Upload
katie-pekarek
View
81
Download
2
Embed Size (px)
Citation preview
SPRING LAKE PARK:A Case Study for Green Infrastructure & LID
Jim [email protected] of OmahaEnvironmental Services Manager
Omaha CSO Program & Spring Lake ParkAn example of what is possible…
Challenges Facing Omaha Meet the increasing
requirements of the Federal Clean Water Act
Balancing the following needs: Regulatory compliance Economic affordability Community acceptance
EconomicAffordability
Community Acceptance
Regulatory Compliance
CSOSolutions
CSO is not a sewer separation program, it is not the City’s sewer
overhaul program
*When Omaha is ‘done’ separating the sewers as a part of CSO, it will have separated less than 20% of is combined sewer system*
CSO is a Public Health Program that must meet
federal law that requires us to reduce the amount of human sewage and disease causing bacteria that enter the rivers
and streams.
Evolution of the CSO Program 2009 - Original CSO LTCP submitted to NDEQ 2014 - Revised CSO LTCP submitted Both LTCPs generally rely on ‘gray infrastructure’
Need to manage 8 billion gallons of CSO annually Assumed there was little “green” in the original LTCP…
Evolution of the CSO Program Green Infrastructure was part of the program from
the start... may not have called it “green” Use water as a resource instead of a waste product Each capital project explores GI opportunities Committed to working with private entities & all
City Departments, including Parks Department Parks in Omaha provide a unique opportunity for
GI, projects so far include:
CSO GI in Omaha ParksA great collaboration…
Elmwood Park - 2012 Spring Lake Park - 2016 Adams Park - 2016 Field Club Trail, Vinton-2016 Albright Park (Gilmore) -
Construction Fontanelle Park – Just started Hanscom Park – 90% design Hitchcock Park –95% design Others being exploredNon-park GI Country Club - 2013 SOIA Lift Station – 2014 24th Street - 2015
Elmwood Park29 acres of Aksarben neighborhood routed through park w/7 weirs, bioswale & bioretention
Adams Park WetlandsLarge scale GI taking on 277 acres of urban runoff with 77 acre-feet of detention volue
Fontanelle ParkConstruction started March 2017; utilizing former golf course & existing lagoon
Hanscom ParkOldest Omaha park; improving existing pond & embracing water through the park
Welcome toSpring Lake Park!
Initial Grey Solution vs Final GI Plan
Storm pipe through park vs 20 GI elements
Multiple benefits w/GI
Overview of Spring Lake Park
Overview of Spring Lake Park
2 phases to the project
Missouri Ave
S 13th St
S 24th St
F St
S 27th St
J St
B St
I 80
S 16th St
Spring Lake Dr
John F Kennedy Expy
S Omaha Bridge Rd
S 22nd St
Funding Saved approx. $5 million by utilizing GI Grants from Nebraska Environmental Trust &
Nebraska Game and Parks commission totaled $1.3 million
Overall, the project cost the City $10.4 million dollars, with funding paid for from the Sewer Revenue Fund
Why this project… This was not the City’s idea, this was the
neighborhood’s idea. My boss at the time, Marty Grate, said that the City
needed a ‘signature project’ that helped give back to the community something tangible, to help them see what they are paying for
The Public Works Department asked permission from the Parks Department to use Spring Lake as that project.
Janet BonetSouth Omaha ResidentSpring Lake Park Team
A Little History and Residents Perspective
Spring Lake
Park TeamPresident Janet BonetVice President Jason
RoseSecretary John BonetTreasurer Callyann
CasteelBoard Members
James BonetJean IncontroGary Hansum
Keeping Nature in the City
Spring Lake Neighborhood
Spring Lake School
Henry Doorly Zoo
Rosenblatt Stadium
Spring Lake Golf Course
South High School
Suicide Hill / Baseball Field
County Treasurer Office
Current Swimming Pool
Old Ball field
1930’s Rubble Fill
Small Dam
Tree Frog aka Cricket Frog
Dragonfly Swarm August 2010
Sunflower and Honey Bee
Deer
Blue Grosbeak
Chipping Sparrow
Motivation for a community to take action
The Spark1994 Dedication of new playground
1960’s Landfill Site part of the park
The playground, parking, and picnic shelter (1994) are in the background.
The “dead spot”, noticed in 1995, is in the foreground.150 ppm salt
Somebody should
do something
Heritage
1994 – SLPT BLOSSOMS DRIVES EFFORT TO “PUT THE LAKE BACK IN SPRING LAKE PARK”
1995 – FEDERAL MANDATE SEWER SEPARATION
1999 – SLPT & KSU COMMUNITY VISIONING 2000 – COMPLIANCE ENFORCEMENT
NOTICE 2001 – SLPT CONCEPT PRESENTED TO
MAYOR 2002 – OMAHA GEARS UP FOR CSO
PROGRAM 2005 – SLPT AMONG COMMUNITY
STAKEHOLDERS ON CSO STEERING COMMITTEE
Moving toward doing something
Why do it? It has been said: It’ll never happen, City does not care about
South O It’s just a dump anyway, just fill it in I’ll be dead before those trees make shade I’m leaving the neighborhood why should I
care The city doesn’t care about our parks why
should I The kids today will just mess it up so why try It’ll cost too much Nobody will appreciate all that work Who the heck cares Who is going to take care of it when it’s done
Positive Partnerships
Broader-than-usual Out-of-the-box Creative Project-specific Mutually beneficial Truly collaborative Uniquely innovative Community inclusive
In order to be poised to seize the opportunities presented by changes in the broader trends: Community needs/wants Government mandates/budgets NGO funding shifts Social/environmental conditions Engineering & design
innovations Funding sources
Keep Omaha Beautiful Douglas County Health Dept Nebraska Dept Environmental Quality Papio Missouri Natural Resources District City Depts. – Parks, Planning, Public
Works Jacobson Helgoth Consultants / Tetra
Tech Nebraska Wildlife Federation Audubon Society & Sierra Club Groundwater Guardian Program
Society for Ecological Restoration Nebraska Statewide Arboretum Joslyn Institute for Sustainable
Communities EPA TOSC / Kansas State Univ UNL Water Resources Program KSU Urban Design in School of
Architecture National Parks Service Center for Health, Environment & Justice
Advisory Team & Expert Resources
The Other Kind of Experts Neighbors –
residents and businesses
History Sources
Youth / Schools
Community Groups
Potential Park Visitors
39
SLNA Visioning Session with KSU Team
Inclusive40
The condition of our parks says a lot about our city, its government, and its people.
Environmental Health Reflects and Impacts Community Health
Small seep area NW of pond, south of F Street --- 1999
SLPT’s Plan October 2001 at The Mayor’s Office
2014 - looking north from 14th & J48
Summer 2015, 14th & J St. No outlet
Old Dam - South of F Street - 2000 with KSU Urban Design Class
.
Spring below Swimming
Pool road in 2000
Is now underwater
feeding the Lake
Of Miracles and Mandates: Maximizing Opportunities for
Partnership BuildingBy Janet BonetNeighborhood ActivistSouth Omaha, Nebraska
NUSAHouston, TXMay 22, 2015
EPA – Region 7Technical Outreach Services to Communities at Kansas State University
CSO!
CSO’sCommunity
Liaison
Another rare bird
Keep Partners and Public Informed and Involved
Spring 2016 Public Tour
Big Muddy Workshop 2015 Renderings of Lake Concept
Summer 2016
Annual Neighborhood Clean-up 2015
2016 Annual Park Spring Clean Up
The year of Garbage,
Goats&
Guns
Thank you!
Pat Slaven, PLA, ASLACity of OmahaPark Planner
Omaha Parks and the CSO Program
Project Role: Department Liaison between the Parks Department and everyone else
Return the “lake” to Spring Lake Park
Park Goals: Respect History of the Park
Attract more and a greater diversity of wildlife
Park Goals: Wildlife Habitat
Provide more and varied recreation opportunities in the Park
Park Goals: Recreation
Don’t increase maintenance for park maintenance and golf course staff
Park Goals: Low Maintenance
Making sure we’re all swimming in the same direction
Parks and the Project TeamPark Planner Responsibilities on CSO Projects: Make sure everyone understands Parks Department goals for the
project Attend regular meetings with Public Works, consultants, project
management team Attend onsite meetings to discuss issues and solutions Review and comment on progress plans in terms of park goals Enforce Parks Dept. tree mitigation requirements Coordinate with other park entities, i.e. golf course staff, park
maintenance staff, etc. and communicate their concerns to the project team
Park Tree Mitigation – Individual Trees
(#sq ft canopy/500) x 2
Mitigation – Continuous Canopy with Understory
Will create maintenance nightmare, wet areas Will create places to lose balls, slowing down
play Will interfere with play in general
Golf Courses and Green Infrastructure
G.I. Team met onsite Bob and golf course staff Discussed concerns Developed design to address concerns
Golf Courses and Green Infrastructure
Parks to mow, pick up trash Public Works to hire or contract out for special
crews to maintain green infrastructure components
Park Maintenance
Educational Signage
Describes history of the spring lake, the CSO project lake reconstruction and the benefits of putting the lake back into Spring Lake Park.
Bilingual text makes sign accessible to all citizens
Speakers discuss the key design components of the project
Emily M. Holtzclaw, PECH2MSenior Project Manager
Permits and Compliance
Permitting
USACE 404 NW 27 Solid Waste
Removal Lead in Soils Low Hazard Dam 408 Levee Permit Dewatering PCSWMP NPDES CSW/Grading
Compliance Highlights Regulatory Coordination
Early (Jurisdiction) Consistent
Onsite Mitigation Minimize Impacts Maintaining Seeps Design Tweaks Annual Monitoring
Breach Zone 2017 NW permits
Hydrology & Hydraulic Design
Rocky J Keehn, PESEHSenior Water Resources Engineer
Project Role: Lead Water Resources Engineer for Consultant Team
The Modeling Challenge
Required to Design for: Green Infrastructure, 10-year, 100-year, Dam Break – PMP and natural seepage flows
Water Quality -Cascading Planes
Lots of models use this concept. Aids in showing
Note: areas broken into direct impervious and indirect (includes pervious). For indirect pervious CN was from 74 in urban yard areas and 61 in undisturbed areas
HydroCAD
Water Quality – First Flush Systems
HydroCAD
Inlet
1st Flush
Large Flows
1st Flush PondEmergency Outlet Natural Downstream Pond
Primary Outlet
Water Quality – Manhole Spillway
HydroCAD
Inlet
1st Flush
Large Flows
1st Flush PondEmergency Outlet Natural
Spillway
Primary Outlet Infiltration Pond
Downstream, no pipes
New Conveyance Channel
HydroCAD
100yr – cross entire valley
10yr – about 20 feet wide
Vegetated
About 1 foot incised
Detention to protect channel
#5 Primary outlet to channel #4 -Gate Control to
adjust flows from pond
HydroCAD
#2 - Location Primary Overflow -Armored
#3 - Location Emergency Overflow –Access Road
#1 Pond outlet to Gate Control MH
Detention Pond
Constructed Wetland – final protection
Multiple depths…various vegetation
Stop Logs Control water elevation which allow “tweaking” to make sure vegetation as planned is established
Stop Logs
HydroCAD
7 area contribution to wetland
Extend Dry Basin Outlet
Spring Flow
Lake Drawdown pipe
MH with gateLake control structure, main overflow
Emergency “F” Street dam overflow.
Lake Outlet
Complex Outlet Under “F” Street
Extend Dry Basin Overflow
Dam Design Floods all way up north valley, 100 year all under water including wetland, 10-year trail just under water
Final Hydraulic StructuresSouth Side “F” Street
North Side “F” Street
Value of modeling…something not working…design or construction
related?
Emergency overflow, showing signs of flow and erosion
Primary overflowCone Structure
Emergency overflow designed for 10-year.
Primary: 1070.71, Emergency 1071.50, 10-year 1071.24.Road OK
Emergency overlow working too often.Check. As-built Prim: 1071.24, 10-year now 1071.58Overtops road!
Model explains what might be the problem...shows a very sensitive design.
Treatment Train..
SAFL Baffle in residential
neighborhood
First Flush Diversion Manhole
Extended Dry Detention
BasinDry Detention
Facility
Meandering Channel with
Boulder Drops
Constructed Wetland
Flat Sloped
Channel
Spring Lake
Combined Pipe now
Storm Pipe
Missouri River
Conveyance Train
Dry Detention Pond and gated outlet pipe
Meandering Channel with Boulder Drops
Constructed Wetland and outlet pipe under trail to Lake
Energy Dissipation Structure to “Natural” Channel
Spring Lake and pipe under “F” Street
Low flow culvert and “Texas Crossing” to wetland
Roof/impervious surface near houses
Though the yards
Down the Street
Storm pipes through the park
Replace pipes (grey) with surface flow (green) to reduce project cost
Dry Detention Pond and gated outlet pipe
Meandering Channel with Boulder Drops
Constructed Wetland and outlet pipe under trail to Lake
Energy Dissipation Structure to “Natural” Channel
Spring Lake and pipe under “F” Street
Low flow culvert and “Texas Crossing” to wetland
or 2500 feet (1/2 mile) of 36” to 66” RCP Underground Storm Pipe
Green infrastructure reduced cost by $5 million
Questions . . .Or time for a break!