Upload
chris-myers
View
151
Download
4
Embed Size (px)
Citation preview
Introduction
Introductions
Purpose of this session Provide you with a brief account of what is
generally required with regards to documentation of a construction project and why
2
Why do we keep records?
Because if it is not written then it did not happen
To provide an official document as part of the contract administration
To verify quantities for payment To record changes in the work For future reference To manage claims from the public and
contractors3
What we will discuss at this session Daily and weekly reports Photographic record keeping Forms Red line drawings or your As Builts Meeting preparation and participation Audits Field Services Manual
4
Daily and Weekly Reports
What do we record? Time on and off site for us and the contractor Visitors to site Site conditions Traffic channelization set up Changed conditions Underground utilities Extras and claims
5
Photos
The Inspector should have a camera on site A pictorial record, if properly done, can avoid
many arguments later and also support the Inspector’s position in court if necessary
A picture taken of the excavation shows proof of underground conditions, of the contractor’s safety practices etc
Any unexpected conditions or faulty workmanship should be recorded
6
Common errors in daily reports
Not enough information Calculation errors Use of non standard short forms Statements in the remarks section that do
not make sense
7
Who uses the records
Contract Administrator Payment Clerks Clients Auditors Insurance Investigator Public Lawyers
8
Case history whereby daily reports were used to deal with a claim Plans were prepared to reconstruct a existing
combined sewer in the exact same alignment and existing drains were to be reconnected to the new sewer
Tender was issued for a sewer reconstruction project and the project commenced
But the existing sewer was found to be radius pipe (not straight from MH to MH) and on top of this the hydro conduit was found to be closer than shown on the plan
9
Forms
Great way to document because they act as a checklist
Every organization has them but they naturally vary from place to place
Should be signed usually by both parties, in triplicate (contractor, inspector, and office copies) and numbered
11
A Properly Prepared Change Directive will answer the following
why the work was ordered Where it was done When it was done How it is to be paid
In addition add photos, record in daily report and attach any relevant e mails 12
Final payment and contract close out
Summaries and checks Must be able to substantiate quantities Calculations should be checked by someone
else Checklist of required documents
13
As builts
Record changes of 300mm or more. Show any changed locations for utilities Show lengths of drains or waterservices
replaced. , sizes and material types Remember that others will use these plans to
alter the mylars so someone should check them after they are completed.
14
Meetings
Important for inspector Be prepared and make a list as it is your
chance to get issues resolved in a formal manner that is documented
For contentious issues you might want to discuss with the PM first
Conduct yourself appropriately Keep your own notes
15