Upload
paula-barmaimon
View
829
Download
1
Embed Size (px)
Citation preview
Final Project in Construction Management
Final Presentation
Winter Semester 2013/14Advisor: Ziv Hendel
Submitted by: Paula Barmaimon 941104093
LocationRechov Nisim Aloni, Tel Aviv
13500 m²
Rechov Nisim Aloni, Tel Aviv
Site Layout
Site offices
Parking Parking
Baranovich
Storage Area
Eating area
Toilets
10 m
45 m45 m
Concrete pumpCheck the crane model
Site preparation
Earthworks
Parking
Structural Works
Finishing works
Schedule
Development
Crews
Baranovich team
Formwork walls, external &
internal
Steel
Slab
Schedule
Walls formwork placingWalls steel placingSlab formwork placingConcrete casting
Concrete setting
Slab steel placing
Day 1-4
Day 1-4
Day 5-7
Day 5-7
Day 8
Day 8
Day 9-12
Crews
Baranovich team
Formwork walls, external &
internal
Steel
Slab
Baranovich system1. Clean2. Place the stones
3. Place the fuga
4. Place isolation
5. Place steel mesh
• Used in high rise building with many typical floors• Shortens the duration of exterior cladding• Casts external walls and stones at the same time
Baranovich system• Scaffolding needed for workers to place it• At least 4 anchores/stone• Must be cleaned extremely well
Slab team – PERI Skydeck system
Advantages• Removal is possible after 1 day• Light components • Easy to clean• Fewer slab props- saves time and space
Total workers needed for
concrete works20 workers
Cost Analysis CIP CONCRETE
CIP concrete• Quantity
• Cost
Steel
Density of steel 7850 kg/m3
Cost of steel
Steel in beams
Steel
Formwork
Total Cost
Summary for Concrete Works
Total Cost of Project 300,000,000 concrete works ~ 16% of total proyect
The total duration of the proyect is 36 months. The total duration of concrete works is 19 months.Concrete works must be completed in 2 weeks/floorPeri Skydeck must be used to achieve this rate.
The crew size for this purpose is 20 workers .
Project Manager
2 Site Engineer
2 Head Foreman
Concrete Foreman
Steel Foreman
Parking Foreman
Finishing Foreman
Development
Foreman
Secretaries Guard
MEP Manager BOQ Buying Coordinators
MANAGEMENT CREW
Overheads
THANK YOU!!