UNDER REAMED PILES PREPARED BY :- RAVAL DIVY DINESHKUMAR

Under reamed piles

Embed Size (px)

Citation preview

Page 1: Under reamed piles

UNDER REAMED PILES

PREPARED BY :- RAVAL DIVY DINESHKUMAR

Page 2: Under reamed piles

2 INTRODUCTION

Under reamed piles are made by C.B.R.I.( Central Building Research Institute).

They are made of R.C.C.

In the bottom portion of the pile, enlarged portion is given which is called ‘under reamed’ or ‘bulb’.

If pile has one bulb, it is called single reamed, if the pile has two bulbs then it is called double reamed, and if there are more than two bulbs, it is called multiple under reamed piles.

Page 3: Under reamed piles

3

SINGLE AND DOUBLE UNDER REAMED PILES

Page 4: Under reamed piles

4 FEATURES

Dia. Of the pile = 20 to 50cm Dia. Of the bulb = 2 to 3 times of dia. of pile Length of the pile = 3 to 8m Spacing between two piles = 2 to 4m Spacing between two bulbs = 1.25 to 1.5 times of bulb dia. Load carrying capacity = 20 to 40 ton

Page 5: Under reamed piles

5 APPLICATIONS

1. Black cotton soil expands as it comes in contact with water and it gets contracted as it is dried out. Because of this reason, there may be a chance of cracks in the structure. To avoid such damage, under reamed pile are used in black cotton soil.

2. When the soil doesn’t have much load carrying capacity, under reamed piles are used to increase the capacity.

3. It is used when the water level in sandy soil is high.

4. When there are lifting forces acting, it should be used.

Page 6: Under reamed piles

6 INCREASING LOAD CARRYING CAPACITY1. By putting more bulbs

2. By increasing the dia. of bulb

3. By increasing the length of pile

4. By providing proper reinforcement

Page 7: Under reamed piles

7 Construction of under reamed pile

Under reamed piles are mostly constructed by manual work.

The machine for the construction of pile is made by C.B.R.I. Rurki.

The machine is easy to use and it is light weighted. It consists of three tools :

1. Spiral Auger

2. Under – reamer

3. Boring guide

Page 8: Under reamed piles

8

Spiral auger is used to make a hole in the land for the under reamed pile.

The auger contains special cutter at the bottom to dig the land.

The soil that is dug is taken out by the bucket.

Page 9: Under reamed piles

9

SPIRAL AUGER INSERTED THROUGH TRIPOD IN VERTICAL DIRECTION

Page 10: Under reamed piles

10

BUCKET PROVIDED TO TAKE OUT THE SOIL

Page 11: Under reamed piles

11

REINFORCEMENT

Page 12: Under reamed piles

12

CONTRUCTED UNDER REAMED PILE

Page 13: Under reamed piles

13

Special cutter is used for making the bulb. By putting enough pressure, we can increase the dia. of bulb.

The auger is kept through the tripod and after than the digging is done. So the digging is done in the vertical direction.

After digging the desired depth, the auger is pulled out. The reinforcement is then inserted in the hole. Concreting is done. If more than one pile, beam is constructed which connect the piles and make them act like a single unit. The wall is than constructed on the beam.

Page 14: Under reamed piles

14

PILE CAP CONNECTING ALL THE PILES

Page 15: Under reamed piles

15 ADVANTAGES

1. It is 15 to 20% cheaper than the strip footing.

2. Less material required.

3. Digging is normal so the work is carried out for anytime of the year.

4. No back filling is required.

5. Shoring is not required.

6. Dewatering is not necessary.

Page 16: Under reamed piles

16 Reference

ADVENCED CONSTRUCTION TECHNOLOGY, DR. R.P.RETHALIYA..

Page 17: Under reamed piles

17

THANK YOU