EGLINTON CROSSTOWNEglinton-Mount Pleasant Construction Liaison CommitteeJune 13, 2017
2
Agenda
• Eglinton Station Update
• Mount Pleasant Station Update
3
Eglinton Station Updates
Complete
Demolition of the Salvation Army Community Church
Demolition of the abandoned TTC bus depot
Spring/Summer 2017
• Utility relocation works are ongoing at the Yonge-Eglinton intersection
– Water main and sanitary sewer works
• Toronto Hydro relocation is upcoming in June/July – Duplex to Hillsdale to Yonge
• Shoring is underway at the Salvation Army and TTC bus depot sites
– Two rigs are currently in operation; a third drill rig will be in operation later in June
4
Eglinton Station Shoring Stage 1
5
Construction Progress Picture
Shoring at the bus depot site
Shoring at the Salvation Army site
6
Construction Progress Picture
7
Construction Progress Picture
8
Accessible (Main) Entrance
Eglinton Station Aerial Rendering
Mount Pleasant Station Construction Update
Complete
Demolition at 280 and 280 Eglinton Ave E to make way for the Secondary Entrance
Demolition at 256-58 Eglinton Ave E to make way for the Main Entrance
Installation of geotechnical monitoring equipment
Long-term closure of Rawlinson Ave for site trailers and laydown area
Shoring at the Main Entrance
Installation of temporary traffic signals
Spring/Summer 2017
• Continue piling at the Secondary Entrance
• Continue hydro utilities relocation
• Piling in the roadway, beginning on the northwest side of Eglinton Ave E
Mount Pleasant Station Lookahead
Year Quarter Construction ActivityApprox.
Duration
2017Q2-Q4
(April-December)
• Implement traffic staging on the north side of
Eglinton Ave E, and commence utilities relocation and
piling
• Implement traffic staging on the south side of
Eglinton Ave E, continue utilities relocation and piling
• 2 months
• 4 months
2018
Q1-Q2
(January-June)
• Shallow excavation and roof slab construction on the
south side of Eglinton Ave E
• 6 months
Q3-Q4
(July-December)
• Shallow excavation and roof slab construction on the
north side Eglinton Ave E
• 6 months
Current Construction Staging
Began May 31 for approximately two (2) months
Mount Pleasant Station Concept Aerial View
Main Entrance
Secondary Entrance
*60% rendering
Mount Pleasant Station Main Entrance
*60% rendering
Mount Pleasant Station Secondary Entrance
*60% rendering
Mount Pleasant Station Construction Progress
15
DRILL MOVE
PILE INSTALLTION
Mount Pleasant Station Construction Progress
16
TEMPORARY POLE
INSTALLATION
STAGE 1 TRAFFIC SETUP
Mount Pleasant Station Construction Progress
17As of May 2017