Upload
anne-patenaude
View
316
Download
0
Embed Size (px)
Citation preview
Presented by: Shawn Carr, P.Eng
Audit Funding Program Update
TODAY’S OBJECTIVESAudit Funding Goals and Results
The What and Why of Energy Audits
Review Audit Funding incentives, eligibility, and application process
Engage our Panelists with questions on Audit Funding
Case Studies – Using audit funding incentives to uncover your biggest savings potential!
Open for business
We need your continued support
August 2015 until 2020
400GWh target within our territory (7 billion KWh in ON)
2015 – 2020 CONSERVATION FIRST FRAMEWORK
WHY ENERGY EFFICIENCY PROJECTS ARE NOT COSTS BUT ASSETS TO BE MANAGED
Lowering Operating Costs
Reducing GHG’s
Satisfying sustainability initiatives
Green Building Certification and Labelling Systems
Improving tenant comfort
Demonstrating Leadership through benchmarking
Emulating Best Practices in other buildings
Responding to a mandate
Preparing for mandatory disclosure
Productivity Impact
OPTIMIZING RESULTS
Occupant UseBuildingOperations
Building Systems
Savings
Savings
Savings
ESA: Tenant Energy Audits
SystemOptimization
ESA: Building Energy Audit
Retro-commissioning Focuses on Operations-Complicated systems/controls-Troubleshooting required-Has BAS
Energy Audits Focus on Equipment- Renewal- Simple systems and controls- Typically no BAS analysis
Content provided by WSP
Audit Stats since 2011
250 Audit Funding Applications$1,200,000 incentives issued60+% of sites audited so far have applied for Retrofit Incentives
Incentives to Owners for completing building energy audits, RCx studies, and Building System Audits.
Incentives to Tenants of facilities for completing energy audits within their space.
AUDIT FUNDING
AUDIT FUNDING PROGRAM OVERVIEW
Incentives for Energy Studies
Audit Funding Program
Four levels of incentives
Electricity Survey & Analysis for
Owners
For Energy Audits on Entire Building
Electricity Survey & Analysis for
Tenants
For Energy Audits of Tenant Spaces
Building System Audit
For optimizing existing system
performance
Detailed Capital Intensive
ModificationsFor deeper analysis on capital projects
identified in ESA
Existing Building Commissioning
For Rcx your Chilled Water System
Process & SystemsFor customers running
complex systems
AUDIT FUNDING AND EB COMMISSIONING PROGRAM CHANGES
Changes being considered for 2016 and beyond:
EB Commissioning to expand beyond chilled water to include other electricity consuming building systems
Detailed Analysis of Capital Intensive Modifications may be discontinued
AUDIT FUNDING OBJECTIVESHelp you achieve Greater Energy Efficiency
Investigate Benchmark Implement Measure
ASHRAE LEVEL AUDITS
LEVEL 1: WALK-THROUGH SURVEY
LEVEL 2: ENERGY SURVEY AND ANALYSIS (ESA)
LEVEL 3: DETAILED ANALYSIS OF CAPITAL-INTENSIVE MODIFICATIONS (DCIM)
BUILDING OWNERS AND TENANTS
ELECTRICITY SURVEYAND ANALYSIS
• Connected to the LDC’s distribution system, classified as non-residential.• Own or lease the building• Not eligible if the facility has already received a ESA.• Auditor must be a P.Eng, CEM, or Building Assessment Professional (ASHRAE)• Meets ASHRAE Level 2 requirements• Commitment to implement no/low cost measures (<$1,000 and <1 year payback)
Applicant Building Size IncentiveBuilding Owner Up to 30,000
sq.ft$0.10/sq.ft to a maximum of 50%
Building Owner Larger than 30,000 sq.ft
$3000 for 30,000 sq.ft and $0.05/sq.ft thereafter up to $25,000 or 50% of audit costs
Tenant Any Size $0.03/sq.ft up to $7,500 or 50% of audit costs
BUILDING OWNERS
BUILDING SYSTEM AUDIT
• Analysis of energy savings by optimizing existing building systems (Ventilation, chilled water distribution, DHW distribution, Controls/BAS, AHU’s, etc)
• One incentive per building system to a maximum of $50,000• Can be used to evaluate design options/repair strategies through an energy lens• Excludes lighting systems
Building Size IncentiveAny 50% of audit costs up to
$5,000
BUILDING OWNER
EXISTING BUILDING CX
• Incentives to evaluate and increase chilled water system efficiency.• Equipment older than 3 years and not had a major overhaul in last 2 years• No planted overhaul or replacement in next 2 years• Refer to participant agreement and report requirements for more details.
Phase Incentive RequirementScoping Study Up to $2,500 or 100% of cost -Commissioning Agent
must have certain credentials
Investigation $6/ton for data logging equipment (up to 75% of costs)$18/ton for preparing Cx report (up to 75% of costs)Up to a maximum of $30,000
Data Acquistion System installed to log performance dataProject M&V plan
Implementation Up to $5,000 or 100% of cost for implementation report
Implement measureswith simple payback <2 years
Hand-off/Completion Up to $2,500 or 100% of cost for completionreport
Analysis of yearlyenergyconsumption/savings
BUILDING OWNER
PROCESS & SYSTEMS
• Different payment terms and M&V requirements depending on Incentive Stream
Phase Incentive RequirementInvestigation Preliminary Engineering Study (PES): Up to
$10,000Detailed Engineering Study (DES): Up to $50,000
- 100 MWh of Annualized SavingsDelivered
- - 3rd party review of report
Project Implementation –Behind the MeterGeneration Projects(i.e: Combined Heatand Power, WasteEnergy Recovery)- Compressed air systems
Three Incentive Streams:
Small Capital Incentives (<$1,000,000)- Up to 70% of project cost or $200/MWhLarge Capital Incentives (>$1,000,000)- Up to 70% of project cost or $200/MWhRetrofit Program-Up to 50% of project cost
HOW TO PARTICIPATE?
Establish Eligibility
Apply to Program
Obtain Pre-Approval
Receive Cheque
Engage us early to determine best funding path based on your needs
Submit Application & Participant Agreement and review audit report requirements before beginning your audit
Refer to Post-Project Evaluation Checklist
Submit Post-Project Documentation
LDC reviews report and meets with you to discuss implementation plans and deliver cheque
http://cdm.hydroottawa.com/support-centre/worksheets-and-forms
Bentall Kennedy - Sun Life Financial Centre
• Electricity Survey and Analysis Audit with some Rcx• Building Simulation• Design Systems Analysis for Cooling Plant
• Audit Project Cost: $49,000• Audit Incentive Paid: $24,500• Led to $2,000,000 capital upgrade of cooling plant• $536,000 retrofit incentive from Hydro Ottawa• Projected Annual Savings: $185,000
QUESTIONS?
Shawn [email protected] ext. 7474