Final Project in Construction Management Final Presentation

Final project in Construction Management - Technion Institute of Technology

Embed Size (px)

Citation preview

Page 1: Final project in Construction Management - Technion Institute of Technology

Final Project in Construction Management

Final Presentation

Page 2: Final project in Construction Management - Technion Institute of Technology

Winter Semester 2013/14Advisor: Ziv Hendel

Submitted by: Paula Barmaimon 941104093

Page 3: Final project in Construction Management - Technion Institute of Technology

LocationRechov Nisim Aloni, Tel Aviv

Page 4: Final project in Construction Management - Technion Institute of Technology

13500 m²

Rechov Nisim Aloni, Tel Aviv

Page 5: Final project in Construction Management - Technion Institute of Technology

Site Layout

Site offices

Parking Parking

Baranovich

Storage Area

Eating area

Toilets

10 m

45 m45 m

Concrete pumpCheck the crane model

Page 6: Final project in Construction Management - Technion Institute of Technology

Site preparation

Earthworks

Parking

Structural Works

Finishing works

Schedule

Development

Page 7: Final project in Construction Management - Technion Institute of Technology

Crews

Baranovich team

Formwork walls, external &

internal

Steel

Slab

Page 8: Final project in Construction Management - Technion Institute of Technology

Schedule

Walls formwork placingWalls steel placingSlab formwork placingConcrete casting

Concrete setting

Slab steel placing

Page 9: Final project in Construction Management - Technion Institute of Technology
Page 10: Final project in Construction Management - Technion Institute of Technology

Day 1-4

Page 11: Final project in Construction Management - Technion Institute of Technology

Day 1-4

Page 12: Final project in Construction Management - Technion Institute of Technology

Day 5-7

Page 13: Final project in Construction Management - Technion Institute of Technology

Day 5-7

Page 14: Final project in Construction Management - Technion Institute of Technology

Day 8

Page 15: Final project in Construction Management - Technion Institute of Technology

Day 8

Page 16: Final project in Construction Management - Technion Institute of Technology

Day 9-12

Page 17: Final project in Construction Management - Technion Institute of Technology

Crews

Baranovich team

Formwork walls, external &

internal

Steel

Slab

Page 18: Final project in Construction Management - Technion Institute of Technology

Baranovich system1. Clean2. Place the stones

3. Place the fuga

4. Place isolation

5. Place steel mesh

• Used in high rise building with many typical floors• Shortens the duration of exterior cladding• Casts external walls and stones at the same time

Page 19: Final project in Construction Management - Technion Institute of Technology

Baranovich system• Scaffolding needed for workers to place it• At least 4 anchores/stone• Must be cleaned extremely well

Page 20: Final project in Construction Management - Technion Institute of Technology

Slab team – PERI Skydeck system

Page 21: Final project in Construction Management - Technion Institute of Technology

Advantages• Removal is possible after 1 day• Light components • Easy to clean• Fewer slab props- saves time and space

Page 22: Final project in Construction Management - Technion Institute of Technology

Total workers needed for

concrete works20 workers

Page 23: Final project in Construction Management - Technion Institute of Technology

Cost Analysis CIP CONCRETE

Page 24: Final project in Construction Management - Technion Institute of Technology

CIP concrete• Quantity

• Cost

Page 25: Final project in Construction Management - Technion Institute of Technology

Steel

Density of steel 7850 kg/m3

Page 26: Final project in Construction Management - Technion Institute of Technology

Cost of steel

Page 27: Final project in Construction Management - Technion Institute of Technology

Steel in beams

Page 28: Final project in Construction Management - Technion Institute of Technology

Steel

Page 29: Final project in Construction Management - Technion Institute of Technology

Formwork

Page 30: Final project in Construction Management - Technion Institute of Technology

Total Cost

Page 31: Final project in Construction Management - Technion Institute of Technology

Summary for Concrete Works

Total Cost of Project 300,000,000 concrete works ~ 16% of total proyect

The total duration of the proyect is 36 months. The total duration of concrete works is 19 months.Concrete works must be completed in 2 weeks/floorPeri Skydeck must be used to achieve this rate.

The crew size for this purpose is 20 workers .

Page 32: Final project in Construction Management - Technion Institute of Technology

Project Manager

2 Site Engineer

2 Head Foreman

Concrete Foreman

Steel Foreman

Parking Foreman

Finishing Foreman

Development

Foreman

Secretaries Guard

MEP Manager BOQ Buying Coordinators

MANAGEMENT CREW

Page 33: Final project in Construction Management - Technion Institute of Technology

Overheads

Page 34: Final project in Construction Management - Technion Institute of Technology
Page 35: Final project in Construction Management - Technion Institute of Technology

THANK YOU!!