17
EGLINTON CROSSTOWN Eglinton-Mount Pleasant Construction Liaison Committee June 13, 2017

Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

Embed Size (px)

Citation preview

Page 1: Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

EGLINTON CROSSTOWNEglinton-Mount Pleasant Construction Liaison CommitteeJune 13, 2017

Page 2: Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

2

Agenda

• Eglinton Station Update

• Mount Pleasant Station Update

Page 3: Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

3

Eglinton Station Updates

Complete

Demolition of the Salvation Army Community Church

Demolition of the abandoned TTC bus depot

Spring/Summer 2017

• Utility relocation works are ongoing at the Yonge-Eglinton intersection

– Water main and sanitary sewer works

• Toronto Hydro relocation is upcoming in June/July – Duplex to Hillsdale to Yonge

• Shoring is underway at the Salvation Army and TTC bus depot sites

– Two rigs are currently in operation; a third drill rig will be in operation later in June

Page 4: Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

4

Eglinton Station Shoring Stage 1

Page 5: Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

5

Construction Progress Picture

Shoring at the bus depot site

Shoring at the Salvation Army site

Page 6: Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

6

Construction Progress Picture

Page 7: Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

7

Construction Progress Picture

Page 8: Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

8

Accessible (Main) Entrance

Eglinton Station Aerial Rendering

Page 9: Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

Mount Pleasant Station Construction Update

Complete

Demolition at 280 and 280 Eglinton Ave E to make way for the Secondary Entrance

Demolition at 256-58 Eglinton Ave E to make way for the Main Entrance

Installation of geotechnical monitoring equipment

Long-term closure of Rawlinson Ave for site trailers and laydown area

Shoring at the Main Entrance

Installation of temporary traffic signals

Spring/Summer 2017

• Continue piling at the Secondary Entrance

• Continue hydro utilities relocation

• Piling in the roadway, beginning on the northwest side of Eglinton Ave E

Page 10: Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

Mount Pleasant Station Lookahead

Year Quarter Construction ActivityApprox.

Duration

2017Q2-Q4

(April-December)

• Implement traffic staging on the north side of

Eglinton Ave E, and commence utilities relocation and

piling

• Implement traffic staging on the south side of

Eglinton Ave E, continue utilities relocation and piling

• 2 months

• 4 months

2018

Q1-Q2

(January-June)

• Shallow excavation and roof slab construction on the

south side of Eglinton Ave E

• 6 months

Q3-Q4

(July-December)

• Shallow excavation and roof slab construction on the

north side Eglinton Ave E

• 6 months

Page 11: Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

Current Construction Staging

Began May 31 for approximately two (2) months

Page 12: Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

Mount Pleasant Station Concept Aerial View

Main Entrance

Secondary Entrance

*60% rendering

Page 13: Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

Mount Pleasant Station Main Entrance

*60% rendering

Page 14: Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

Mount Pleasant Station Secondary Entrance

*60% rendering

Page 15: Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

Mount Pleasant Station Construction Progress

15

DRILL MOVE

PILE INSTALLTION

Page 16: Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

Mount Pleasant Station Construction Progress

16

TEMPORARY POLE

INSTALLATION

STAGE 1 TRAFFIC SETUP

Page 17: Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017

Mount Pleasant Station Construction Progress

17As of May 2017