Upload
soumyadeep-nag
View
487
Download
3
Embed Size (px)
Citation preview
Trends and Challenges in the Operation Of Pumped-
Storage Hydro-power Plants
Dr Kwang Y Lee
Introduction
Pumped hydro storage
bull Pure off-stream PHS - which rely entirely on water that were previously pumped into an upper reservoir as the source of energy ndash also referred to as closed loop system
bull Combined PHS - which use both pumped water and natural stream flow water to generate power
bull Turbine to grid efficiency ndash 50 to 80 (GE proposes gt95)bull Earliest operation in 1890 in Switzerland with separate pump impeller and
propeller turbinebull The arrival of single pump-turbine in 1950rsquos changed the market for PHSbull Rapid growth in PHS market can be mainly attributed to the increased
penetration of intermittent renewable energy resourcesbull Most recent advances include
ndash Variable speed PHSndash Sea water PHSndash Compressed air PHSndash Under-sea PHS
Barriers to PHS and overcoming them
bull High investment costs (around 536 to 2474 $kW) and the difficulty to recover this cost
bull Factors affecting recovery of investment costndash Income from price arbitrage between peak and off-peak hours is
enough in just a few electricity markets ndash PSHPs are obliged to pay grid fees for the usage of transmission
lines when they are consuming as it occurs in many power systems such as the Spanish system or
ndash high water fees for utilizing rivers or lakes reduce profits of PSHP operation
bull Hence the operation in only peak-shaving based markets is not profitable However many research in the literature have displayed the operation of the PHS plant to be more profitable in the secondary regulation market
Advantages of PHS
bull Regulatory and reserve power - can participate in various reserves and regulatory actions of the market
bull Provides the highest power and energy density
bull Quick start and Black start capability
bull High ramp rate and instant voltage and frequency support capability
bull High round-trip efficiency gt80
[1]
bull Technical maturitybull Significant remaining potential
Image Courtesy - NREL
Peak shaving mode
Image courtesy - Wikipedia
Profitability and bidding
bull Bidding strategy 1- peak shaving
bull Bidding strategy 2- ancillary services
bull Bidding strategy 3- biding simultaneously in both can almost double the profitability ndash requires heuristic optimization
Current market trends
bull Generating on week days and pumping on weekends have proved to be more profitable - They generate more on weekdays and pump more during weekends
bull Within a season generation and pumping schedules do not change much - Both generating and pumping hours are twice as much in winter than in summer
Current Challenges
bull Considering the uncertainty of real time use of regulation reserves
bull Revising the methods used to determine long term guidelines
bull Defining the optimal strategy for PSHPs with variable speed and hydraulic short-circuit operation
bull Modeling and design of hydraulic short circuit and variable speed machines and equipments and their grid connected advantages
Modern trends in pumped hydro
Evolution of Pumped Hydro
Separate pump and turbine
bull Two hydraulic machines
bull Two different shafts
bull Two electrical machines
Reversible pump turbine
bull One hydraulic machine
bull One shaft
bull One electric machine
Ternary set
bull Two hydraulic machines but same shaft
bull One electric machine
bull One shaft
bull Voithbull Seimensbull GE
Variable speed pumped hydro -Benefits
bull Benefits of variable speed operation
ndash Variable speed could help avoid draft tube pressure oscillations and cavitation among others
ndash Improved performance at off-design heads and improved range of heads
ndash Improved performance at off-design discharge and improved range of discharge
ndash Variable speed allows power consumed in the pumping mode to be varied over a range of outputs
ndash Variable speed also allows the turbine to operate the turbine at peak efficiencies over a wide range of its operating band
ndash Doubly fed induction generators fed through thyristor cyclo-converters are extremely beneficial for grid connected operations
Speed discharge characteristics of a turbine [2]
Variable speed operation - Control
bull 2 important methods similar to wind are ndash Pitch control ndash high flow rate ndash comparatively
small time constant
ndash Load control ndash medium flow rate ndash slow due to the large inertia involved
These equations are used to control the turbine gate angle and the speed so as
to obtain power output set-point under any particular head (fortunately they are
linear)
Variable Speed operation ndash Electrical machine
bull Static frequency converters have been used before but for smaller purposes (lt30 MVA) but for ratings above 250 MVA this solution becomes infeasible Thus the use of DFIM sets into the picture The converter needed for the DFIM depends directly upon the slip for which it is optimized to operate
bull The wound rotor induction machine has come up from the wind turbine industry Control of DFIM is possible through rotor and stator side converters
bull ldquoVARSPEEDrdquo by ABB is one famous commercial example advantages of which arendash Increased overall efficiencyndash Possibility of active power control in pumping mode ndash Possibility of reactive power control at interconnection point to the grid
Variable speed operation - DFIM
bull DFIM is advantageous over the synchronous machine as itrsquos speed stabilizes faster than a conventional synchronous machine for a grid side voltage drop event Excellent self-stabilizing properties
bull The machine can be used to instantaneously inject real power into the grid The reduction in reference speed can be used to extract the required real power Conventional plants need accumulated steam for the same Thus they can be used for grid control
bull Due to the possibility of speed adjustment the pump power may easily be adjusted This feature is also advantageous for grid control Variable speed pumping
Modern hydraulic equipment - Ternary Set
Pelton turbine Clutch and gear(torque coupler)
Multi-stage centrifugal pump
Tail-raceOutlet of pump
Turbine inlet scroll
Pumped storage hydraulic equipment with pump and turbine as separate hydraulic machines but on
the same shaft [3]
Ternary Set
bull Using two separate hydraulic devices the direction of rotation will be the same in both modes of operation This is very convenient as far as uniform stress on the structure and electrical control and connections are concerned
bull The change-over time required between pumping and generating mode can be reduced due to the pre-rotating single ndash shaft Thereby enabling faster controls and no additional starting power requirements
bull Two modes are separated by a clutch which can engage either mode in no time
Hydraulic short-circuit
bull In a ternary set it is possible to transfer the water from the pump to the turbine and drive the turbine and feed the upper reservoir simultaneously It may also be possible to supplement the flow of water into the turbine and hence reduce the discharge from the upper reservoir In both cases the ternary set acts as a controllable load
bull Direct shaft control is better and faster than generator control due to the large generator inertia Hence hydraulic short circuit enables the operation of a fixed load on the same shaft The difference between the pump power and the turbine power is only fed to the grid
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Introduction
Pumped hydro storage
bull Pure off-stream PHS - which rely entirely on water that were previously pumped into an upper reservoir as the source of energy ndash also referred to as closed loop system
bull Combined PHS - which use both pumped water and natural stream flow water to generate power
bull Turbine to grid efficiency ndash 50 to 80 (GE proposes gt95)bull Earliest operation in 1890 in Switzerland with separate pump impeller and
propeller turbinebull The arrival of single pump-turbine in 1950rsquos changed the market for PHSbull Rapid growth in PHS market can be mainly attributed to the increased
penetration of intermittent renewable energy resourcesbull Most recent advances include
ndash Variable speed PHSndash Sea water PHSndash Compressed air PHSndash Under-sea PHS
Barriers to PHS and overcoming them
bull High investment costs (around 536 to 2474 $kW) and the difficulty to recover this cost
bull Factors affecting recovery of investment costndash Income from price arbitrage between peak and off-peak hours is
enough in just a few electricity markets ndash PSHPs are obliged to pay grid fees for the usage of transmission
lines when they are consuming as it occurs in many power systems such as the Spanish system or
ndash high water fees for utilizing rivers or lakes reduce profits of PSHP operation
bull Hence the operation in only peak-shaving based markets is not profitable However many research in the literature have displayed the operation of the PHS plant to be more profitable in the secondary regulation market
Advantages of PHS
bull Regulatory and reserve power - can participate in various reserves and regulatory actions of the market
bull Provides the highest power and energy density
bull Quick start and Black start capability
bull High ramp rate and instant voltage and frequency support capability
bull High round-trip efficiency gt80
[1]
bull Technical maturitybull Significant remaining potential
Image Courtesy - NREL
Peak shaving mode
Image courtesy - Wikipedia
Profitability and bidding
bull Bidding strategy 1- peak shaving
bull Bidding strategy 2- ancillary services
bull Bidding strategy 3- biding simultaneously in both can almost double the profitability ndash requires heuristic optimization
Current market trends
bull Generating on week days and pumping on weekends have proved to be more profitable - They generate more on weekdays and pump more during weekends
bull Within a season generation and pumping schedules do not change much - Both generating and pumping hours are twice as much in winter than in summer
Current Challenges
bull Considering the uncertainty of real time use of regulation reserves
bull Revising the methods used to determine long term guidelines
bull Defining the optimal strategy for PSHPs with variable speed and hydraulic short-circuit operation
bull Modeling and design of hydraulic short circuit and variable speed machines and equipments and their grid connected advantages
Modern trends in pumped hydro
Evolution of Pumped Hydro
Separate pump and turbine
bull Two hydraulic machines
bull Two different shafts
bull Two electrical machines
Reversible pump turbine
bull One hydraulic machine
bull One shaft
bull One electric machine
Ternary set
bull Two hydraulic machines but same shaft
bull One electric machine
bull One shaft
bull Voithbull Seimensbull GE
Variable speed pumped hydro -Benefits
bull Benefits of variable speed operation
ndash Variable speed could help avoid draft tube pressure oscillations and cavitation among others
ndash Improved performance at off-design heads and improved range of heads
ndash Improved performance at off-design discharge and improved range of discharge
ndash Variable speed allows power consumed in the pumping mode to be varied over a range of outputs
ndash Variable speed also allows the turbine to operate the turbine at peak efficiencies over a wide range of its operating band
ndash Doubly fed induction generators fed through thyristor cyclo-converters are extremely beneficial for grid connected operations
Speed discharge characteristics of a turbine [2]
Variable speed operation - Control
bull 2 important methods similar to wind are ndash Pitch control ndash high flow rate ndash comparatively
small time constant
ndash Load control ndash medium flow rate ndash slow due to the large inertia involved
These equations are used to control the turbine gate angle and the speed so as
to obtain power output set-point under any particular head (fortunately they are
linear)
Variable Speed operation ndash Electrical machine
bull Static frequency converters have been used before but for smaller purposes (lt30 MVA) but for ratings above 250 MVA this solution becomes infeasible Thus the use of DFIM sets into the picture The converter needed for the DFIM depends directly upon the slip for which it is optimized to operate
bull The wound rotor induction machine has come up from the wind turbine industry Control of DFIM is possible through rotor and stator side converters
bull ldquoVARSPEEDrdquo by ABB is one famous commercial example advantages of which arendash Increased overall efficiencyndash Possibility of active power control in pumping mode ndash Possibility of reactive power control at interconnection point to the grid
Variable speed operation - DFIM
bull DFIM is advantageous over the synchronous machine as itrsquos speed stabilizes faster than a conventional synchronous machine for a grid side voltage drop event Excellent self-stabilizing properties
bull The machine can be used to instantaneously inject real power into the grid The reduction in reference speed can be used to extract the required real power Conventional plants need accumulated steam for the same Thus they can be used for grid control
bull Due to the possibility of speed adjustment the pump power may easily be adjusted This feature is also advantageous for grid control Variable speed pumping
Modern hydraulic equipment - Ternary Set
Pelton turbine Clutch and gear(torque coupler)
Multi-stage centrifugal pump
Tail-raceOutlet of pump
Turbine inlet scroll
Pumped storage hydraulic equipment with pump and turbine as separate hydraulic machines but on
the same shaft [3]
Ternary Set
bull Using two separate hydraulic devices the direction of rotation will be the same in both modes of operation This is very convenient as far as uniform stress on the structure and electrical control and connections are concerned
bull The change-over time required between pumping and generating mode can be reduced due to the pre-rotating single ndash shaft Thereby enabling faster controls and no additional starting power requirements
bull Two modes are separated by a clutch which can engage either mode in no time
Hydraulic short-circuit
bull In a ternary set it is possible to transfer the water from the pump to the turbine and drive the turbine and feed the upper reservoir simultaneously It may also be possible to supplement the flow of water into the turbine and hence reduce the discharge from the upper reservoir In both cases the ternary set acts as a controllable load
bull Direct shaft control is better and faster than generator control due to the large generator inertia Hence hydraulic short circuit enables the operation of a fixed load on the same shaft The difference between the pump power and the turbine power is only fed to the grid
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Pumped hydro storage
bull Pure off-stream PHS - which rely entirely on water that were previously pumped into an upper reservoir as the source of energy ndash also referred to as closed loop system
bull Combined PHS - which use both pumped water and natural stream flow water to generate power
bull Turbine to grid efficiency ndash 50 to 80 (GE proposes gt95)bull Earliest operation in 1890 in Switzerland with separate pump impeller and
propeller turbinebull The arrival of single pump-turbine in 1950rsquos changed the market for PHSbull Rapid growth in PHS market can be mainly attributed to the increased
penetration of intermittent renewable energy resourcesbull Most recent advances include
ndash Variable speed PHSndash Sea water PHSndash Compressed air PHSndash Under-sea PHS
Barriers to PHS and overcoming them
bull High investment costs (around 536 to 2474 $kW) and the difficulty to recover this cost
bull Factors affecting recovery of investment costndash Income from price arbitrage between peak and off-peak hours is
enough in just a few electricity markets ndash PSHPs are obliged to pay grid fees for the usage of transmission
lines when they are consuming as it occurs in many power systems such as the Spanish system or
ndash high water fees for utilizing rivers or lakes reduce profits of PSHP operation
bull Hence the operation in only peak-shaving based markets is not profitable However many research in the literature have displayed the operation of the PHS plant to be more profitable in the secondary regulation market
Advantages of PHS
bull Regulatory and reserve power - can participate in various reserves and regulatory actions of the market
bull Provides the highest power and energy density
bull Quick start and Black start capability
bull High ramp rate and instant voltage and frequency support capability
bull High round-trip efficiency gt80
[1]
bull Technical maturitybull Significant remaining potential
Image Courtesy - NREL
Peak shaving mode
Image courtesy - Wikipedia
Profitability and bidding
bull Bidding strategy 1- peak shaving
bull Bidding strategy 2- ancillary services
bull Bidding strategy 3- biding simultaneously in both can almost double the profitability ndash requires heuristic optimization
Current market trends
bull Generating on week days and pumping on weekends have proved to be more profitable - They generate more on weekdays and pump more during weekends
bull Within a season generation and pumping schedules do not change much - Both generating and pumping hours are twice as much in winter than in summer
Current Challenges
bull Considering the uncertainty of real time use of regulation reserves
bull Revising the methods used to determine long term guidelines
bull Defining the optimal strategy for PSHPs with variable speed and hydraulic short-circuit operation
bull Modeling and design of hydraulic short circuit and variable speed machines and equipments and their grid connected advantages
Modern trends in pumped hydro
Evolution of Pumped Hydro
Separate pump and turbine
bull Two hydraulic machines
bull Two different shafts
bull Two electrical machines
Reversible pump turbine
bull One hydraulic machine
bull One shaft
bull One electric machine
Ternary set
bull Two hydraulic machines but same shaft
bull One electric machine
bull One shaft
bull Voithbull Seimensbull GE
Variable speed pumped hydro -Benefits
bull Benefits of variable speed operation
ndash Variable speed could help avoid draft tube pressure oscillations and cavitation among others
ndash Improved performance at off-design heads and improved range of heads
ndash Improved performance at off-design discharge and improved range of discharge
ndash Variable speed allows power consumed in the pumping mode to be varied over a range of outputs
ndash Variable speed also allows the turbine to operate the turbine at peak efficiencies over a wide range of its operating band
ndash Doubly fed induction generators fed through thyristor cyclo-converters are extremely beneficial for grid connected operations
Speed discharge characteristics of a turbine [2]
Variable speed operation - Control
bull 2 important methods similar to wind are ndash Pitch control ndash high flow rate ndash comparatively
small time constant
ndash Load control ndash medium flow rate ndash slow due to the large inertia involved
These equations are used to control the turbine gate angle and the speed so as
to obtain power output set-point under any particular head (fortunately they are
linear)
Variable Speed operation ndash Electrical machine
bull Static frequency converters have been used before but for smaller purposes (lt30 MVA) but for ratings above 250 MVA this solution becomes infeasible Thus the use of DFIM sets into the picture The converter needed for the DFIM depends directly upon the slip for which it is optimized to operate
bull The wound rotor induction machine has come up from the wind turbine industry Control of DFIM is possible through rotor and stator side converters
bull ldquoVARSPEEDrdquo by ABB is one famous commercial example advantages of which arendash Increased overall efficiencyndash Possibility of active power control in pumping mode ndash Possibility of reactive power control at interconnection point to the grid
Variable speed operation - DFIM
bull DFIM is advantageous over the synchronous machine as itrsquos speed stabilizes faster than a conventional synchronous machine for a grid side voltage drop event Excellent self-stabilizing properties
bull The machine can be used to instantaneously inject real power into the grid The reduction in reference speed can be used to extract the required real power Conventional plants need accumulated steam for the same Thus they can be used for grid control
bull Due to the possibility of speed adjustment the pump power may easily be adjusted This feature is also advantageous for grid control Variable speed pumping
Modern hydraulic equipment - Ternary Set
Pelton turbine Clutch and gear(torque coupler)
Multi-stage centrifugal pump
Tail-raceOutlet of pump
Turbine inlet scroll
Pumped storage hydraulic equipment with pump and turbine as separate hydraulic machines but on
the same shaft [3]
Ternary Set
bull Using two separate hydraulic devices the direction of rotation will be the same in both modes of operation This is very convenient as far as uniform stress on the structure and electrical control and connections are concerned
bull The change-over time required between pumping and generating mode can be reduced due to the pre-rotating single ndash shaft Thereby enabling faster controls and no additional starting power requirements
bull Two modes are separated by a clutch which can engage either mode in no time
Hydraulic short-circuit
bull In a ternary set it is possible to transfer the water from the pump to the turbine and drive the turbine and feed the upper reservoir simultaneously It may also be possible to supplement the flow of water into the turbine and hence reduce the discharge from the upper reservoir In both cases the ternary set acts as a controllable load
bull Direct shaft control is better and faster than generator control due to the large generator inertia Hence hydraulic short circuit enables the operation of a fixed load on the same shaft The difference between the pump power and the turbine power is only fed to the grid
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Barriers to PHS and overcoming them
bull High investment costs (around 536 to 2474 $kW) and the difficulty to recover this cost
bull Factors affecting recovery of investment costndash Income from price arbitrage between peak and off-peak hours is
enough in just a few electricity markets ndash PSHPs are obliged to pay grid fees for the usage of transmission
lines when they are consuming as it occurs in many power systems such as the Spanish system or
ndash high water fees for utilizing rivers or lakes reduce profits of PSHP operation
bull Hence the operation in only peak-shaving based markets is not profitable However many research in the literature have displayed the operation of the PHS plant to be more profitable in the secondary regulation market
Advantages of PHS
bull Regulatory and reserve power - can participate in various reserves and regulatory actions of the market
bull Provides the highest power and energy density
bull Quick start and Black start capability
bull High ramp rate and instant voltage and frequency support capability
bull High round-trip efficiency gt80
[1]
bull Technical maturitybull Significant remaining potential
Image Courtesy - NREL
Peak shaving mode
Image courtesy - Wikipedia
Profitability and bidding
bull Bidding strategy 1- peak shaving
bull Bidding strategy 2- ancillary services
bull Bidding strategy 3- biding simultaneously in both can almost double the profitability ndash requires heuristic optimization
Current market trends
bull Generating on week days and pumping on weekends have proved to be more profitable - They generate more on weekdays and pump more during weekends
bull Within a season generation and pumping schedules do not change much - Both generating and pumping hours are twice as much in winter than in summer
Current Challenges
bull Considering the uncertainty of real time use of regulation reserves
bull Revising the methods used to determine long term guidelines
bull Defining the optimal strategy for PSHPs with variable speed and hydraulic short-circuit operation
bull Modeling and design of hydraulic short circuit and variable speed machines and equipments and their grid connected advantages
Modern trends in pumped hydro
Evolution of Pumped Hydro
Separate pump and turbine
bull Two hydraulic machines
bull Two different shafts
bull Two electrical machines
Reversible pump turbine
bull One hydraulic machine
bull One shaft
bull One electric machine
Ternary set
bull Two hydraulic machines but same shaft
bull One electric machine
bull One shaft
bull Voithbull Seimensbull GE
Variable speed pumped hydro -Benefits
bull Benefits of variable speed operation
ndash Variable speed could help avoid draft tube pressure oscillations and cavitation among others
ndash Improved performance at off-design heads and improved range of heads
ndash Improved performance at off-design discharge and improved range of discharge
ndash Variable speed allows power consumed in the pumping mode to be varied over a range of outputs
ndash Variable speed also allows the turbine to operate the turbine at peak efficiencies over a wide range of its operating band
ndash Doubly fed induction generators fed through thyristor cyclo-converters are extremely beneficial for grid connected operations
Speed discharge characteristics of a turbine [2]
Variable speed operation - Control
bull 2 important methods similar to wind are ndash Pitch control ndash high flow rate ndash comparatively
small time constant
ndash Load control ndash medium flow rate ndash slow due to the large inertia involved
These equations are used to control the turbine gate angle and the speed so as
to obtain power output set-point under any particular head (fortunately they are
linear)
Variable Speed operation ndash Electrical machine
bull Static frequency converters have been used before but for smaller purposes (lt30 MVA) but for ratings above 250 MVA this solution becomes infeasible Thus the use of DFIM sets into the picture The converter needed for the DFIM depends directly upon the slip for which it is optimized to operate
bull The wound rotor induction machine has come up from the wind turbine industry Control of DFIM is possible through rotor and stator side converters
bull ldquoVARSPEEDrdquo by ABB is one famous commercial example advantages of which arendash Increased overall efficiencyndash Possibility of active power control in pumping mode ndash Possibility of reactive power control at interconnection point to the grid
Variable speed operation - DFIM
bull DFIM is advantageous over the synchronous machine as itrsquos speed stabilizes faster than a conventional synchronous machine for a grid side voltage drop event Excellent self-stabilizing properties
bull The machine can be used to instantaneously inject real power into the grid The reduction in reference speed can be used to extract the required real power Conventional plants need accumulated steam for the same Thus they can be used for grid control
bull Due to the possibility of speed adjustment the pump power may easily be adjusted This feature is also advantageous for grid control Variable speed pumping
Modern hydraulic equipment - Ternary Set
Pelton turbine Clutch and gear(torque coupler)
Multi-stage centrifugal pump
Tail-raceOutlet of pump
Turbine inlet scroll
Pumped storage hydraulic equipment with pump and turbine as separate hydraulic machines but on
the same shaft [3]
Ternary Set
bull Using two separate hydraulic devices the direction of rotation will be the same in both modes of operation This is very convenient as far as uniform stress on the structure and electrical control and connections are concerned
bull The change-over time required between pumping and generating mode can be reduced due to the pre-rotating single ndash shaft Thereby enabling faster controls and no additional starting power requirements
bull Two modes are separated by a clutch which can engage either mode in no time
Hydraulic short-circuit
bull In a ternary set it is possible to transfer the water from the pump to the turbine and drive the turbine and feed the upper reservoir simultaneously It may also be possible to supplement the flow of water into the turbine and hence reduce the discharge from the upper reservoir In both cases the ternary set acts as a controllable load
bull Direct shaft control is better and faster than generator control due to the large generator inertia Hence hydraulic short circuit enables the operation of a fixed load on the same shaft The difference between the pump power and the turbine power is only fed to the grid
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Advantages of PHS
bull Regulatory and reserve power - can participate in various reserves and regulatory actions of the market
bull Provides the highest power and energy density
bull Quick start and Black start capability
bull High ramp rate and instant voltage and frequency support capability
bull High round-trip efficiency gt80
[1]
bull Technical maturitybull Significant remaining potential
Image Courtesy - NREL
Peak shaving mode
Image courtesy - Wikipedia
Profitability and bidding
bull Bidding strategy 1- peak shaving
bull Bidding strategy 2- ancillary services
bull Bidding strategy 3- biding simultaneously in both can almost double the profitability ndash requires heuristic optimization
Current market trends
bull Generating on week days and pumping on weekends have proved to be more profitable - They generate more on weekdays and pump more during weekends
bull Within a season generation and pumping schedules do not change much - Both generating and pumping hours are twice as much in winter than in summer
Current Challenges
bull Considering the uncertainty of real time use of regulation reserves
bull Revising the methods used to determine long term guidelines
bull Defining the optimal strategy for PSHPs with variable speed and hydraulic short-circuit operation
bull Modeling and design of hydraulic short circuit and variable speed machines and equipments and their grid connected advantages
Modern trends in pumped hydro
Evolution of Pumped Hydro
Separate pump and turbine
bull Two hydraulic machines
bull Two different shafts
bull Two electrical machines
Reversible pump turbine
bull One hydraulic machine
bull One shaft
bull One electric machine
Ternary set
bull Two hydraulic machines but same shaft
bull One electric machine
bull One shaft
bull Voithbull Seimensbull GE
Variable speed pumped hydro -Benefits
bull Benefits of variable speed operation
ndash Variable speed could help avoid draft tube pressure oscillations and cavitation among others
ndash Improved performance at off-design heads and improved range of heads
ndash Improved performance at off-design discharge and improved range of discharge
ndash Variable speed allows power consumed in the pumping mode to be varied over a range of outputs
ndash Variable speed also allows the turbine to operate the turbine at peak efficiencies over a wide range of its operating band
ndash Doubly fed induction generators fed through thyristor cyclo-converters are extremely beneficial for grid connected operations
Speed discharge characteristics of a turbine [2]
Variable speed operation - Control
bull 2 important methods similar to wind are ndash Pitch control ndash high flow rate ndash comparatively
small time constant
ndash Load control ndash medium flow rate ndash slow due to the large inertia involved
These equations are used to control the turbine gate angle and the speed so as
to obtain power output set-point under any particular head (fortunately they are
linear)
Variable Speed operation ndash Electrical machine
bull Static frequency converters have been used before but for smaller purposes (lt30 MVA) but for ratings above 250 MVA this solution becomes infeasible Thus the use of DFIM sets into the picture The converter needed for the DFIM depends directly upon the slip for which it is optimized to operate
bull The wound rotor induction machine has come up from the wind turbine industry Control of DFIM is possible through rotor and stator side converters
bull ldquoVARSPEEDrdquo by ABB is one famous commercial example advantages of which arendash Increased overall efficiencyndash Possibility of active power control in pumping mode ndash Possibility of reactive power control at interconnection point to the grid
Variable speed operation - DFIM
bull DFIM is advantageous over the synchronous machine as itrsquos speed stabilizes faster than a conventional synchronous machine for a grid side voltage drop event Excellent self-stabilizing properties
bull The machine can be used to instantaneously inject real power into the grid The reduction in reference speed can be used to extract the required real power Conventional plants need accumulated steam for the same Thus they can be used for grid control
bull Due to the possibility of speed adjustment the pump power may easily be adjusted This feature is also advantageous for grid control Variable speed pumping
Modern hydraulic equipment - Ternary Set
Pelton turbine Clutch and gear(torque coupler)
Multi-stage centrifugal pump
Tail-raceOutlet of pump
Turbine inlet scroll
Pumped storage hydraulic equipment with pump and turbine as separate hydraulic machines but on
the same shaft [3]
Ternary Set
bull Using two separate hydraulic devices the direction of rotation will be the same in both modes of operation This is very convenient as far as uniform stress on the structure and electrical control and connections are concerned
bull The change-over time required between pumping and generating mode can be reduced due to the pre-rotating single ndash shaft Thereby enabling faster controls and no additional starting power requirements
bull Two modes are separated by a clutch which can engage either mode in no time
Hydraulic short-circuit
bull In a ternary set it is possible to transfer the water from the pump to the turbine and drive the turbine and feed the upper reservoir simultaneously It may also be possible to supplement the flow of water into the turbine and hence reduce the discharge from the upper reservoir In both cases the ternary set acts as a controllable load
bull Direct shaft control is better and faster than generator control due to the large generator inertia Hence hydraulic short circuit enables the operation of a fixed load on the same shaft The difference between the pump power and the turbine power is only fed to the grid
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Image Courtesy - NREL
Peak shaving mode
Image courtesy - Wikipedia
Profitability and bidding
bull Bidding strategy 1- peak shaving
bull Bidding strategy 2- ancillary services
bull Bidding strategy 3- biding simultaneously in both can almost double the profitability ndash requires heuristic optimization
Current market trends
bull Generating on week days and pumping on weekends have proved to be more profitable - They generate more on weekdays and pump more during weekends
bull Within a season generation and pumping schedules do not change much - Both generating and pumping hours are twice as much in winter than in summer
Current Challenges
bull Considering the uncertainty of real time use of regulation reserves
bull Revising the methods used to determine long term guidelines
bull Defining the optimal strategy for PSHPs with variable speed and hydraulic short-circuit operation
bull Modeling and design of hydraulic short circuit and variable speed machines and equipments and their grid connected advantages
Modern trends in pumped hydro
Evolution of Pumped Hydro
Separate pump and turbine
bull Two hydraulic machines
bull Two different shafts
bull Two electrical machines
Reversible pump turbine
bull One hydraulic machine
bull One shaft
bull One electric machine
Ternary set
bull Two hydraulic machines but same shaft
bull One electric machine
bull One shaft
bull Voithbull Seimensbull GE
Variable speed pumped hydro -Benefits
bull Benefits of variable speed operation
ndash Variable speed could help avoid draft tube pressure oscillations and cavitation among others
ndash Improved performance at off-design heads and improved range of heads
ndash Improved performance at off-design discharge and improved range of discharge
ndash Variable speed allows power consumed in the pumping mode to be varied over a range of outputs
ndash Variable speed also allows the turbine to operate the turbine at peak efficiencies over a wide range of its operating band
ndash Doubly fed induction generators fed through thyristor cyclo-converters are extremely beneficial for grid connected operations
Speed discharge characteristics of a turbine [2]
Variable speed operation - Control
bull 2 important methods similar to wind are ndash Pitch control ndash high flow rate ndash comparatively
small time constant
ndash Load control ndash medium flow rate ndash slow due to the large inertia involved
These equations are used to control the turbine gate angle and the speed so as
to obtain power output set-point under any particular head (fortunately they are
linear)
Variable Speed operation ndash Electrical machine
bull Static frequency converters have been used before but for smaller purposes (lt30 MVA) but for ratings above 250 MVA this solution becomes infeasible Thus the use of DFIM sets into the picture The converter needed for the DFIM depends directly upon the slip for which it is optimized to operate
bull The wound rotor induction machine has come up from the wind turbine industry Control of DFIM is possible through rotor and stator side converters
bull ldquoVARSPEEDrdquo by ABB is one famous commercial example advantages of which arendash Increased overall efficiencyndash Possibility of active power control in pumping mode ndash Possibility of reactive power control at interconnection point to the grid
Variable speed operation - DFIM
bull DFIM is advantageous over the synchronous machine as itrsquos speed stabilizes faster than a conventional synchronous machine for a grid side voltage drop event Excellent self-stabilizing properties
bull The machine can be used to instantaneously inject real power into the grid The reduction in reference speed can be used to extract the required real power Conventional plants need accumulated steam for the same Thus they can be used for grid control
bull Due to the possibility of speed adjustment the pump power may easily be adjusted This feature is also advantageous for grid control Variable speed pumping
Modern hydraulic equipment - Ternary Set
Pelton turbine Clutch and gear(torque coupler)
Multi-stage centrifugal pump
Tail-raceOutlet of pump
Turbine inlet scroll
Pumped storage hydraulic equipment with pump and turbine as separate hydraulic machines but on
the same shaft [3]
Ternary Set
bull Using two separate hydraulic devices the direction of rotation will be the same in both modes of operation This is very convenient as far as uniform stress on the structure and electrical control and connections are concerned
bull The change-over time required between pumping and generating mode can be reduced due to the pre-rotating single ndash shaft Thereby enabling faster controls and no additional starting power requirements
bull Two modes are separated by a clutch which can engage either mode in no time
Hydraulic short-circuit
bull In a ternary set it is possible to transfer the water from the pump to the turbine and drive the turbine and feed the upper reservoir simultaneously It may also be possible to supplement the flow of water into the turbine and hence reduce the discharge from the upper reservoir In both cases the ternary set acts as a controllable load
bull Direct shaft control is better and faster than generator control due to the large generator inertia Hence hydraulic short circuit enables the operation of a fixed load on the same shaft The difference between the pump power and the turbine power is only fed to the grid
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Peak shaving mode
Image courtesy - Wikipedia
Profitability and bidding
bull Bidding strategy 1- peak shaving
bull Bidding strategy 2- ancillary services
bull Bidding strategy 3- biding simultaneously in both can almost double the profitability ndash requires heuristic optimization
Current market trends
bull Generating on week days and pumping on weekends have proved to be more profitable - They generate more on weekdays and pump more during weekends
bull Within a season generation and pumping schedules do not change much - Both generating and pumping hours are twice as much in winter than in summer
Current Challenges
bull Considering the uncertainty of real time use of regulation reserves
bull Revising the methods used to determine long term guidelines
bull Defining the optimal strategy for PSHPs with variable speed and hydraulic short-circuit operation
bull Modeling and design of hydraulic short circuit and variable speed machines and equipments and their grid connected advantages
Modern trends in pumped hydro
Evolution of Pumped Hydro
Separate pump and turbine
bull Two hydraulic machines
bull Two different shafts
bull Two electrical machines
Reversible pump turbine
bull One hydraulic machine
bull One shaft
bull One electric machine
Ternary set
bull Two hydraulic machines but same shaft
bull One electric machine
bull One shaft
bull Voithbull Seimensbull GE
Variable speed pumped hydro -Benefits
bull Benefits of variable speed operation
ndash Variable speed could help avoid draft tube pressure oscillations and cavitation among others
ndash Improved performance at off-design heads and improved range of heads
ndash Improved performance at off-design discharge and improved range of discharge
ndash Variable speed allows power consumed in the pumping mode to be varied over a range of outputs
ndash Variable speed also allows the turbine to operate the turbine at peak efficiencies over a wide range of its operating band
ndash Doubly fed induction generators fed through thyristor cyclo-converters are extremely beneficial for grid connected operations
Speed discharge characteristics of a turbine [2]
Variable speed operation - Control
bull 2 important methods similar to wind are ndash Pitch control ndash high flow rate ndash comparatively
small time constant
ndash Load control ndash medium flow rate ndash slow due to the large inertia involved
These equations are used to control the turbine gate angle and the speed so as
to obtain power output set-point under any particular head (fortunately they are
linear)
Variable Speed operation ndash Electrical machine
bull Static frequency converters have been used before but for smaller purposes (lt30 MVA) but for ratings above 250 MVA this solution becomes infeasible Thus the use of DFIM sets into the picture The converter needed for the DFIM depends directly upon the slip for which it is optimized to operate
bull The wound rotor induction machine has come up from the wind turbine industry Control of DFIM is possible through rotor and stator side converters
bull ldquoVARSPEEDrdquo by ABB is one famous commercial example advantages of which arendash Increased overall efficiencyndash Possibility of active power control in pumping mode ndash Possibility of reactive power control at interconnection point to the grid
Variable speed operation - DFIM
bull DFIM is advantageous over the synchronous machine as itrsquos speed stabilizes faster than a conventional synchronous machine for a grid side voltage drop event Excellent self-stabilizing properties
bull The machine can be used to instantaneously inject real power into the grid The reduction in reference speed can be used to extract the required real power Conventional plants need accumulated steam for the same Thus they can be used for grid control
bull Due to the possibility of speed adjustment the pump power may easily be adjusted This feature is also advantageous for grid control Variable speed pumping
Modern hydraulic equipment - Ternary Set
Pelton turbine Clutch and gear(torque coupler)
Multi-stage centrifugal pump
Tail-raceOutlet of pump
Turbine inlet scroll
Pumped storage hydraulic equipment with pump and turbine as separate hydraulic machines but on
the same shaft [3]
Ternary Set
bull Using two separate hydraulic devices the direction of rotation will be the same in both modes of operation This is very convenient as far as uniform stress on the structure and electrical control and connections are concerned
bull The change-over time required between pumping and generating mode can be reduced due to the pre-rotating single ndash shaft Thereby enabling faster controls and no additional starting power requirements
bull Two modes are separated by a clutch which can engage either mode in no time
Hydraulic short-circuit
bull In a ternary set it is possible to transfer the water from the pump to the turbine and drive the turbine and feed the upper reservoir simultaneously It may also be possible to supplement the flow of water into the turbine and hence reduce the discharge from the upper reservoir In both cases the ternary set acts as a controllable load
bull Direct shaft control is better and faster than generator control due to the large generator inertia Hence hydraulic short circuit enables the operation of a fixed load on the same shaft The difference between the pump power and the turbine power is only fed to the grid
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Profitability and bidding
bull Bidding strategy 1- peak shaving
bull Bidding strategy 2- ancillary services
bull Bidding strategy 3- biding simultaneously in both can almost double the profitability ndash requires heuristic optimization
Current market trends
bull Generating on week days and pumping on weekends have proved to be more profitable - They generate more on weekdays and pump more during weekends
bull Within a season generation and pumping schedules do not change much - Both generating and pumping hours are twice as much in winter than in summer
Current Challenges
bull Considering the uncertainty of real time use of regulation reserves
bull Revising the methods used to determine long term guidelines
bull Defining the optimal strategy for PSHPs with variable speed and hydraulic short-circuit operation
bull Modeling and design of hydraulic short circuit and variable speed machines and equipments and their grid connected advantages
Modern trends in pumped hydro
Evolution of Pumped Hydro
Separate pump and turbine
bull Two hydraulic machines
bull Two different shafts
bull Two electrical machines
Reversible pump turbine
bull One hydraulic machine
bull One shaft
bull One electric machine
Ternary set
bull Two hydraulic machines but same shaft
bull One electric machine
bull One shaft
bull Voithbull Seimensbull GE
Variable speed pumped hydro -Benefits
bull Benefits of variable speed operation
ndash Variable speed could help avoid draft tube pressure oscillations and cavitation among others
ndash Improved performance at off-design heads and improved range of heads
ndash Improved performance at off-design discharge and improved range of discharge
ndash Variable speed allows power consumed in the pumping mode to be varied over a range of outputs
ndash Variable speed also allows the turbine to operate the turbine at peak efficiencies over a wide range of its operating band
ndash Doubly fed induction generators fed through thyristor cyclo-converters are extremely beneficial for grid connected operations
Speed discharge characteristics of a turbine [2]
Variable speed operation - Control
bull 2 important methods similar to wind are ndash Pitch control ndash high flow rate ndash comparatively
small time constant
ndash Load control ndash medium flow rate ndash slow due to the large inertia involved
These equations are used to control the turbine gate angle and the speed so as
to obtain power output set-point under any particular head (fortunately they are
linear)
Variable Speed operation ndash Electrical machine
bull Static frequency converters have been used before but for smaller purposes (lt30 MVA) but for ratings above 250 MVA this solution becomes infeasible Thus the use of DFIM sets into the picture The converter needed for the DFIM depends directly upon the slip for which it is optimized to operate
bull The wound rotor induction machine has come up from the wind turbine industry Control of DFIM is possible through rotor and stator side converters
bull ldquoVARSPEEDrdquo by ABB is one famous commercial example advantages of which arendash Increased overall efficiencyndash Possibility of active power control in pumping mode ndash Possibility of reactive power control at interconnection point to the grid
Variable speed operation - DFIM
bull DFIM is advantageous over the synchronous machine as itrsquos speed stabilizes faster than a conventional synchronous machine for a grid side voltage drop event Excellent self-stabilizing properties
bull The machine can be used to instantaneously inject real power into the grid The reduction in reference speed can be used to extract the required real power Conventional plants need accumulated steam for the same Thus they can be used for grid control
bull Due to the possibility of speed adjustment the pump power may easily be adjusted This feature is also advantageous for grid control Variable speed pumping
Modern hydraulic equipment - Ternary Set
Pelton turbine Clutch and gear(torque coupler)
Multi-stage centrifugal pump
Tail-raceOutlet of pump
Turbine inlet scroll
Pumped storage hydraulic equipment with pump and turbine as separate hydraulic machines but on
the same shaft [3]
Ternary Set
bull Using two separate hydraulic devices the direction of rotation will be the same in both modes of operation This is very convenient as far as uniform stress on the structure and electrical control and connections are concerned
bull The change-over time required between pumping and generating mode can be reduced due to the pre-rotating single ndash shaft Thereby enabling faster controls and no additional starting power requirements
bull Two modes are separated by a clutch which can engage either mode in no time
Hydraulic short-circuit
bull In a ternary set it is possible to transfer the water from the pump to the turbine and drive the turbine and feed the upper reservoir simultaneously It may also be possible to supplement the flow of water into the turbine and hence reduce the discharge from the upper reservoir In both cases the ternary set acts as a controllable load
bull Direct shaft control is better and faster than generator control due to the large generator inertia Hence hydraulic short circuit enables the operation of a fixed load on the same shaft The difference between the pump power and the turbine power is only fed to the grid
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Modern trends in pumped hydro
Evolution of Pumped Hydro
Separate pump and turbine
bull Two hydraulic machines
bull Two different shafts
bull Two electrical machines
Reversible pump turbine
bull One hydraulic machine
bull One shaft
bull One electric machine
Ternary set
bull Two hydraulic machines but same shaft
bull One electric machine
bull One shaft
bull Voithbull Seimensbull GE
Variable speed pumped hydro -Benefits
bull Benefits of variable speed operation
ndash Variable speed could help avoid draft tube pressure oscillations and cavitation among others
ndash Improved performance at off-design heads and improved range of heads
ndash Improved performance at off-design discharge and improved range of discharge
ndash Variable speed allows power consumed in the pumping mode to be varied over a range of outputs
ndash Variable speed also allows the turbine to operate the turbine at peak efficiencies over a wide range of its operating band
ndash Doubly fed induction generators fed through thyristor cyclo-converters are extremely beneficial for grid connected operations
Speed discharge characteristics of a turbine [2]
Variable speed operation - Control
bull 2 important methods similar to wind are ndash Pitch control ndash high flow rate ndash comparatively
small time constant
ndash Load control ndash medium flow rate ndash slow due to the large inertia involved
These equations are used to control the turbine gate angle and the speed so as
to obtain power output set-point under any particular head (fortunately they are
linear)
Variable Speed operation ndash Electrical machine
bull Static frequency converters have been used before but for smaller purposes (lt30 MVA) but for ratings above 250 MVA this solution becomes infeasible Thus the use of DFIM sets into the picture The converter needed for the DFIM depends directly upon the slip for which it is optimized to operate
bull The wound rotor induction machine has come up from the wind turbine industry Control of DFIM is possible through rotor and stator side converters
bull ldquoVARSPEEDrdquo by ABB is one famous commercial example advantages of which arendash Increased overall efficiencyndash Possibility of active power control in pumping mode ndash Possibility of reactive power control at interconnection point to the grid
Variable speed operation - DFIM
bull DFIM is advantageous over the synchronous machine as itrsquos speed stabilizes faster than a conventional synchronous machine for a grid side voltage drop event Excellent self-stabilizing properties
bull The machine can be used to instantaneously inject real power into the grid The reduction in reference speed can be used to extract the required real power Conventional plants need accumulated steam for the same Thus they can be used for grid control
bull Due to the possibility of speed adjustment the pump power may easily be adjusted This feature is also advantageous for grid control Variable speed pumping
Modern hydraulic equipment - Ternary Set
Pelton turbine Clutch and gear(torque coupler)
Multi-stage centrifugal pump
Tail-raceOutlet of pump
Turbine inlet scroll
Pumped storage hydraulic equipment with pump and turbine as separate hydraulic machines but on
the same shaft [3]
Ternary Set
bull Using two separate hydraulic devices the direction of rotation will be the same in both modes of operation This is very convenient as far as uniform stress on the structure and electrical control and connections are concerned
bull The change-over time required between pumping and generating mode can be reduced due to the pre-rotating single ndash shaft Thereby enabling faster controls and no additional starting power requirements
bull Two modes are separated by a clutch which can engage either mode in no time
Hydraulic short-circuit
bull In a ternary set it is possible to transfer the water from the pump to the turbine and drive the turbine and feed the upper reservoir simultaneously It may also be possible to supplement the flow of water into the turbine and hence reduce the discharge from the upper reservoir In both cases the ternary set acts as a controllable load
bull Direct shaft control is better and faster than generator control due to the large generator inertia Hence hydraulic short circuit enables the operation of a fixed load on the same shaft The difference between the pump power and the turbine power is only fed to the grid
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Evolution of Pumped Hydro
Separate pump and turbine
bull Two hydraulic machines
bull Two different shafts
bull Two electrical machines
Reversible pump turbine
bull One hydraulic machine
bull One shaft
bull One electric machine
Ternary set
bull Two hydraulic machines but same shaft
bull One electric machine
bull One shaft
bull Voithbull Seimensbull GE
Variable speed pumped hydro -Benefits
bull Benefits of variable speed operation
ndash Variable speed could help avoid draft tube pressure oscillations and cavitation among others
ndash Improved performance at off-design heads and improved range of heads
ndash Improved performance at off-design discharge and improved range of discharge
ndash Variable speed allows power consumed in the pumping mode to be varied over a range of outputs
ndash Variable speed also allows the turbine to operate the turbine at peak efficiencies over a wide range of its operating band
ndash Doubly fed induction generators fed through thyristor cyclo-converters are extremely beneficial for grid connected operations
Speed discharge characteristics of a turbine [2]
Variable speed operation - Control
bull 2 important methods similar to wind are ndash Pitch control ndash high flow rate ndash comparatively
small time constant
ndash Load control ndash medium flow rate ndash slow due to the large inertia involved
These equations are used to control the turbine gate angle and the speed so as
to obtain power output set-point under any particular head (fortunately they are
linear)
Variable Speed operation ndash Electrical machine
bull Static frequency converters have been used before but for smaller purposes (lt30 MVA) but for ratings above 250 MVA this solution becomes infeasible Thus the use of DFIM sets into the picture The converter needed for the DFIM depends directly upon the slip for which it is optimized to operate
bull The wound rotor induction machine has come up from the wind turbine industry Control of DFIM is possible through rotor and stator side converters
bull ldquoVARSPEEDrdquo by ABB is one famous commercial example advantages of which arendash Increased overall efficiencyndash Possibility of active power control in pumping mode ndash Possibility of reactive power control at interconnection point to the grid
Variable speed operation - DFIM
bull DFIM is advantageous over the synchronous machine as itrsquos speed stabilizes faster than a conventional synchronous machine for a grid side voltage drop event Excellent self-stabilizing properties
bull The machine can be used to instantaneously inject real power into the grid The reduction in reference speed can be used to extract the required real power Conventional plants need accumulated steam for the same Thus they can be used for grid control
bull Due to the possibility of speed adjustment the pump power may easily be adjusted This feature is also advantageous for grid control Variable speed pumping
Modern hydraulic equipment - Ternary Set
Pelton turbine Clutch and gear(torque coupler)
Multi-stage centrifugal pump
Tail-raceOutlet of pump
Turbine inlet scroll
Pumped storage hydraulic equipment with pump and turbine as separate hydraulic machines but on
the same shaft [3]
Ternary Set
bull Using two separate hydraulic devices the direction of rotation will be the same in both modes of operation This is very convenient as far as uniform stress on the structure and electrical control and connections are concerned
bull The change-over time required between pumping and generating mode can be reduced due to the pre-rotating single ndash shaft Thereby enabling faster controls and no additional starting power requirements
bull Two modes are separated by a clutch which can engage either mode in no time
Hydraulic short-circuit
bull In a ternary set it is possible to transfer the water from the pump to the turbine and drive the turbine and feed the upper reservoir simultaneously It may also be possible to supplement the flow of water into the turbine and hence reduce the discharge from the upper reservoir In both cases the ternary set acts as a controllable load
bull Direct shaft control is better and faster than generator control due to the large generator inertia Hence hydraulic short circuit enables the operation of a fixed load on the same shaft The difference between the pump power and the turbine power is only fed to the grid
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Variable speed pumped hydro -Benefits
bull Benefits of variable speed operation
ndash Variable speed could help avoid draft tube pressure oscillations and cavitation among others
ndash Improved performance at off-design heads and improved range of heads
ndash Improved performance at off-design discharge and improved range of discharge
ndash Variable speed allows power consumed in the pumping mode to be varied over a range of outputs
ndash Variable speed also allows the turbine to operate the turbine at peak efficiencies over a wide range of its operating band
ndash Doubly fed induction generators fed through thyristor cyclo-converters are extremely beneficial for grid connected operations
Speed discharge characteristics of a turbine [2]
Variable speed operation - Control
bull 2 important methods similar to wind are ndash Pitch control ndash high flow rate ndash comparatively
small time constant
ndash Load control ndash medium flow rate ndash slow due to the large inertia involved
These equations are used to control the turbine gate angle and the speed so as
to obtain power output set-point under any particular head (fortunately they are
linear)
Variable Speed operation ndash Electrical machine
bull Static frequency converters have been used before but for smaller purposes (lt30 MVA) but for ratings above 250 MVA this solution becomes infeasible Thus the use of DFIM sets into the picture The converter needed for the DFIM depends directly upon the slip for which it is optimized to operate
bull The wound rotor induction machine has come up from the wind turbine industry Control of DFIM is possible through rotor and stator side converters
bull ldquoVARSPEEDrdquo by ABB is one famous commercial example advantages of which arendash Increased overall efficiencyndash Possibility of active power control in pumping mode ndash Possibility of reactive power control at interconnection point to the grid
Variable speed operation - DFIM
bull DFIM is advantageous over the synchronous machine as itrsquos speed stabilizes faster than a conventional synchronous machine for a grid side voltage drop event Excellent self-stabilizing properties
bull The machine can be used to instantaneously inject real power into the grid The reduction in reference speed can be used to extract the required real power Conventional plants need accumulated steam for the same Thus they can be used for grid control
bull Due to the possibility of speed adjustment the pump power may easily be adjusted This feature is also advantageous for grid control Variable speed pumping
Modern hydraulic equipment - Ternary Set
Pelton turbine Clutch and gear(torque coupler)
Multi-stage centrifugal pump
Tail-raceOutlet of pump
Turbine inlet scroll
Pumped storage hydraulic equipment with pump and turbine as separate hydraulic machines but on
the same shaft [3]
Ternary Set
bull Using two separate hydraulic devices the direction of rotation will be the same in both modes of operation This is very convenient as far as uniform stress on the structure and electrical control and connections are concerned
bull The change-over time required between pumping and generating mode can be reduced due to the pre-rotating single ndash shaft Thereby enabling faster controls and no additional starting power requirements
bull Two modes are separated by a clutch which can engage either mode in no time
Hydraulic short-circuit
bull In a ternary set it is possible to transfer the water from the pump to the turbine and drive the turbine and feed the upper reservoir simultaneously It may also be possible to supplement the flow of water into the turbine and hence reduce the discharge from the upper reservoir In both cases the ternary set acts as a controllable load
bull Direct shaft control is better and faster than generator control due to the large generator inertia Hence hydraulic short circuit enables the operation of a fixed load on the same shaft The difference between the pump power and the turbine power is only fed to the grid
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Variable speed operation - Control
bull 2 important methods similar to wind are ndash Pitch control ndash high flow rate ndash comparatively
small time constant
ndash Load control ndash medium flow rate ndash slow due to the large inertia involved
These equations are used to control the turbine gate angle and the speed so as
to obtain power output set-point under any particular head (fortunately they are
linear)
Variable Speed operation ndash Electrical machine
bull Static frequency converters have been used before but for smaller purposes (lt30 MVA) but for ratings above 250 MVA this solution becomes infeasible Thus the use of DFIM sets into the picture The converter needed for the DFIM depends directly upon the slip for which it is optimized to operate
bull The wound rotor induction machine has come up from the wind turbine industry Control of DFIM is possible through rotor and stator side converters
bull ldquoVARSPEEDrdquo by ABB is one famous commercial example advantages of which arendash Increased overall efficiencyndash Possibility of active power control in pumping mode ndash Possibility of reactive power control at interconnection point to the grid
Variable speed operation - DFIM
bull DFIM is advantageous over the synchronous machine as itrsquos speed stabilizes faster than a conventional synchronous machine for a grid side voltage drop event Excellent self-stabilizing properties
bull The machine can be used to instantaneously inject real power into the grid The reduction in reference speed can be used to extract the required real power Conventional plants need accumulated steam for the same Thus they can be used for grid control
bull Due to the possibility of speed adjustment the pump power may easily be adjusted This feature is also advantageous for grid control Variable speed pumping
Modern hydraulic equipment - Ternary Set
Pelton turbine Clutch and gear(torque coupler)
Multi-stage centrifugal pump
Tail-raceOutlet of pump
Turbine inlet scroll
Pumped storage hydraulic equipment with pump and turbine as separate hydraulic machines but on
the same shaft [3]
Ternary Set
bull Using two separate hydraulic devices the direction of rotation will be the same in both modes of operation This is very convenient as far as uniform stress on the structure and electrical control and connections are concerned
bull The change-over time required between pumping and generating mode can be reduced due to the pre-rotating single ndash shaft Thereby enabling faster controls and no additional starting power requirements
bull Two modes are separated by a clutch which can engage either mode in no time
Hydraulic short-circuit
bull In a ternary set it is possible to transfer the water from the pump to the turbine and drive the turbine and feed the upper reservoir simultaneously It may also be possible to supplement the flow of water into the turbine and hence reduce the discharge from the upper reservoir In both cases the ternary set acts as a controllable load
bull Direct shaft control is better and faster than generator control due to the large generator inertia Hence hydraulic short circuit enables the operation of a fixed load on the same shaft The difference between the pump power and the turbine power is only fed to the grid
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Variable Speed operation ndash Electrical machine
bull Static frequency converters have been used before but for smaller purposes (lt30 MVA) but for ratings above 250 MVA this solution becomes infeasible Thus the use of DFIM sets into the picture The converter needed for the DFIM depends directly upon the slip for which it is optimized to operate
bull The wound rotor induction machine has come up from the wind turbine industry Control of DFIM is possible through rotor and stator side converters
bull ldquoVARSPEEDrdquo by ABB is one famous commercial example advantages of which arendash Increased overall efficiencyndash Possibility of active power control in pumping mode ndash Possibility of reactive power control at interconnection point to the grid
Variable speed operation - DFIM
bull DFIM is advantageous over the synchronous machine as itrsquos speed stabilizes faster than a conventional synchronous machine for a grid side voltage drop event Excellent self-stabilizing properties
bull The machine can be used to instantaneously inject real power into the grid The reduction in reference speed can be used to extract the required real power Conventional plants need accumulated steam for the same Thus they can be used for grid control
bull Due to the possibility of speed adjustment the pump power may easily be adjusted This feature is also advantageous for grid control Variable speed pumping
Modern hydraulic equipment - Ternary Set
Pelton turbine Clutch and gear(torque coupler)
Multi-stage centrifugal pump
Tail-raceOutlet of pump
Turbine inlet scroll
Pumped storage hydraulic equipment with pump and turbine as separate hydraulic machines but on
the same shaft [3]
Ternary Set
bull Using two separate hydraulic devices the direction of rotation will be the same in both modes of operation This is very convenient as far as uniform stress on the structure and electrical control and connections are concerned
bull The change-over time required between pumping and generating mode can be reduced due to the pre-rotating single ndash shaft Thereby enabling faster controls and no additional starting power requirements
bull Two modes are separated by a clutch which can engage either mode in no time
Hydraulic short-circuit
bull In a ternary set it is possible to transfer the water from the pump to the turbine and drive the turbine and feed the upper reservoir simultaneously It may also be possible to supplement the flow of water into the turbine and hence reduce the discharge from the upper reservoir In both cases the ternary set acts as a controllable load
bull Direct shaft control is better and faster than generator control due to the large generator inertia Hence hydraulic short circuit enables the operation of a fixed load on the same shaft The difference between the pump power and the turbine power is only fed to the grid
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Variable speed operation - DFIM
bull DFIM is advantageous over the synchronous machine as itrsquos speed stabilizes faster than a conventional synchronous machine for a grid side voltage drop event Excellent self-stabilizing properties
bull The machine can be used to instantaneously inject real power into the grid The reduction in reference speed can be used to extract the required real power Conventional plants need accumulated steam for the same Thus they can be used for grid control
bull Due to the possibility of speed adjustment the pump power may easily be adjusted This feature is also advantageous for grid control Variable speed pumping
Modern hydraulic equipment - Ternary Set
Pelton turbine Clutch and gear(torque coupler)
Multi-stage centrifugal pump
Tail-raceOutlet of pump
Turbine inlet scroll
Pumped storage hydraulic equipment with pump and turbine as separate hydraulic machines but on
the same shaft [3]
Ternary Set
bull Using two separate hydraulic devices the direction of rotation will be the same in both modes of operation This is very convenient as far as uniform stress on the structure and electrical control and connections are concerned
bull The change-over time required between pumping and generating mode can be reduced due to the pre-rotating single ndash shaft Thereby enabling faster controls and no additional starting power requirements
bull Two modes are separated by a clutch which can engage either mode in no time
Hydraulic short-circuit
bull In a ternary set it is possible to transfer the water from the pump to the turbine and drive the turbine and feed the upper reservoir simultaneously It may also be possible to supplement the flow of water into the turbine and hence reduce the discharge from the upper reservoir In both cases the ternary set acts as a controllable load
bull Direct shaft control is better and faster than generator control due to the large generator inertia Hence hydraulic short circuit enables the operation of a fixed load on the same shaft The difference between the pump power and the turbine power is only fed to the grid
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Modern hydraulic equipment - Ternary Set
Pelton turbine Clutch and gear(torque coupler)
Multi-stage centrifugal pump
Tail-raceOutlet of pump
Turbine inlet scroll
Pumped storage hydraulic equipment with pump and turbine as separate hydraulic machines but on
the same shaft [3]
Ternary Set
bull Using two separate hydraulic devices the direction of rotation will be the same in both modes of operation This is very convenient as far as uniform stress on the structure and electrical control and connections are concerned
bull The change-over time required between pumping and generating mode can be reduced due to the pre-rotating single ndash shaft Thereby enabling faster controls and no additional starting power requirements
bull Two modes are separated by a clutch which can engage either mode in no time
Hydraulic short-circuit
bull In a ternary set it is possible to transfer the water from the pump to the turbine and drive the turbine and feed the upper reservoir simultaneously It may also be possible to supplement the flow of water into the turbine and hence reduce the discharge from the upper reservoir In both cases the ternary set acts as a controllable load
bull Direct shaft control is better and faster than generator control due to the large generator inertia Hence hydraulic short circuit enables the operation of a fixed load on the same shaft The difference between the pump power and the turbine power is only fed to the grid
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Ternary Set
bull Using two separate hydraulic devices the direction of rotation will be the same in both modes of operation This is very convenient as far as uniform stress on the structure and electrical control and connections are concerned
bull The change-over time required between pumping and generating mode can be reduced due to the pre-rotating single ndash shaft Thereby enabling faster controls and no additional starting power requirements
bull Two modes are separated by a clutch which can engage either mode in no time
Hydraulic short-circuit
bull In a ternary set it is possible to transfer the water from the pump to the turbine and drive the turbine and feed the upper reservoir simultaneously It may also be possible to supplement the flow of water into the turbine and hence reduce the discharge from the upper reservoir In both cases the ternary set acts as a controllable load
bull Direct shaft control is better and faster than generator control due to the large generator inertia Hence hydraulic short circuit enables the operation of a fixed load on the same shaft The difference between the pump power and the turbine power is only fed to the grid
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Hydraulic short-circuit
bull In a ternary set it is possible to transfer the water from the pump to the turbine and drive the turbine and feed the upper reservoir simultaneously It may also be possible to supplement the flow of water into the turbine and hence reduce the discharge from the upper reservoir In both cases the ternary set acts as a controllable load
bull Direct shaft control is better and faster than generator control due to the large generator inertia Hence hydraulic short circuit enables the operation of a fixed load on the same shaft The difference between the pump power and the turbine power is only fed to the grid
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Hydraulic short-circuit
Valve control
Right now there is only one early access paper in IEEE and two papers in science direct that realize hydraulic short-circuit
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Wind Hydro a Unit Commitment Point of View for Co-ordination
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Hydraulic Constraints in operation of a PHS
Other than electrical constraints there are numerous hydraulic constraints which need to be considered
bull Energy content of a reservoirbull Mode of reservoir
ndash Pumpinggeneratingndash Different for units with ternary set ndash clutch setting constraint
bull Reservoir volume constraint different for upward and downward reservoir bull Unit ramp rate constraintbull Rate of change of discharge limitsbull Reservoir spill limitsbull Branch flow limits
With the introduction of the use of ternary sets and variable speed machines new and modified constraints will arise These are areas of research which need attention
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Wind hydro Operation ndash I ndash (research based)
bull [4] presents the operation of an under construction Greek island power system with a hybrid power sources consisting of a pumped storage station where pumping is facilitated by a wind farm Wind power dispatch methods -ndash Only for pumpingndash Penetration into the grid with a margin with wind curtailmentndash Direct dispatch to connected grid with the pumped storage
plant as a fast controller
bull Advantagesndash Increased RES penetration under the dispatch strategy as tested
under dry avg and wet hydrological years for both high and low wind profiles
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Wind hydro Operation ndash II ndash (research based)
bull Khodayar et al [5] presents the SCUC for a 6 bus power system where wind farm and PHS are at the same bus including thermal generators on other busses Here the PHS acted as a volatility controller for the wind farm With the co-ordination the following were realizedndash Reduction in curtailed number of units and hence
increase in wind penetration which proves the fast control ability of PHS
ndash Reduction in operation cost of other plants due to high RES penetration
ndash Increase in transmission network security
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Wind hydro Operation ndash III ndash (research based)
bull Khodayar et al [6] extended their work on SCUC to considering different scenarios with uncertainties such asndash Line generator or other equipment failure
ndash Forecast error
bull Monte-carlo simulations were used generate almost 3000 scenarios and scenario reduction techniques were used to consider 12 scenarios The scenarios were implemented under 4 different co-ordination strategiesndash Wind only along with other generation units
ndash Wind and hydro co-ordination with constant temporal pond level constraint
ndash Wind and hydro co-ordination with constant temporal power level constraint
ndash System level co-ordination with PHS dispatch optimized with the system
bull Criterion for selecting the best strategyndash Availability of units for control and regulation
ndash Corrective action cost ndash cost for performing actions apart from base case
ndash Total operation cost
ndash Wind curtailment
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Coordinated output and corrective output actions
Corrective action performed by
thermal plants is reduced due to
system level coordination of
PHS
Coordinated power output
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Pond level control Strategy ndash Inflexible to Grid and Wind Fluctuations
Pond level control
Constant power level
System level co-ordination
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Congestion and operation cost reduction strategy ndash system level coordination
Gen 3 is costly and is not committed when
strategy 4 is used Congestion is reduced
and so is operation cost
Wind only with other thermal units
Wind and PS coordinated at system level
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Challenges in retrofitting existing plants with modern
equipment of PHS
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Hydraulic design[7]
bull Hydraulic transients considering the existing waterways
bull Integration of new hydraulic components
bull Cavitation free operation with available runner settings
Electrical Design[7]
bull Synchronous generator with full power frequency converter
bull Replacing the Synchronous gen by a DFIM with low power frequency converter
Power Electronic control[7]
bull Harmonic filters
bull Voltage source inverter and transformer
bull Low frequency current and voltage transformers
bull Rotor feed equipment
Challenges in Reconfiguring an existing plant
Building a new one takes 8 years and millions
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo
Reference
bull [1] - Comparative Review of Long-Term Energy Storage Technologies for Renewable Energy Systems A Andrijanovits H Hoimoja D Vinnikov Department of Electrical Drives and Power Electronics Tallinn University of Technology
bull [2] - J Fraile-Ardanuy J R Wilhelmi J J Fraile-Mora and J I Perez Variable-speed hydro generation operational aspects and control in IEEE Transactions on Energy Conversion vol 21 no 2 pp 569-574 June 2006
bull [3] - httpvoithcomen11_06_Broschuere-Pumped-storage_einzelnpdf
bull [4] - Stefanos V Papaefthymiou Eleni G Karamanou Stavros A Papathanassiou Michael P Papadopoulos ldquoA Wind-Hydro-Pumped Storage Station Leading to High RES Penetration in the Autonomous Island System of Ikariardquo ieee TRANSACTIONS ON SUSTAINABLE ENERGY
bull [5] ndash Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoCoordination of Wind and Pumped-Storage Hydro Units for Managing Transmission Securityrdquo 2012
bull [6] Mohammad Shahidehpour Fellow IEEE and Mohammad Khodayar Member IEEE ldquoEnhancing the Dispatchability of Variable Wind Generation by Coordination With Pumped-Storage Hydro Units in Stochastic Power Systemsrdquo
bull [7] ldquohttpwwwhydroworldcomarticlesprintvolume-21issue-5articlespumped-storageconverting-to-variable-speed-at-a-pumped-storage-planthtmlrdquo