City of College Station
City of College Station
2016 Bond Sale and Refunding
City of College Station
Outline
Competitive Sale
2016 Bond Issue
First Southwest Presentation
Staff Recommendations
City of College Station
Competitive Sale
• Competitive Sale Underwriters are chosen through a bid process Maximum bond par parameters are set Maximum interest rate and maturities are set for
new money Must have at least a 5% net present value savings
on refunded bond Mayor, City Manager or Assistant City Manager is
given authority to execute sale through adoption of Bond Ordinance
City of College Station
2016 Bond Sale (new money)
General Obligation Bonds
• General Government Project– Library Expansion $ 4,185,000
City of College Station
2016 Bond Sale (new money)
General Obligation Bonds
• Street Projects– Lakeway Extension $4,000,000– Traffic Signals $600,000Streets Total $ 4,600,000
City of College Station
2016 Bond Sale (new money)
Certificates of Obligation
• Street/Traffic Projects– Munson Street Rehabilitation $200,000– Francis Drive Rehab Ph. 1 &2 $1,330,000– Intelligent Traffic System $3,050,000– Greens Prairie Trail 2154 – Royder $4,100,000– Cain/Deacon Railroad Crossing $1,000,000– Design 2818 Capacity Imp. $655,000
City of College Station
2016 Bond Sale (new money)Certificates of Obligation
• Street Projects– Rock Pr Rd West - Wellborn to CL $700,000– Capstone & Barron Rd Alignment $800,000– Holick, Park Place, Anna, Glade $500,000
• Neighborhood Safety Improvements– Holleman Dr South Widening $1,500,000
City of College Station
2016 Bond Sale (new money)Certificates of Obligation
• Street Projects– Greens Prairie @ Arrington $515,000
• Intersection Improvements– Royder Road Expansion $2,700,000
Street Total $17,050,000
City of College Station
2016 Bond Sale (new money)
Certificates of Obligation
• General Government– Police Station Design/Initial Costs. $3,000,000
City of College Station
2016 Bond Sale (new money)Certificates of Obligation
• Water Projects– Water Well #9 $2,030,000– Well #9 Collection Line $1,250,000– State Highway 6 Water Lines $600,000– Munson Rehabilitation $500,000– Eastgate Rehabilitation $1,195,000– Variable Frequency Drive Repl $1,350,000
City of College Station
2016 Bond Sale (new money)Certificates of Obligation
• Water Projects– Francis Drive Rehab Ph 1 & 2 $850,000
– Lakeway Water line Extension $125,000
Water Total $7,900,000
City of College Station
2016 Bond Sale (new money)
New Money Total
• General Obligation Bond Projects $8,785,000• Certificates of Obligation Projects $28,270,000
Total $37,055,000
City of College Station
2016 Bond Sale (Refunding)
Recommended Refunding
• 2006 Bonds (GO Refunding) $2,205,000• 2007 Bonds (GO/CO/URB) $16,450,000• 2008 Bonds (GO/CO) $12,700,000
Total $31,355,000
City of College Station
City of College Station
First Southwest Presentation
Drew Masterson, Managing Director
City of College Station
2016 Bond Sale and Refunding
• Staff Recommendations– Approval of the Ordinance authorizing the
issuance of the General Obligation Improvement and Refunding Bonds, Series 2016;
– Delegating the authority to certain City Officials to execute certain documents relating to the sale of the Bonds;
– Approving and authorizing instruments and other procedures relating to said bonds; and
– Enacting other provisions relating to the subject.
City of College Station
2016 Bond Sale and Refunding
• Staff Recommendations– Approval of the Ordinance authorizing the
issuance of the Certificates of Obligation, Series 2016;
– Delegating the authority to certain City Officials to execute certain documents relating to the sale of the Bonds;
– Approving and authorizing instruments and other procedures relating to said bonds; and
– Enacting other provisions relating to the subject.
City of College Station
Questions ?