30
Getting the Lead Out How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years Randall Roost Angie Goodman Principle Planner, Water Operations Water Quality Administrator Lansing Board of Water and Light Lansing Board of Water and Light Scott Hamelink Director, Water Operations Lansing Board of Water & Light

Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Embed Size (px)

Citation preview

Page 1: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Getting the Lead Out How Lansing, Michigan Replaced 13,500 Lead

Service Lines in 12 Years

Randall Roost Angie GoodmanPrinciple Planner, Water Operations Water Quality AdministratorLansing Board of Water and Light Lansing Board of Water and Light

Scott HamelinkDirector, Water OperationsLansing Board of Water & Light

Page 2: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Municipally owned utilityGoverned by a Board of Commissioners who set policy, approve budgets and ratesGroundwater supplies two water conditioning plants that use lime-soda softening on water from 124 wells22 MGD average daily demand providing water to 59,000 retail accounts

Lansing, Michigan Board of Water & Light

Page 3: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Our Lead Service Lines

Took ownership of all water service lines in 1927Stopped installing LSLs in 1956

As a result of our ownership we developed a fairly accurate record of service line materials. Our service card files were kept up to date throughout.Inventoried all service line materials in 1980s, identifying as lead, copper, plastic or galvanized steel. Lead and galvanized were labeled “non-standard”.In 2004 we asked customers to self-identify LSLs. Vast majority confirmed our records. Card files were transferred to GIS.

Page 4: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

BWL Lead Monitoring All sampling rounds have shown 90th % ile below 15ppb

BWL conditioned water is high pH (9.4), moderate alkalinity (35)and hardness (98)Optimal Corrosion Control installed in 1997

Monitoring reduced to 50 locations every three yearsSome sampling rounds higher than othersBegan accelerated LSLR, public education in 2004

Page 5: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Our LSLR Program

Inventory showed about 17,000 LSLs as of the early 1990sEstimates were based on Customer Information System and GIS project Before 2004 lead service lines were replaced as needed.

Developed accelerated LSLR Program, 2004Proposed 14 year program, but the Board of Commissioners required that we target 10 years.Due to slowdown in combined sewer separation project, the anticipated completion date is now June of 2017.

Current active LSLs remaining estimated at <500, 170 services with unknown materials that will be investigated to be determined if lead.

Page 6: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Prioritization of Replacements

Any lead service that is physically disturbed by such things as dig-ins, excavations, or leak repair.Services supplying schools, day care centers, or other identified sensitive populations as defined by the USEPA.Services where there are sample results in excess of 15 ppb.Services in the work zone of CSO replacement or street restorations.Multiple services within a compact area.Length of lead pipe present in the service line.

Page 7: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

LSLR Schedule

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

0

500

1000

1500

2000

2500

7 46 71 106172

94 138

631

16321573

1669

1984 1974

902

596

388329

198 210

Number of LSLs Replaced

Number of LSLs Replaced

Page 8: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Factors that affect the cost of LSLR

Coordination with street projectsMore difficult and expensive without City Combined Sewer Overflow (CSO) Separation Project or road resurfacingCost per service goes from $3,500 when coordinating with CSO to $6,500 without CSO.Current removal method further reduces costs.

Material CostsCopper price fluctuations and the Lead Free Act have some impact but are small relative to street cut impact

Page 9: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

More Factors

Meter location and ownershipHouse on slab, service line under house, porch, or drivewayMeter pit conundrum, re: ownership

Crew Mobilization No partial LSL replacement mandates same-day completion, leaving us the choice of idle crew or overtimeWorking in the same or adjacent blocks reduces mobilization costs

Page 10: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

BWL Lead Communications Plan

• Bill stuffers• Special brochures to schools, day cares, health offices• Lead information on the BWL web site• Special meetings and community events• Neighborhood meetings• Preparations for customer response FAQs• Lead Hotline• Meetings with local media

Page 11: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Communications with our CustomersThe BWL hosted several community open houses at various locations around the city.

8 Stations were manned at each location:

Station 1 – Information about lead service linesStation 2 – Identifying lead service linesStation 3 – Sources of leadStation 4 – What the BWL is doingStation 5 – How to protect yourself from leadStation 6 – Where your water comes from

Additionally there were two other stations. One manned by staff from the county health department , and one staffed by the MDEQ.

Page 12: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Engaging Customers in LSLRsBWL does not repair LSLs…replacements only!General Customer Outreach

Beginning in 2004 we developed and distributed brochures and articles in bill stuffersConducted Open Houses at local schools and community centersAdded further recommended customer precautions to our Water Quality ReportAs LSLR continues there is less concern from the general public

LSLR NotificationLetter is sent to LSL address requesting customer to contact us for an appointment. The letter explains the processLetter includes an explanation of the replacement tasks, the need for home access, BWL and customer responsibilitiesMeet with customer prior to or day of LSLR to explain the process, including follow-up. This helps the customer understand the details.

Emergency ReplacementsUsed only in special conditions such as service breaks. We speak with the customer on site.

Page 13: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Letters to our customers

Page 14: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Communicating with our Employees

Page 15: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Five Largest Hurdles

Access Normally just coordination but ultimately comes down to a condition of service

EasementsWe have not sought easements and therefore must count on good customer interaction and follow-through

Through Wall BorePotential liability. Occasional disputes can be expensive

Page 16: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Five Largest Hurdles (Cont.)

Yard Restoration, non-standard installationsTrees, shrubs, plantings, crawl spaces, slab foundations, porches, driveways, sheds, drywall interiors, meter access require decisions case-by-case

Budget!Approximately $42 million has been spent since 2004LSLs are replaced as a capital project (an investment into infrastructure)Rate payers share in the cost and the community has been generally supportiveWe are currently spending on average $3 million per year on LSLR.

Page 17: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Communicating With The Customer to Schedule a LSLR

No Response to First Letter:

Phone Call

Site Visit

Second Letter Sent

10 Days after Water

Service is Turned Off

#1 #2

Beginning the LSLR Process

Page 18: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Prior to beginning the actual replacement of the lead service there is a substantial amount of work that must be done in advance. Scheduling of the replacement with the customer can take many iterations before an acceptable timetable can be reached. Then the utility must coordinate with local Miss-Dig to locate other utilities in the excavation areas.

Beginning the LSLR Process

Page 19: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

The LSLR ProcessThe process begins by shutting off the curb stop to prevent any water in the system from entering the customers premises. This is especially important to minimize the transfer of any lead particulate into the service or the customer’s household piping during the excavation of the corporation at the main.

Page 20: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Once the curb stop has been closed the work can then be divided into two different work groups. The first work group can then enter the premises and disconnect the service from the meter assembly.

The second work group can then begin the excavation process at the main to expose the corporation fitting.

Excavation can be accomplished with either a backhoe or by using a vacuum excavator. The advantage of the excavator is that it can minimize the potential risk to other utilities that can be difficult to locate or may have been miss-marked.

Page 21: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Of course there is always a lot of hand digging that must be done as well. Once the corporation is exposed the water is shut off at that location as well. It is important that the excavation of the main and the corporation be controlled to prevent any water or soils from entering the corporation or the new service once it is installed.

Page 22: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Meanwhile inside…….

While the excavation continues outside the employee inside the residence begins the disconnection of the lead service and preparing the new copper for installation. We are also replacing the water meter at the same time since we already have access to the property.

Page 23: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

One of the most important steps in preparing the new copper line to ready for installation is the sealing of the new service before it is pulled. The end of the copper pipe is covered with electrical tape. The pulling sock is then placed over the end of the copper pipe. Within the pulling sock is a small rubber ball that is pressed against the taped end of the pipe to further prevent any potential particulate from entering the new copper service during installation.

Page 24: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Once the corporation is exposed, the excavation then moves to the curb stop. The curb stop is removed by cutting the lead line on both sides of the curb stop. Then a line is fished through the lead line from the curb stop to the inside and a 3/8” steel cable is pulled back through the service.

Page 25: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

The copper pipe is then connected to the pulling harness and the harness is connected to the steel cable. Using the backhoe, the lead service is pulled out of the ground from the basement to the curb stop.

Page 26: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Once the copper pipe is visible in the curb stop excavation, the process stops to allow the cable to be removed from the backhoe and it is then rethreaded through the portion of the lead service line between the curb stop and the corporation. The backhoe then pulls the copper line through to the corporation excavation. From there the new copper service is attached to the corporation.

Page 27: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Once the copper is attached to the corporation then the copper line is cut in the curb stop excavation and a new curb stop is installed. Water is then turned back on for flushing of the new service line before new water meter is connected.

Page 28: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

We then provide a set of flushing instructions to the property owner for continued flushing of the premise plumbing, with each tap flushed for 5 minutes before moving to the next tap downstream from the meter.If the customer requests it a filter will be provided to them for use for the next 3 months as an added precaution.

Page 29: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Lead Service Line Replacement Finish Line!!

Dec-15Jan

-16Jan

-16Feb

-16Feb

-16

Mar-16

Mar-16

Apr-16

May-16

May-16

Jun-16Jun-16

Jul-16

Aug-16

Aug-16Sep

-16Sep

-16Oct-

16

Nov-16

Nov-16Dec-

16Dec-

16Jan

-17Jan

-17Feb

-17

Mar-17

Mar-17

Apr-17

May-17

May-17

Jun-17Jun-17

0

100

200

300

400

500

600

700

Lead Service Replacement Schedule to Completion

Actual Projected

Num

ber o

f Lea

d Se

rvice

s

Page 30: Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Lines in 12 Years

Questions??