Upload
cdm-smith
View
58
Download
0
Embed Size (px)
Citation preview
June 23, 2016
Phase and Forget?How to Move Phased HMGP Projects to Construction Jordan Williams, CFM
2
Hazard Mitigation
Sustained action to reduce or eliminate long-term risk to human life and
property from hazards.The only phase of emergency
management specifically dedicated to breaking the cycle of damage,
reconstruction, and repeated damage.
Hazard Mitigation Assistance
HMA programs reduce community vulnerability to disasters and their effects, promote individual and community safety and resilience, and promote community vitality after an incident
Pre-Disaster Mitigation (PDM) Provides funds for hazard mitigation planning and projects on an annual basis. Available annually and nationally competitive
Flood Mitigation Assistance (FMA) Provides funds for flood hazard mitigation projects as well as plan
development on an annual basis. Priority to Repetitive Flood Claims, Severe Repetitive Loss, and NFIP properties
Available annually and nationally competitive Hazard Mitigation Grant Program (HMGP)
Assists in implementing long-term hazard mitigation measures following a major disaster.
Hazard Mitigation Assistance
HMA programs reduce community vulnerability to disasters and their effects, promote individual and community safety and resilience, and promote community vitality after an incident
Pre-Disaster Mitigation (PDM) Provides funds for hazard mitigation planning and projects on an annual basis. Available annually and nationally competitive
Flood Mitigation Assistance (FMA) Provides funds for flood hazard mitigation projects as well as plan
development on an annual basis. Priority to Repetitive Flood Claims, Severe Repetitive Loss, and NFIP properties
Available annually and nationally competitive Hazard Mitigation Grant Program (HMGP)
Assists in implementing long-term hazard mitigation measures following a major disaster.
5
What is a phased project?
Projects that receive funding in phases to complete complex activities and to allow the Applicant to develop a full work scope/data package to support the full project description.
Phase 1: Design and Application Development Phase 2: Construction HMGP phasing does NOT equal partial solution/phased
construction Some application components will be based on assumptions
and engineering judgement Can be a great tool to allow communities to implement more
complex projects
6
The Number$
For Hurricane Sandy in New York HMGP Ceiling is approximately $1.4 Billion Approximately 50% is going to phased projects 33% is awaiting obligation pending Phase 2 approval
For Hurricane Katrina in Louisiana Approximately $450 Million allocated to phased projects in January 2015 Approximately $375 Million yet to be obligated
7
Why do projects get phased?
Communities don’t have a lot of technical staff on Cost of design plans Need for more detailed engineering analysis such as H&H Complicated EHP
FEMA/Jennings
8
Examples
Larger complex community drainage projects Large critical facility building retrofits Bridge upgrades
HMGP phasing does NOT equal partial solution/phased constructionFEMA/Booher
9
What should be in the initial application?
Scope of work Available engineering analysis Cost estimate Benefit cost analysis EHP requirements Clearly stated assumptions
10
How do we move these forward?
Clear guidance on Phase 1 deliverables Maintain accountability Frequent and honest communication
FEMA News Photo
11
What are our recommendations?
Set clear deliverables and milestones in award letters Consider time it will take State/Subapplicant to procure a designer Consider the time it will take for FEMA and the State to review
Award letter should include: Engineering analysis required
H&H Geotechnical reports
Required design milestones 30%, 60%, 90%
Detailed cost-estimate Benefit-cost analysis EHP Requirements TIMELINES!
Projects should be evaluated/ confirmed along the way
12
What are our recommendations?
Require Progress Reports and Status meetings Avoid phase and forget
Review along the way If deliverables show that a project will not meet HMA requirements
then adjust or deny Don’t keep investing in projects that will not get approved
FEMA/Booher
13
What are our recommendations?
Joint review of materials versus submitting and corresponding through an RFI Use RFI’s to document the process and to ensure accountability But work together to break the cycle of endless back and forth
14
What are our recommendations?
States should consider using Advance Assistance versus phasing a project
Advance Assistance can be used to develop mitigation strategies and obtain data to prioritize, select, and develop complete HMGP applications
Under HMGP: 25% of ceiling or $10 Million (whichever is less)
15
What are our recommendations?
Not every complex and/or incomplete project needs to be phased, some can be ‘approvable’ through an RFI
FEMA/State should not use phasing as an extended way to avoid saying “No” Phased projects are not meant to be a band aid Wastes resources
Organized file managment
16
Recommendations and Conclusions
Need to avoid “Phase and forget” This process can be more work than traditional applications Communication is key to success These projects can work and provide better comprehensive
mitigation solutions
FEMA/Caliendo
17
Questions?