CB 602: BUILDING MAINTENANCE MANAGEMENTMatric No. Name

08DPB12F1079 HENG CHUN YIK

08DPB12F1081 HO Y NAM

08DPB12F1043 TAN YEE TEAN

CASE STUDY: BUILDING SURVEY

INTRODUCTIONSUBJECT OF PROPERTY :

CIVIL ENGINEERING DEPARTMENT, CLASSROOM LA 208

DATE OF SURVEY : 05 JANUARY 2015

Describe correctly the concept of organization , administrative and managerial of maintenance system

OBJECTIVE :

LOCATION PLAN, LA 208

LIMITATION

46 units of Table 50 of Chairs1 set of Projected 1 White board 1 sheet of projected screen 4 pairs of fan 2 units air conditioner 18 units of fluorescent lamp

  SPECIFICATION

This classroom's function is for student of Civil Engineering

Department, Premier Polytechnic Sultan Salahuddin Abdul Aziz Shah

for education.

SITUATION The student of civil department from semester 1 until semester 6 will

study at this classroom by followed the class schedule everyday except

weekend and holiday.

Student will study many type courses in this classroom with lecturer by

using projector and white board.

SCOPE: STRUCTURE & FACILITIES

DESCRIPTION

LA 208 was built up, in1997.

Purpose to provide student a comfortable place to study

Located at block 2 and second floor .

Height = 3.45 m , width = 8.15 m ; length = 10 m.

Varies type of facility (table , chair , air conditioner)

INFRASTRUCTURE & SERVICES

Staircase

Hose reel

Fire Extinguisher

Dustbin

White board wiper

Electrical magnetic door

SURVEY REPORTPROCEDURES

I. INSPECTION

II. DEFINE DEFLECTION

III. SOLUTION & AUDIT, COST

GENERAL STATE OF PREMISES SURVEYED(Specification in structure & facilities)

• Water seepage from external wall, window, roof, or from ceiling

• Structural cracks in walls

• Defective wall paint crack

DEFECTION OF BUILDING

Floor having potholes, Max: 1m; Min : 0.5mHave some unknown black color liquid leaks from the ceiling.

Hollow door that don’t block out soundWall cracked paint

DEFLECTION OF BUILDING (CONT.)

The door crack, it may cause air infiltration

Improper finishing for magnetic door installation

RECOMMENDATION

I. Building should be implementation maintenance

the classroom every year .

II. Apply preventive maintenance method (follow the

schedule basis)

III. Rubbish in dustbin must be clean on every day .

CONCLUSION

I. Less of maintenance services of this class

room.(building),

II. For overall, student still felt comfortable when

study at here.

III. Polytechnic have to give more effort on the

maintenance services in the future.