Predictive Maintenance Thermograph in GIS 500 KV Unit 4 Company Device Customer Adityan ilmawan Tester: Standard 32° Lens: 2279803 Serial No.: testo 876 Jepara, Central Java Desa Tubanan Kecamatan Kembang Electrical Maintenance Division 11/25/2014 Measuring Date: Measuring Site: Check Temperature and Take Thermograph Photo Task Jepara, Central Java Desa Tubanan Kecamatan Kembang PT KOMIPO PEMBANGKITAN JAWA BALI 1/7 Page

Predictive maintenance thermograph in gis 500 kv unit 4

Embed Size (px)

Citation preview

Page 1: Predictive maintenance thermograph in gis 500 kv unit 4

Predictive Maintenance Thermographin GIS 500 KV Unit 4

Company

Device

Customer

Adityan ilmawan

Tester:

Standard 32°Lens:

2279803Serial No.:testo 876

Jepara, Central Java

Desa Tubanan KecamatanKembang

Electrical Maintenance Division

11/25/2014Measuring Date:

Measuring Site:

Check Temperature and Take Thermograph PhotoTask

Jepara, Central Java

Desa Tubanan KecamatanKembang

PT KOMIPO PEMBANGKITANJAWA BALI

1/7Page

Page 2: Predictive maintenance thermograph in gis 500 kv unit 4

Predictive Maintenance Thermograph in GIS 500 KV Unit 4

File: IV_00236.BMT

11/14/2014 MeasuringTime:

8:48:58 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

Surge Arrester Phase R GIS 500 KV Unit 4

Remarks:

File: IV_00237.BMT

11/14/2014 MeasuringTime:

8:49:49 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

Voltage Transformer Phase R GIS 500 KV Unit 4

Remarks:

File: IV_00238.BMT

11/14/2014 MeasuringTime:

8:50:07 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

Bushing Phase R GIS 500 KV Unit 4

Remarks:

File: IV_00239.BMT

11/14/2014 MeasuringTime:

8:50:23 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

Phase R GIS 500 KV Unit 4

Remarks:

2/7Page

Page 3: Predictive maintenance thermograph in gis 500 kv unit 4

Predictive Maintenance Thermograph in GIS 500 KV Unit 4

File: IV_00240.BMT

11/14/2014 MeasuringTime:

8:51:01 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

V-Suspension Phase R GIS 500 KV Unit 4

Remarks:

File: IV_00241.BMT

11/14/2014 MeasuringTime:

8:51:27 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

Phase R GIS 500 KV Unit 4

Remarks:

File: IV_00230.BMT

11/14/2014 MeasuringTime:

8:45:40 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

Surge Arrester PhaseS GIS 500 KV Unit 4

Remarks:

File: IV_00231.BMT

11/14/2014 MeasuringTime:

8:46:39 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

Voltage Transformer Phase S GIS 500 KV Unit 4

Remarks:

3/7Page

Page 4: Predictive maintenance thermograph in gis 500 kv unit 4

Predictive Maintenance Thermograph in GIS 500 KV Unit 4

File: IV_00232.BMT

11/14/2014 MeasuringTime:

8:46:58 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

Bushing Phase S GIS 500 KV Unit 4

Remarks:

File: IV_00233.BMT

11/14/2014 MeasuringTime:

8:47:12 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

Phase S GIS 500 KV Unit 4

Remarks:

File: IV_00234.BMT

11/14/2014 MeasuringTime:

8:47:35 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

V-Suspension Phase S GIS 500 KV Unit 4

Remarks:

File: IV_00235.BMT

11/14/2014 MeasuringTime:

8:48:10 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

Phase S GIS 500 KV Unit 4

Remarks:

4/7Page

Page 5: Predictive maintenance thermograph in gis 500 kv unit 4

Predictive Maintenance Thermograph in GIS 500 KV Unit 4

File: IV_00223.BMT

11/14/2014 MeasuringTime:

8:40:05 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

Surge Arrester Phase T GIS 500 KV Unit 4

Remarks:

File: IV_00224.BMT

11/14/2014 MeasuringTime:

8:40:50 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

Voltage Transformer Phase T GIS 500 KV Unit 4

Remarks:

File: IV_00226.BMT

11/14/2014 MeasuringTime:

8:42:55 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

Bushing Phase T GIS 500 KV Unit 4

Remarks:

File: IV_00227.BMT

11/14/2014 MeasuringTime:

8:43:31 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

V-Suspension Phase T GIS 500 KV Unit 4

Remarks:

5/7Page

Page 6: Predictive maintenance thermograph in gis 500 kv unit 4

Predictive Maintenance Thermograph in GIS 500 KV Unit 4

File: IV_00228.BMT

11/14/2014 MeasuringTime:

8:44:08 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

Phase T GIS 500 KV Unit 4

Remarks:

File: IV_00229.BMT

11/14/2014 MeasuringTime:

8:44:54 AM

20.0Refl. temp. [°C]:

0.95Emissivity:

Picture parameters:

Date:

Phase T GIS 500 KV Unit 4

Remarks:

6/7Page

Page 7: Predictive maintenance thermograph in gis 500 kv unit 4

Predictive Maintenance Thermograph in GIS 500 KV Unit 4

Adityan ilmawan

,11/25/2014