigation Schemes

The Department of Agriculture, Forestry and Fisheries and Provincial Departments of Agriculture and Rural Development to provide the Committee with detailed information as to what funding and support has been rendered to the project thus far, including future funding allocations (irrigation schemes, recap and RID projects in this area)•Response:

Page 14: Land & Environmental Claims Report

Slide 14

Intsika Yethu Municipality, Chris Hani District, Eastern Cape

Project Expenditure Recorded

NCORA IRRIGATION SCHEMEDate Amounts Transferred09/12.2011 12 000 000.0028/08/2012 8 100 000.00  20 100 000.00QAMATA IRRIGATION SCHEMEDate Amounts Transferred26/03/2012 5 500 000.0001/08/2012 5 000 000.00  10 500 000.00QAMATA IRRIGATION SCHEME  Date Amounts transferred28/08/2012 3 300 000  3 300 000.00

Page 15: Land & Environmental Claims Report

Slide 15

Intsika Yethu Municipality, Chris Hani District, Eastern Cape

Ncorha• 1021 cows were delivered to the dairy in the period between July

and August 2012. Almost 657 cows are being milked currently. The current market available for selling milk from Ncora is Coega Dairy.

• Installation of feed-mill has been completed and is sufficient to feed the number of cows present in the dairy farm.

• Renovation and installation of Silos have been completed, the weigh bridge has been installed and only the computers are awaiting installation.

• Installation of 21000 L bulk milk tank has been completed. • Planting of 200 ha’s of Maize (100 ha for silage and 100ha for

grain) was completed and harvested. Planting of ryegrass and clover in 300ha’s experienced delays but ultimately completed.

• Repairs on Fencing and installation of irrigation infrastructure in 200 hectares have been completed.

Page 16: Land & Environmental Claims Report

Slide 16

Intsika Yethu Municipality, Chris Hani District, Eastern Cape

Ncorha

• A total of 728 ha of Maize were planted in Qumaco area of Ncora irrigation scheme, the area covered includes six villages, which are Ndenxe, Maqomeni, Sigangeni, Thaleni, Kwa Dlomo and Matafeni.

• Harvesting of maize started on 22 July 2012 and was completed end August 2012. Pre-harvest yield estimates was 3.5 tons per hectare and was done in early June 2012. The actual average yield is 1.7 tons per hectare and there were some challenges that led to the decrease and these are as follows:

Page 17: Land & Environmental Claims Report

Slide 17

Intsika Yethu Municipality, Chris Hani District, Eastern Cape

Qamata• Village cluster development • - Chris Hani Cooperative centre completed the situation analysis

and skills audit work in the ;• Infrastructure Development • - Fencing of the fields: The project is in progress as the contractor

established site;• - De-bushing and canal clearing: The contractor has turned-down

the appointment, this is due to the cost escalations. The second recommended contractor is being approached although its cost estimates were fairly higher than the estimated cost.

• - Flood irrigation infrastructure rehabilitation- The rehabilitation mainly relies completion of the de-bushing and canal clearing as there needs to be an assessment of the amount of damage and costing thereof.

Page 18: Land & Environmental Claims Report

Slide 18

Intsika Yethu Municipality, Chris Hani District, Eastern Cape

QamataRenovate Office Block • Office renovations: The contractor has started work;Upgrade Gravel Access Road from R 61 to Section 1A • o A geotechnical engineer has been appointed to investigate

the surrounding borrow pits for suitable road making material. This report has been completed and MBB is in the process of establishing whether the borrow pit is registered with the Department of Minerals and Energy.

Milling and Mixing Plant • The project has not commenced yet, it is deemed prudent

that a commercial partner must be secured first in order to develop plans sequentially.

Page 19: Land & Environmental Claims Report

Slide 19

Intsika Yethu Municipality, Chris Hani District, Eastern Cape

QamataCropping Plans from Sept 2012 • Partnership has been secured where there will be joint funding

for the cropping programme this coming summer season. This partnership will see the provincial DRDAR will be funding some of the inputs and the funding from DRDLR will fund mechanisation costs and any shortfall in inputs.

• The targeted priority crops are: • - Dry Maize in 415 ha • - Green Mealies in 60 ha • - Cabbage in 50 ha • - and Butternut in 20 ha • DRDAR are in a process of procuring fertilizer and other inputs

for delivery by mid September 2012.

Page 20: Land & Environmental Claims Report

Slide 20

Intsika Yethu Municipality, Chris Hani District, Eastern Cape

BilatyeCropping Programme • A total of 120 ha has been earmarked for planting of maize under

irrigation. Procurement for production of inputs is underway. • It is expected that the Municipality will settle the Eskom debt and

continue to pay electricity costs until harvesting time. • Village Cluster Development • Chris Hani Co-operative Centre has undertaken social facilitation and

covered the key areas mentioned :o Situation analysis o Skills audit

Page 21: Land & Environmental Claims Report

Slide 21

Intsika Yethu Municipality, Chris Hani District, Eastern Cape

Recommendation Response

The issue of individuals securing funds to the amount of R9.9 million in the name of Ncora Irrigation Scheme without proper consultation and information provided to project members must be investigated at a provincial level.

National Dept of Agriculture to deal with this

Page 22: Land & Environmental Claims Report

Slide 22

OVERSIGHT VISIT TO MUYEXE; GIYANI; LIMPOPO

Page 23: Land & Environmental Claims Report

Slide 23

Limpopo: MuyexeRecommendations Response

The Department of Rural Development and Land Reform to hold aco-ordination and planning session with the Councilors if the Districtand the Local Municipalities on the status of the projects in theMuyexe area.

There is an improvement in the intergovernmental relations, as showcased by a meeting which was held at Muyexe on the 10th October 2012. At this meeting almost all affected departments were present and many new initiatives including Dairy and abattoir cooperatives were also discussed

The Department of Rural Development and Land Reform and theDepartment of Agriculture, Forestry and Fisheries to provide acomplete report on the loan that was procured for the MacenaWoman's Project.

Report presented separately on the project

Page 24: Land & Environmental Claims Report

Slide 24

Limpopo: MuyexeRecommendation ResponseContractor who was appointed to build the clinic at Muyexe abandoned the project and that the delivery of medical supplies is slow and delayed.

The contractor who abandoned the project was subcontracted by Tsusanani Training Centre, who are the main contractor. Differences led to termination of the services of the subcontractor.

The shortage of medicines was caused by the fact that the storage facility was initially not capable to store large quantities. This situation has been dealt with accordingly because one room has been allocated for this purpose

With regard to the non availability of the Antiretroviral medication, it was indicated that Muyexe clinic is not accredited to provide this type of medication due to its size and it will start to dispense such medication after its completion

Page 25: Land & Environmental Claims Report

Slide 25

Additional Interventions in Giyani

• Boreholes: the projects currently underway in Muyexe are Communal drinking points

• A contractor has been appointed to construct cattle drinking troughs and reservoir with pipe works to support farmers in Muyexe

• Boreholes: we have borehole projects in three villages (Thomo, Gon’on’o and Dingamanzi), the scope of work consist of drilling of borehole, pump house and a reservoir (all on tender stage)

Page 26: Land & Environmental Claims Report

Slide 26

Thank you Thank you