NEW YORK CITY ECONOMIC DEVELOPMENT CORPORATION CITYWIDE FERRY SERVICE March 2015

Ferryservicesummary

Embed Size (px)

Citation preview

NEW YORK CITY ECONOMIC DEVELOPMENT CORPORATION

CITYWIDE FERRY SERVICE

March 2015

NEW YORK CITY ECONOMIC DEVELOPMENT CORPORATION 2

EDC has built experience in ferry operations and planning since 2008

● 2008 First Rockaway Pilot

● 2010 Citywide Ferry Study ● 2011 East River Ferry Pilot ● 2012 Rockaway Emergency Service ● 2013 Citywide Ferry Study (Preliminary) ● 2014 Begin ERF Long-term Operations ● 2014 Finalize ferry study and refine for implementation

● Feb 3, 2015 – Mayor announces Citywide Ferries by 2017

How we got here

NEW YORK CITY ECONOMIC DEVELOPMENT CORPORATION

Project Overview

3

� Proposed Ferry Network – 20 Landings (9 new) – 6 Routes (5 new routes + 1 existing route) – $2.75 fare, same as subway/bus fare – Expected to serve 4.6M trips/year – 550,000 people live near proposed landings

� Landing Designs – Primarily spud barges with gangway access – Minimal upland improvements in first iteration

� Funding

– $55M in City capital for floats, gangways and capital infrastructure needs. – City and EDC working together to budget for operating subsidies

� Governance

– Staten Island Ferry remains with DOT – ERF and new routes are EDC managed, using private ferry operators – Landing maintenance, operations to be established through agreements with DOT

NEW YORK CITY ECONOMIC DEVELOPMENT CORPORATION

Proposed Ferry Network

4

New landings:

Rockaway

Bay Ridge

Red Hook

Astoria

Long Island City-North

Roosevelt Island

Soundview

E 62nd Street

Stuyvesant Cove

Grand

Existing Landings:

Wall St/Pier 11

Fulton/DUMBO

Schaefer Landing

North Williamsburg

Greenpoint

*Hunters Point South

E 34th Street

*E 90th Street

*Brooklyn Army Terminal

*Atlantic Ave / Pier 6

Governors Island [seasonal]

*Upgrades proposed

NEW YORK CITY ECONOMIC DEVELOPMENT CORPORATION

Project Goals

1. Create a safe ferry system

2. Launch three routes by 2017 ( Rockaway, Astoria, and South Brooklyn)

3. Launch remaining two routes by 2018 (Lower East Side, Soundview)

4. Ensure continuity of the East River Ferry service

5. Create a unified system focused on customer experience