-Rakesh Sunari Magar(77)-Pawan Bhatta(65)-Nirajan Dahal(58)-Needesh Budhathoki(56)
FEASIBILITY ANALYSIS OF A ROAD UPGRADING PROJECT
(PANG GAUN ~ TIKABHAIRAV)
Advanced College of Engineering
Prof. Dr. Padma Bahadur Shahi
Under Guidance
of
Prepared by:
1
Background
As per our syllabus, we fourth year students have to present our final year project in our desired field of interest. It is a vital part of IOE syllabus in order to make students competent to work in the actual field.
We have chosen rural road development project among the number of options available in transportation project.
We want to experience the working technique with new innovative concept of ours while designing a road in a sense of future demand that is structurally, eco-friendly and atheistically designed.
2
IntroT
R
A
N
S
P
O
R
T
A
T
I
O
N
Transportation plays a vital role in basic infrastructure development in mountainous country like Nepal.
It is a social property.
It is demand fulfilling demand.
3
Objectives and Scope
To setup an alignment of a road as per the environmental condition.
To consider gradient, earthwork, road components (drainage, retaining walls), geometric properties of the road properly in the design.
To prepare economical and stable road in rural areas.
To link urban and rural areas with comfort, wide, safe, smooth road.
4
Objectives and Scope
For the overall development of country.
To minimize the risk of loss of property and lives by designing stable roads.
To know the importance of team work.
To design the road with innovative concept that is structurally, atheistically and eco-friendly aspect.
5
Gantt chart
WORKING SCHEDULE
6
METHODOLOGY
PlanningSurveyPreliminary DesignGeometric DesignDetailingCalculationPlottingModelingAnalysisReport Preparation
7
The work to be performed while doing our project are listed as series below:
Project PERT Chart
START
Pre synopsis submission
Site Selection
Synopsis Submission
Reconnaissance survey
11 th Nov , 2014
8
Survey and data plot
Tests of soil samples
Computation and design
Traffic count
9
Project report submission
Conclusion END
2015
10
ROAD SITEPang Gaun to Tika Bhairav (2.5km)
Location: Zone: Bagmati District: Lalitpur VDC: Pang Gaun
11
12
MAP STUDYLocation :- Where are things situated? A location can be specific for example, it can be
stated as coordinates of longitude and latitude or as a distance from one place to another place. eg. In our case, road site’s location is south east from the valley.
Latitudes/easting are imaginary lines running parallel to the Equator.
Longitudes(departures)/northing are imaginary lines running parallel to the Prime Meridian.
13
MAP STUDY
14
Place :- What makes a place different from other places? Differences might be defined in terms of climate, physical features, or the people who live there and their traditions.
Human-environment interaction :- What are the relationships among people and places? How have people changed the environment to better suit their needs?
SOCIO-ECONOMIC CONDITIONThe major caste in this area are newars,
brahmin, chhetri, sarkis, etc.
Mainly the people are involved in agriculture.
People are not well educated.
The economic condition is poor.
Equipments used in geometric surveyGPS (Global Positioning System)
2 numbers
Principle: Satellites based allocation of a position by latitude, departure and elevation.
16
Geometric design
17
ProfilePlanCross section
18
fig. Plan (central alignment only)
Pavement designTraffic countCBR test
19
Traffic studyA traffic study is an engineering
investigation to evaluate a transportation system.
A study typically consists of collecting data, projecting traffic volumes, and identifying the improvements required for the transportation system.
20
Traffic CountA traffic count is a count of traffic along a
particular road, either done electronically or by people counting by the side of the road.
Traffic counts can be used by local councils to identify which routes are used most, and to either improve that road or provide an alternative if there is an excessive amount of traffic.
Traffic Count
Leaving the valley Entering the valley
22
bike car/jeep bus Truck( unloaded)
Truck(loaded)
Heavy(tipper) tandem
19 5 2 1 8 1 0
11 2 4 1 3 1 0
8 2 3 4 13 2 1
9 3 1 1 12 0 0
bike car/jeep bus Truck( unloaded)
Truck(loaded)
Heavy(tipper) tandem
15 2 4 5 3 0 0
7 4 1 6 0 0 0
11 1 1 2 0 0 0
6 3 6 12 0 0 0
minutes
15
other 15
other 15
other 15
39 10 12 25 3 0 0 47 12 10 7 36 4 1total
Therefore,
Total traffic volume= 206 vehicles per hour
23
CBR test
24
CBR test
25
26
CBR = CBR [%]
p = measured pressure for site soils [N/mm²]
ps= pressure to achieve equal penetration on standard soil [N/mm²]
27
CBR VALUE SUBGRADE STRENGTH
3% and less Poor
3% - 5% Normal
5% - 15% Good
CONCLUSION Geometric analysis of different roads has become
evitable in today’s world. So, we are quite interested in indulging us in this research as we have interest towards this subject. Further in Nepal, geometric analysis of roads are to be done and for this we want to prepare ourselves.
We believe that after the completion of this project we are not only capable of geometrically analyzing existing as well as newly prepared roads but also can put forward our suggestions to ensure or increase the safety, strength and durability of the roads.
28
design references Rural Road Standard, DOLIDARPavement Design Guidelines, DOR
29
Thank You!!!