21
PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 1 of 21 Addressing Project Capital Efficiency through a Business Basis of Design By Bob Prieto Large capital construction projects in both the industrial and infrastructure sectors are challenged today in three significant ways: Capital efficiency of the project this considers both first costs as well as life cycle costs Capital certainty reflecting execution efficiency, predictability and effective risk transfer through appropriate contracting strategies Time to market perhaps best thought of as schedule certainty but also accelerated delivery of projects, often an essential ingredient in capital efficiency This paper focuses on achieving improved capital efficiency in large capital asset projects through the adoption of an expanded basis of design that considers all aspects of a capital assets life cycle. In many projects today the basis of design (BOD) largely encompasses the engineering parameters which are required to meet the owner’s project requirements. Constructability and maintainability are often treated as review items to confirm that the developed design is both constructible and maintainable and to suggest improvements at the margins. Effective constructability and maintainability reviews add value to the project but do not fundamentally act to shape the design itself in most instances. The premise of this paper is that more, much more, is required to develop effective designs that are developed with construction and maintenance as fundamental project requirements. In this sense construction and maintenance considerations are not items to be reviewed but rather fundamental requirements to be satisfied together with other project requirements established by the owner. The change suggested is about a shift in mindset and perspective as well as in our design work processes.

Business basis of design

Embed Size (px)

DESCRIPTION

Addressing Project Capital Efficiency through a Business Basis of Design Large capital construction projects in both the industrial and infrastructure sectors are challenged today in three significant ways:  Capital efficiency of the project – this considers both first costs as well as life cycle costs  Capital certainty – reflecting execution efficiency, predictability and effective risk transfer through appropriate contracting strategies  Time to market – perhaps best thought of as schedule certainty but also accelerated delivery of projects, often an essential ingredient in capital efficiency This paper focuses on achieving improved capital efficiency in large capital asset projects through the adoption of an expanded basis of design that considers all aspects of a capital asset’s life cycle. In many projects today the basis of design (BOD) largely encompasses the engineering parameters which are required to meet the owner’s project requirements. Constructability and maintainability are often treated as review items to confirm that the developed design is both constructible and maintainable and to suggest improvements at the margins. Effective constructability and maintainability reviews add value to the project but do not fundamentally act to shape the design itself in most instances. The premise of this paper is that more, much more, is required to develop effective designs that are developed with construction and maintenance as fundamental project requirements. In this sense construction and maintenance considerations are not items to be reviewed but rather fundamental requirements to be satisfied together with other project requirements established by the owner. The change suggested is about a shift in mindset and perspective as well as in our design work processes.

Citation preview

Page 1: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 1 of 21

Addressing Project Capital Efficiency through a

Business Basis of Design

By Bob Prieto

Large capital construction projects in both the industrial and infrastructure sectors are

challenged today in three significant ways:

Capital efficiency of the project – this considers both first costs as well as life

cycle costs

Capital certainty – reflecting execution efficiency, predictability and effective risk

transfer through appropriate contracting strategies

Time to market – perhaps best thought of as schedule certainty but also

accelerated delivery of projects, often an essential ingredient in capital efficiency

This paper focuses on achieving improved capital efficiency in large capital asset

projects through the adoption of an expanded basis of design that considers all aspects

of a capital asset’s life cycle. In many projects today the basis of design (BOD) largely

encompasses the engineering parameters which are required to meet the owner’s

project requirements.

Constructability and maintainability are often treated as review items to confirm that the

developed design is both constructible and maintainable and to suggest improvements

at the margins. Effective constructability and maintainability reviews add value to the

project but do not fundamentally act to shape the design itself in most instances.

The premise of this paper is that more, much more, is required to develop effective

designs that are developed with construction and maintenance as fundamental project

requirements. In this sense construction and maintenance considerations are not items

to be reviewed but rather fundamental requirements to be satisfied together with other

project requirements established by the owner. The change suggested is about a shift in

mindset and perspective as well as in our design work processes.

Page 2: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 2 of 21

1. Terminology & Definitions

The following constitute the key terminology used throughout this paper and provide the

context for a so-called “Business Basis of Design”. This term, an “expanded basis of

design” and BODX are all used synonymously in this paper.

Owner’s Project Requirements (OPR) – sometimes confusingly called “design intent”

but referring to OPR

BOD – Functional or performance based narrative description of what designer will do

to meet OPR; finalized at end of construction; includes assumptions and criteria used

CBOD – Construction Basis of Design – narrative description of construction

requirements to be reflected in design (developed by construction manager) and

finalized at end of construction; includes assumptions and constraints used including

means & methods preferences (specific tools or equipment as an example)

O&MBOD – O&M Basis of Design - narrative description of operations and

maintenance (O&M) requirements to be reflected in design (developed by

operator/O&M) and finalized at end of construction; includes maintenance philosophy,

assumptions and criteria used. Provides a basis for development of the O&M program

and manual.

BODX – Expanded basis of design, collectively incorporating the traditional engineering

basis of design (BOD), new construction basis of design (CBOD) and a new operating

and maintenance basis of design (O&MBOD). BODX is driven by construction and O&M

considerations while meeting the performance and functional requirements typically

detailed in the OPR.

2. Focus of BODX

The Business Basis of design or BODX is focused on improving the quality and cost

effectiveness of the developed design throughout the full life cycle. Specifically it:

Ensures all project participants are aligned on strategic business objectives as

reflected in OPR

Ensures owner, construction management and O&M are clear on wants and

needs

Page 3: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 3 of 21

Ensures designer is focused on supporting an efficient construction execution

strategy which reflects project construction considerations, opportunities and

constraints

Informs the process for identification, evaluation and selection of design solutions

to meet functional or performance specifications.

Provides expanded criteria to evaluate and validate design solutions and

submissions

Provides clear acceptance criteria verified during construction, commissioning

and initial operation

Informs decisions on equipment selection, layout, installation, operation,

maintenance and replacement until requirements change

Delivers a more effective asset management database at startup

Improves construction efficiency and effectiveness

Enhances construction safety

Improves O&M efficiency and effectiveness

Supports 7DSM Optioneering – considering all life cycle costs

The BODX encompasses the traditional “engineering” basis of design as well as an

expanded basis of design encompassing construction, operations and maintenance

considerations. The following sections will further develop the scope and content of both

the construction basis of design (CBOD) and operations and maintenance basis of

design (O&MBOD). Common to each of the three basis of design requirements are the

following three elements:

Project Narrative

Rationale from the defined perspective

Validation and verification

This last element is often not adequately addressed in developed basis of design

documents but takes on increased importance as:

Inspection technologies allow us to “see” previously undetectable flaws

Construction means and methods around which a design may be developed are

assessed for completeness of design inclusion and actual effectiveness

Performance based standards and contracting take on larger roles in facility

development and operation.

Let’s look at some of the elements that comprise these expanded elements of the basis

of design.

Page 4: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 4 of 21

3. Elements of a Construction Basis of Design (CBOD)

The CBOD seeks to further actualize CII Constructability Concepts I-1 and I-5.

CII Constructability Concept I-1 states “Constructability Program is an integral

part of the Project Execution Plan.”

CII Constructability Concept I-5 states “Basic design approaches consider major

construction methods.”

Specific elements that an effective construction basis of design will consider include:

Comprehensive identification of required or preferred construction strategies, tactics,

techniques and tools to be incorporated in the construction process that influence

project management and design

Construction labor, skills, equipment, materials of construction, logistical constraints

to be reflected in basis of design

Construction Basis of Design addresses unique requirements to be incorporated in

design development that reflects owner or contractor preferences for achieving the

owner’s project requirements (OPR).

These requirements may reflect:

Prior experience of the owner

Unique risks, opportunities or constraints associated with the project

Contractor capabilities and experience

Special tools uniquely available to the project

Broader programmatic objectives required of the owner or independently

committed to by the owner that influences construction execution.

Applicable safety program to be used on project

CBOD considerations may be broadly grouped as basis of design requirements

related to:

Labor

Equipment

Materials

Means & methods

Management processes and practices

Page 5: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 5 of 21

Labor

Sourcing

Labor relations

(1) Work rules and requirements

(2) Labor jurisdictional requirements to be addressed

Visa requirements, limitations, process durations

Multi-national labor force impact on site segregation and development

Safety

Hazard elimination

(1) Hazard avoidance or reduction features to be facilitated by design

(a) Eliminate hazards

The unique lifting capabilities of the Left Coast Lifter fundamentally altered

design and significantly reduced capital costs on the new Tappan Zee Bridge.

Photo: Left Coast Lifter – SFOBB

"Photograph © Joseph A. Blum"

Page 6: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 6 of 21

(b) Pinch points

(c) Heavy lifts minimized or eliminated

(i) Use of jack up construction

(ii) Vertical modules

(d) Work at height

(i) minimized or eliminated by construction at grade (less than 6’)

(ii) permanent structures incorporate platforms or provisions for

temporary platforms

Hazard mitigation

(1) Reduce the hazard

(a) Equip any required scaffolding with railings and toe boards

(2) Improved access to workface

(a) Access requirements for construction identified considering sequence

of construction (and maintenance)

(b) Enhanced positional awareness through use of RFID

Knowledge

Labor

(1) activity linked safety and skills training reflected in construction resourcing

plan and master project schedule

(2) activity linked equipment, materials and tools to facilitate staging and

reduction in idle time

(3) reskilling for later stage activities including maintenance phase activities

Mining project stockpile utilized jack up construction to help reduce

heavy lifts at the site

Page 7: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 7 of 21

Welfare

Onsite medical facilities and requirements

Camp requirements (facilities and services)

Productivity

Enhance labor productivity through design

(1) Minimize the number of sku’s for components and materials to be

manually installed (nuts & bolts; welds; fasteners)

(2) Use controlled environments at environmentally challenged sites

(a) Early usage of permanent facilities (warehouse, admin building)

(b) Temporary facilities provided for in plot plan development (dynamic air

shelters)

Equipment

Procurement

Labeling/tracking requirements (barcode/RFID)

Measurement units in installation (and maintenance) documents

(English/metric)

Orientation of installation schematics to conform to installation position

Hazard mitigation

(1) No sharp corners

Logistics

Incorporation of adequately sized and placed lifting points

Shipping and packaging to eliminate removal of temporary bracing

Single stream protection and packaging materials to facilitate recycling

Installation

Self alignment

Self leveling

Required laydown and movement envelopes including associated logistical

equipment

Access corridors for installation

Pre-commissioning

Incorporation of pre-commissioning isolation valves and electrical lockouts

required

Accessible temporary attachment points for test equipment

Materials

Preferred material sources and alternates and impact on design

Material tracking requirements to be reflected in design specifications

Page 8: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 8 of 21

Preferred logistical approach and impact on design

On-site use of batch plant – available quality of concrete

Concrete placement strategy – pumped vs. bucket

On-site bending of rebar – quality considerations to be reflected in design

On-site welding of pipe and structural steel assemblies – impact on design and

construction sequence

Means & methods

Focus is on means and methods selection rationale for design impacting

elements of construction

Strategies

Reduce indirects

(1) Reduce general conditions cost by

(a) shortening schedule elements with high GC costs (specialized labor or

equipment)

(b) reducing overall project schedule

Reduce need for enabling works

(1) reduce overall project schedule

Modularization/fabrication with appropriate metrics such as manhours

displaced embedded in each shipment received

Requirements for off-site construction

Tactics

Reduce temporary works

(1) Minimize need for scaffolding by incorporating platforms or support for

temporary, reusable platforms in structural design

(2) Incorporate temporary steel for shipping of assemblies in final assembly

design to eliminate removal of shipping steel

Reuse formwork and temporary works

(1) Size foundations to re-use formwork

Minimize excavations

Techniques

Lift many once – high lifts with long duty cycle benefit from lifting many items

at once to height and final placing with alternate equipment

(1) Daisy chaining requires lift points that facilitate safe lift

(2) Racking and packaging for lifts may eliminate lifting skids and pallets

Tools

Unique equipment to be employed

(1) Heavy lift

Page 9: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 9 of 21

(a) Example – Left Coast Lifter

(2) Welding

(3) RFID

Management processes and practices

Owner’s policies, guidelines or other directives affecting construction

Regulatory limitations on construction practices, means & methods

Desired sequence of construction

Early works packages required

Permanent facilities to support construction

Trade sequencing or other labor driven sequencing

Restricted construction

Preliminary execution strategy and plan

Eliminate later stage trenching operations impacting site logistics

Incorporate commissioning sequence and temporary facilities and equipment

Establish “site needs” dates (including mod yard need dates)

RFI reduction by reflecting means & methods considerations in design model

(BIM)

Sustainability

Construction energy, water, waste requirements

(1) Energy

(2) Waste

(3) Water

(4) Social

(a) Knowledge transfer

(b) Community development

(c) Industry development

(i) Areas targeted for local sourcing

Validation and verification

Quality control and assurance

Commissioning

Provisions to be reflected in design

(1) Systems/subsystems/components should be designed to be functionally,

mechanically, electrically and electronically as independent as practical to

facilitate pre-commissioning testing.

(2) Recognize that commissioning starts with the first drawings in the

feasibility stage

Workface planning

Page 10: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 10 of 21

4. Elements of O&MBOD

Operating and maintenance costs often represent over half of life cycle costs of a

capital asset on a present worth basis as shown in the following figure for a typical

steam assisted gravity drain (SAGD) oil sands project.

Development of an effective O&M basis of design should as a minimum encompass:

Comprehensive identification of required or preferred construction strategies, tactics,

techniques and tools to be incorporated in the operations and maintenance (O&M)

process that influence design

O&M labor, skills, equipment, materials (including consumables), temporary

provisions for maintenance to be reflected in basis of design

O&M Basis of Design addresses unique requirements to be incorporated in design

development that reflects owner or contractor preferences for achieving the owner’s

project requirements (OPR).

These requirements may reflect:

Prior experience of the owner

Page 11: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 11 of 21

Unique constraints associated with the project location; environmental setting;

process operations; and labor availability, cost and skills level.

Contracting community capabilities and experience

Special tools required for major maintenance

Broader programmatic objectives required of the owner or independently

committed to by the owner that influences maintenance execution.

Applicable safety program to be used during facility operation

O&MBOD considerations may be broadly grouped as basis of design

requirements related to:

Labor

Equipment

Materials

O&M practices and techniques

Management processes and practices

Pipe location makes replacement due to high abrasion rates difficult (shown in

thermal image). Consideration in O&MBOD would have identified this added basis of

design.

Page 12: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 12 of 21

Labor

Sourcing

Provisions required to address union work rules

Provisions required to meet workforce cultural or local practices requirements

(1) Example – prayer rooms; special food preparation requirements; gender

segregation

Safety

Hazard elimination

(1) Identify changed safety conditions associated with maintenance activities

and eliminate or mitigate new safety hazards

(2) Access points and covers should not have sharp corners

(3) Design should reflect safe access for maintenance and repair

(4) Avoid hazardous access points (manholes in live traffic areas)

(5) Reduce weight of components frequently moved (manhole cover; access

plate; paving slabs; concrete curbs)

The need for access to valves on tail pumps would be part of an O&MBOD

Page 13: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 13 of 21

(6) Provide for “isolation” of equipment to maintenance under continuous

operations

(a) Lockout valves and switches

(b) Electrical isolation

Hazard mitigation

(1) Reduce the hazard

(a) Minimize work at height

(b) Minimize hand operations during maintenance

(c) Minimize potential pinch points

(d) Minimize sharp corners

(e) Minimize exposure time in extreme environments associated with

periodic maintenance

(f) Minimize need for lifts or temporary ladders for routine maintenance

(2) Improved access to workface

Heater controls are local to the heater only, with no access to

the control panel which is 6 meters above the ground. An

O&MBOD would identify accessibility requirements to reduce

work at heights.

Page 14: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 14 of 21

(a) Required work platforms and equipment laydown or pull areas to be

reflected in design

(b) Space provisions for temporary equipment required for maintenance

operations and accessibility envelope

Knowledge

Ensure full engineering, procurement, construction data pull through to asset

management and O&M systems

Productivity

Facilitate grouping or simultaneous performance of maintenance operations

Equipment

Maintenance

Incorporate maintenance provisions in design development

(1) Reflect maintenance set-up and staging requirements

(2) Identify typical combinations of maintenance activities in plant and

systems design and layout

(3) Design for rapid replacement of routine maintenance items (plug and play;

quick opening fasteners)

(4) Systems/subsystems/components should be designed to be functionally,

mechanically, electrically and electronically as independent as practical to

facilitate maintenance and testing.

(5) Maintenance “envelops” should be reflected in design layouts

(6) Increase accessibility to areas of frequent maintenance

(a) Provide flat laydown areas for components removed during

maintenance or replacement

(b) Identify provisions for maintenance (scaffolding, lifts etc)

(c) Identify any maintenance crane or other temporary equipment support

points and confirm capacity and clearances

(7) Minimize joints and bearings

Incorporate temporary maintenance provisions in base design to avoid use of

temporary hoses, power lines etc.

(1) Power

(2) Water

(3) Compressed gases

(4) Wastewater including spill collection

(5) Attachment points (for lifting equipment for access removal or repair or

replacement)

Page 15: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 15 of 21

(6) Attachment points for temporary crane rails or mobile equipment

envelopes

Repair

Reduce spare parts requirements, costs and risks through design

(1) Minimize spare part types

(2) Identify long lead items for spares planning

(3) Ensure long term availability for spares

(4) Standardization of components to minimize maintenance spares and tool

sets

Replacement

All machines fail and must be repaired or replaced. Provide for this activity.

(1) Consider replacement strategies for major components over the project’s

full lifetime

Materials

Minimize maintenance to the extent achievable

Improve deterioration and environmental resistance of exposed systems and

structures (mildew; organic pollutants)

Page 16: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 16 of 21

(1) Moisture – eliminate ponding especially on exposed steel surfaces; ensure

good drainage

(2) Caustic materials including materials associated with cleaning and

maintenance

(3) UV light

Minimize need for painting

Minimize surface and material wear

(1) Identify potential areas susceptible to corrosion abrasion

O&M practices and techniques

Unique O&M practices or techniques to be utilized and provided for in design

Management processes and practices

Build O&M documentation from initiation of design

FMEA and FTA analysis should be included in system and component

maintenance documentation

Identify all maintenance assumptions and requirements in design documents

and consolidate and track

O&M information, including equipment and vendor data, required to be directly

incorporated in the facility asset model (building information model (BIM)) or

database

Contractual provisions to support long term O&M

Special warranty or servicing requirements

Performance contracting requirements

5. Conclusion

The rational and role for an expanded basis of design or a so called “Business Basis of

Design” is initially established and new terminology to address the elements of an

expanded and more robust basis of design laid out. Initial scopes of a construction basis

of design and an operations and maintenance basis of design have been laid out with a

framework to support further development. Finally, checklists to guide development of

these expanded elements of the basis of design document have been provided in

Tables 1 and 2.

Page 17: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 17 of 21

References

1. Application of Life Cycle Analysis in the Capital Assets Industry; Construction Management Association of America (CMAA); June 2013; ISBN 978-1-938014-06-2 (eBook); ISBN 978-1-938014-07-9 (Print)

2. Life Cycle Analysis – a 7DSM Future; National Institute of Building Sciences; January 9, 2014

3. Application of Life Cycle Analysis in the Capital Assets Industry; PM World Today; March 2012

4. How Radically will Project Execution Change: A 7DSM Future; CMAA Future Focus; Washington DC; March 4 -5, 2012

Page 18: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 18 of 21

Table 1

BODX Checklist - CBOD

General

Comprehensive identification of required or preferred construction strategies, tactics,

techniques and tools

Construction labor, skills, equipment, materials of construction, logistical constraints

to be reflected in basis of design

Unique requirements that reflects owner or contractor preferences such as:

Prior experience of the owner

Unique risks, opportunities or constraints associated with the project

Contractor capabilities and experience

Special tools uniquely available to the project

Broader programmatic objectives required of the owner or independently

committed to by the owner that influences construction execution.

Applicable safety program to be used on project

Specific

CBOD considerations may be broadly grouped as basis of design requirements related

to:

Labor

Equipment

Materials

Means & methods

Management processes and practices

Labor

Sourcing

Safety – hazard elimination and mitigation

Knowledge

Welfare

Productivity

Equipment

Procurement

Logistics

Installation

Materials

Page 19: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 19 of 21

Preferred material sources

Material tracking

Preferred logistical approach

On-site material activities

Means & methods

Focus on design impacting elements of construction

Strategies

Reduce indirects

Reduce need for enabling works

Modularization/fabrication with appropriate metrics

Requirements for off-site construction

Tactics

Reduce temporary works

Minimize excavations

Techniques

Tools - Unique equipment to be employed

Management processes and practices

Owner’s policies, guidelines or other directives affecting construction

Regulatory limitations on construction practices, means & methods

Desired sequence of construction

RFI reduction

Sustainability

Construction energy, water, waste requirements

Commissioning - Provisions to be reflected in design

Workface planning

Page 20: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 20 of 21

Table 2

BODX Checklist - O&MBOD General

Operations and maintenance (O&M) process that influence design

O&M labor, skills, equipment, materials (including consumables), temporary

provisions for maintenance to be reflected in basis of design

Unique requirements such as:

Contracting community capabilities and experience

Special tools required for major maintenance

Broader programmatic objectives required of the owner or independently

committed to by the owner that influences maintenance execution.

Applicable safety program to be used during facility operation

Specific

O&MBOD considerations may be broadly grouped as basis of design requirements related to:

Labor

Equipment

Materials

O&M practices and techniques

Management processes and practices

Labor

Sourcing

Safety

Knowledge

Productivity

Equipment

Maintenance – provisions; combinations; accessibility, minimization

Repair – minimization of spare types

Replacement

Materials – minimize maintenance

O&M practices and techniques that are unique

Management processes and practices

Documentation

Asset management

Contractual provisions to support long term O&M

Page 21: Business basis of design

PM World Journal Addressing Project Capital Efficiency Vol. III, Issue IV – April 2014 through a Business Basis of Design www.pmworldjournal.net Featured Paper by Bob Prieto

© 2014 Bob Prieto www.pmworldlibrary.net Page 21 of 21

About the Author

Bob Prieto Senior Vice President Fluor Princeton, NJ, USA

Bob Prieto is a senior vice president of Fluor, one of the largest, publicly traded engineering and construction companies

in the world. He is responsible for strategy for the firm’s Industrial & Infrastructure group which focuses on the development and delivery of large, complex projects worldwide. The group encompasses three major business lines including Infrastructure, with an emphasis on Public Private Partnerships; Mining; and Industrial Services. Bob consults with owners of large engineering & construction capital construction programs across all market sectors in the development of programmatic delivery strategies encompassing planning, engineering, procurement, construction and financing. He is author of “Strategic Program Management”, “The Giga Factor: Program Management in the Engineering and Construction Industry” and “Application of Life Cycle Analysis in the Capital Assets Industry” published by the Construction Management Association of America (CMAA) and “Topics in Strategic Program Management” as well as over 450 other papers and presentations. Bob is a member of the ASCE Industry Leaders Council, National Academy of Construction and a Fellow of the Construction Management Association of America. Bob served until 2006 as one of three U.S. presidential appointees to the Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC), working with U.S. and Asia-Pacific business leaders to shape the framework for trade and economic growth and had previously served as both as Chairman of the Engineering and Construction Governors of the World Economic Forum and co-chair of the infrastructure task force formed after September 11th by the New York City Chamber of Commerce. Previously, he served as Chairman at Parsons Brinckerhoff (PB), one of the world’s leading engineering companies. Bob Prieto can be contacted at [email protected].