McCORMICK PLACE HEADQUARTERS HOTEL & EVENT CENTER Metropolitan Pier and Exposition Authority

Clark Construction/PD3 Presentation - McCormick HQ

Embed Size (px)

Citation preview

Page 1: Clark Construction/PD3 Presentation - McCormick HQ

McCORMICK PLACEHEADQUARTERS HOTEL & EVENT CENTER

Metropolitan Pier and Exposition Authority

Page 2: Clark Construction/PD3 Presentation - McCormick HQ

McCormick Experience

Page 3: Clark Construction/PD3 Presentation - McCormick HQ

Why Design Build ?

Page 4: Clark Construction/PD3 Presentation - McCormick HQ

(MBE)

(MBE)

(MBE)

(MBE/WBE)

(MBE)

(Hotel) (Event Center)

DESIGN-BUILD LEAD

DIVERSITY/ COMMUNITY

OUTREACH MANAGER

CONSTRUCTION MANAGEMENT

PARTNERS

DESIGN LEADS

Page 5: Clark Construction/PD3 Presentation - McCormick HQ

Past Success at McCormick Place

Page 6: Clark Construction/PD3 Presentation - McCormick HQ

2. Hotel Overview

Page 7: Clark Construction/PD3 Presentation - McCormick HQ

Key Facts• 1206-room, 40-floor, Marriott Marquis

Hotel• (2) 25,000sf Ballrooms• 90,000sf Meeting Space• Renovation of Historic ABC Building• Central Plant Upgrades• Anticipated Completion – Q3 2017

Page 8: Clark Construction/PD3 Presentation - McCormick HQ
Page 9: Clark Construction/PD3 Presentation - McCormick HQ

Aerial View Southeast East Elevation

Street Level – Podium Street Level – Pedestrian Walkways

Page 10: Clark Construction/PD3 Presentation - McCormick HQ

Hotel Base Design Hotel Alternate Design

Page 11: Clark Construction/PD3 Presentation - McCormick HQ

Hotel Base Design

Hotel Alternate Design

Page 12: Clark Construction/PD3 Presentation - McCormick HQ

Design Refinement Results• Reduced Elevators• Reduced Enclosure• Removed Building Maintenance Unit• Refined Structure• Mechanical Floor Removed

Page 13: Clark Construction/PD3 Presentation - McCormick HQ

Schedule Highlights• 32-month Design-Build Contract• Schematic & Design Development• Early Demolition & Enabling Work• 25-month Construction Schedule• Potential Early Occupancy

Page 14: Clark Construction/PD3 Presentation - McCormick HQ

3. Event Center Overview

Page 15: Clark Construction/PD3 Presentation - McCormick HQ

Key Facts• MPEA/DePaul University Partnership• 10,000-seat, 300,000sf Basketball

Arena & Multi-Purpose Venue• Anticipated Completion – Q3 2017• Pelli Clarke Pelli – Design Architect • Moody Nolan – Architect-of-Record

Page 16: Clark Construction/PD3 Presentation - McCormick HQ

Design Refinement ResultsMaintained the Spirit of the Pelli Clarke Pelli Design Concept• Raised Event Floor To Grade (was -22.5’)• Building Area Reduced By (approximately) 30,000

GSF• Simplified Roof Expression/Structure• Simplified Façade Materials & Detailing• Simplified HVAC Distribution

Page 17: Clark Construction/PD3 Presentation - McCormick HQ

Event Center Options

Original

Modified

Page 18: Clark Construction/PD3 Presentation - McCormick HQ

Aerial View - Original Aerial View - Modified

Page 19: Clark Construction/PD3 Presentation - McCormick HQ

Event Center– Entry at Cermak Road

Page 20: Clark Construction/PD3 Presentation - McCormick HQ

Event Level - Original Event Level - Modified

Page 21: Clark Construction/PD3 Presentation - McCormick HQ

Building Section – Viewing North

Page 22: Clark Construction/PD3 Presentation - McCormick HQ

Entry Lobby

Page 23: Clark Construction/PD3 Presentation - McCormick HQ

Event Space /Arena

Page 24: Clark Construction/PD3 Presentation - McCormick HQ
Page 25: Clark Construction/PD3 Presentation - McCormick HQ

Schedule Highlights• 30-month Design-Build Contract• Initial Design “Reset” Phase• Schematic & Design Development• Early Demolition & Enabling Work• 23-month Construction Schedule

Page 26: Clark Construction/PD3 Presentation - McCormick HQ

McCORMICK PLACEHEADQUARTERS HOTEL & EVENT CENTER