EN-SEED-Passivistas - 1 - Experts Symposium 2016 Greek case: does it pay off? From sketch to monitoring results Stefan Pallantzas Msc . Civil Engineer NTUA President of HPHI Certified Passive House Designer Building Certifier Design & Construction Lessons learnt Social impact

Passivistas SeedPass Webinar 2016

Embed Size (px)

Citation preview

EN-SEED-Passivistas - 1 -

Experts Symposium 2016

Greek case: does it pay off?From sketch to monitoring results

Stefan PallantzasMsc. Civil Engineer NTUA

President of HPHICertified Passive House Designer

Building Certifier

• Design & Construction

• Lessons learnt• Social impact

EN-SEED-Passivistas - 2 -

Experts Symposium 2016

Project locationPapagou – Athens

GREECE

EN-SEED-Passivistas - 3 -

Experts Symposium 2016

Project locationPapagou – Athens

GREECE

EN-SEED-Passivistas - 4 -

Experts Symposium 2016

TFA:

1ST FLOOR = 85 Τ.Μ.GROUND FLOOR = 30 Τ.Μ.

Project description

EN-SEED-Passivistas - 5 -

Experts Symposium 2016

Application of EIFS on 1st floor + ground floor

Exterior walls

Building envelope

Heating demand 301 kWh/(m2a)Heating load 129 W/m2Cooling demand 77 kWh/(m2a)Cooling load 68 W/m2Estimated airtightness n50 =5.00 /h

EN-SEED-Passivistas - 6 -

Experts Symposium 2016

BEFORE: Ubr.= 1,633 W/m2K

AFTER: Ubr.= 0,178 W/m2KApplication of EIFS on 1st floor + ground floor

Exterior walls

EN-SEED-Passivistas - 7 -

Experts Symposium 2016

Interior insulation of Ground floor exterior walls

adjacent to the ground

EN-SEED-Passivistas - 8 -

Experts Symposium 2016

BEFORE:Ustone = 2,632 W/m2K

AFTER:Ustone = 0,470 W/m2K

Interior insulation of Ground floor exterior walls

adjacent to the ground

EN-SEED-Passivistas - 9 -

Experts Symposium 2016

Exterior insulation of roof

BEFORE:Uroof = 3,442 W/m2K

AFTER:Uroof = 0,100 W/m2K

EN-SEED-Passivistas - 10 -

Experts Symposium 2016

BEFORE:Uslab = 3,959 W/m2K

AFTER:Uslab = 0,484 W/m2K

Interior insulation of GROUND FLOOR slab

EN-SEED-Passivistas - 11 -

Experts Symposium 2016

Interior insulation of 1st FLOOR slab

with wooden finish

BEFORE:Uslab-wood = 1,562 W/m2K

AFTER:Uslab-wood = 0,408 W/m2K

EN-SEED-Passivistas - 12 -

Experts Symposium 2016

EN-SEED-Passivistas - 13 -

Experts Symposium 2016

• PARAPET• BALKONIES• COLUMNS & INTERIOR

WALLS TO 1st FLOOR SLAB• EXTERIOR WALL TO

GROUND SLAB

EN-SEED-Passivistas - 14 -

Experts Symposium 2016

THERMAL BRIDGE FOR UNINSULATED BALCONY

Ψ = 0,628 W/(mK)

EN-SEED-Passivistas - 15 -

Experts Symposium 2016

EN-SEED-Passivistas - 16 -

Experts Symposium 2016

BEFORE:

Uf= 2,50 W/m2K

Ug= 5,80 W/m2K

g= 0,87 W/m2K

AFTER:

Uf= 0,78 – 1,00 W/m2K

Ug= 0,55 W/m2K

g= 0,54 W/m2K

EN-SEED-Passivistas - 17 -

Experts Symposium 2016

WINDOW INSTALLATION ON THE LINTEL

EN-SEED-Passivistas - 18 -

Experts Symposium 2016

WINDOW INSTALLATION ON THE INSULATION

LAYER

EN-SEED-Passivistas - 19 -

Experts Symposium 2016

• SOLAR GAINS MAXIMIZATION

• WINDOW SHADING

Summer concept and shading

EN-SEED-Passivistas - 20 -

Experts Symposium 2016

• PASSIVE HOUSE DOORS

EN-SEED-Passivistas - 21 -

Experts Symposium 2016

EN-SEED-Passivistas - 22 -

Experts Symposium 2016

EN-SEED-Passivistas - 23 -

Experts Symposium 2016

EN-SEED-Passivistas - 24 -

Experts Symposium 2016

EN-SEED-Passivistas - 25 -

Experts Symposium 2016

One HRV for 1st FLOOR

Effective Heat Recovery Efficiency = 92%

Subsoil Heat Exchangerwith Effective efficiency = 64%

EN-SEED-Passivistas - 26 -

Experts Symposium 2016

EN-SEED-Passivistas - 27 -

Experts Symposium 2016

One HRV for GROUND FLOOR

Effective Heat Recovery Efficiency = 89%

EN-SEED-Passivistas - 28 -

Experts Symposium 2016

EnerPHit:First one on the SE

Mediterranean area

EN-SEED-Passivistas - 29 -

Experts Symposium 2016

Lessons learnt

Teamwork!

8 CPH Designers60 Craftsmen

150 Days

EN-SEED-Passivistas - 30 -

Experts Symposium 2016

Lessons learnt

PHPP 9

Is the Tool !

EN-SEED-Passivistas - 31 -

Experts Symposium 2016

Lessons learnt

Insulate first!

15 kWh/(m2a)

10 cm of external

insulation +

double-glazed windows

10 W/m2

20 cm of external

insulation +

double-glazed windows

with a high g-value

triple-glazing Ug = 0.5 W/(m2K)

g-value of 0.54

15 cm of external

insulation+

EN-SEED-Passivistas - 32 -

Experts Symposium 2016

BLOWER DOOR TESTn50 = 0,56 ACH

Lessons learnt : If you know where to “tape”, then airtightness is easy!

EN-SEED-Passivistas - 33 -

Experts Symposium 2016

Lessons learnt

HRV :

Handmade!

EN-SEED-Passivistas - 34 -

Experts Symposium 2016

Lessons learnt

Monitoring & public info

Give the users the data they

need!

EN-SEED-Passivistas - 35 -

Experts Symposium 2016

Lessons learnt

Monitoring & public info

Give the users the data they

need!

EN-SEED-Passivistas - 36 -

Experts Symposium 2016

Lessons learnt

Monitoring & public info

Give the users the data they

need!

EN-SEED-Passivistas - 37 -

Experts Symposium 2016

Lessons learnt

Monitoring & public info

Give the users the data they

need!

EN-SEED-Passivistas - 38 -

Experts Symposium 2016

Measurements

PHPP is right!!!

FINAL ENERGY CONSUMPTION DEC 2015-MAY 2016 (KWh)

Month PHPP MEASURED HEATING PHPP HEATING MEASURED DHW PHPP DHW MEASURED

DEC 589,07 414,96 294,00 263,82 114,14 96,24

JAN 677,07 602,35 414,00 367,45 82,35 50,34

FEB 625,39 339,80 393,00 206,57 63,56 57,87

MAR 379,07 339,80 184,00 141,35 14,12 12,08

APR 197,23 151,35 22,00 5,00 - -

MAY 181,63 205,90 - - - -

SUM 2.649,46 2.054,16 1.307,00 979,19 274,17 216,53

KWh/m2 TFA 23,12 17,92 11,40 8,54 2,39 1,89

Euros/day 1,95 € 1,52 € 0,96 € 0,72 € 0,20 € 0,16 €

Total Winter Cost 184,87 €

Total Heating Cost 88,13 € PER DAY 0,72 €

EN-SEED-Passivistas - 39 -

Experts Symposium 2016

TFA 115 m²

Energy price 1st year 0,172 €/kWh

Annual cost increase 5,00 %year

Inflation 1,00 %/year

Real annual cost increase 3,96 %/year

Time period 10 years

energy consumption for heating of existing house

per m2 300 kWh/(m²year)

Total Energy Consumption 34.620 kWh/year

energy costs 1st year 5.937 €/year

energy consumption for heating after retrofit 11 kWh/(m²year)

Total energy consumption 1.269 kWh/year

energy costs 1st year 218 €/year

Additional Retrofit Costs /m2 400 €/m²

Total costs 46.160 €

Financing the additional cost

Time Period 10,00 years

nominal annual interesr rate 4,00 %/year

real interest rate 2,97 %/year

Annuity a 11,71 %/year

Annual costs of financing 5.403,16 €/year

Cost effective

YES!!!It is

EN-SEED-Passivistas - 40 -

Experts Symposium 2016

Social impact

Passive House Days

>300 Visitors

EN-SEED-Passivistas - 41 -

Experts Symposium 2016

Social impact

PROJECT WEBSITE

Info material

EN-SEED-Passivistas - 42 -

Experts Symposium 2016

Social impact

HPHI Headquarters

6 CEPH courses55 Participants

8 events400

participants

EN-SEED-Passivistas - 43 -

Experts Symposium 2016

Thank You!

For Bella and Noche…