BEST PRACTICES OF ADITYA CEMENT
WORKS SITE, CHITTAURGARH (RAJ.)
FOR IMPLEMENTATION AND CONTINUAL
IMPROVEMENT-DLCL
CLINKER SILO – AN AERIAL VIEW
Major Qty’s Involved in Each lift of
Jump form
Reinforcement - 56.5 Mt
PT Ducting - 960 Rm ( Avg )
PT cable - 1080 Rm / 5 MT
Shuttering - 780 sqm
Concrete - 215 Cum
CLINKER SILO Jump form – Lift Cycle
time 6 Days Achieved in UTCL – Aditya
project
Repairing Material Made in Lab to match the texture of old concrete
with new concrete and defect repairs .
ARRANGEMENT OF GOOD COMMUNICATION SYSTEM BY
WALKIE-TALKIE BETWEEN TOWER CRANE OPERATOR &
SIGNAL MAN
39
42
Safety arrangement in Central Shaft Silo- Safe
access, fall protection with safety net & guard rails.
43
New initiatives: Life line arranged at outer & inner
side on climbing bracket platform in clinker silo.