Bandra-Worli Sea Link Project

Submitted By:Sulakshya Gaur(121684)Aayush Mittal(121685)Harshit Thakur(121689)Rajat Bhardwaj(121696)Puneet Goyal(121699)

Page 2: Bandra worli sea link,Mumbai,Maharashtra,India

INTRODUCTION

Bandra Worli Sea Link(BWSL) is the civil engineering marvel spanning across the arc of Mumbai coastline .•Started in 2000•Opened in 2009

Page 3: Bandra worli sea link,Mumbai,Maharashtra,India

Reduces timeRegulation of trafficStress free drivingReduces accidents and noise pollution

OBJECTIVES

Page 4: Bandra worli sea link,Mumbai,Maharashtra,India

Use of M60 grade concreteLargest span for cable stayed bridgeDimensionsMaterial usedIndia’s first bridge in open sea conditionsAn intelligent bridge management system (IBS) provides traffic information, surveillance, monitoring and control systems.Partners involved were ultratech, TATA steel, VSL Singapore, SPCC etc.

HIGHLIGHTS

Page 5: Bandra worli sea link,Mumbai,Maharashtra,India
Page 6: Bandra worli sea link,Mumbai,Maharashtra,India

The entire project was originally conceived as one large project comprising, different components, but in order to accelerate the overall construction schedule, the project has been divided into five construction packages.

Package I: Construction of flyover over Love Grove junction at Worli.

Package II: Construction of cloverleaf interchange at Mahim intersection.

Package III: Construction of solid approach road from the Mahim intersection up to the start of the Toll Plaza on the Bandra side.

Project Overview

Page 7: Bandra worli sea link,Mumbai,Maharashtra,India

Package IV: Construction of Cable-Stayed Bridges together with viaduct approaches extending from Worli up to the Toll Plaza at Bandra end, Intelligent Bridge System (IBS).

Package V: Improvement to Khan Abdul Gaffar Khan Road.

Page 8: Bandra worli sea link,Mumbai,Maharashtra,India

Package IV is the largest and main phase of Bandra-Worli Sea Link Project. Main features of this technically challenging package are :

Cable-Stayed Bridge including viaduct approaches extending from Worli up to Toll Plaza at Bandra end.

Modern Toll Plaza.

Details of Package – IV

Page 9: Bandra worli sea link,Mumbai,Maharashtra,India

The work order for work of construction of BWSL bridge was issued to HCC for Rs.400.23 crore. The completion time was stated as 30 months from the date of notice to proceed with the work.

The bridge layout is categorized into three different parts:

Part 1 - North-end approach structure. Part 2 - Cable-Stayed Bridge. Part 3 - South end approach structure.

Main Bridge Structure

Page 10: Bandra worli sea link,Mumbai,Maharashtra,India

A modern toll plaza with 16 lanes is provided at the Bandra end. The toll plaza is equipped with a state-of-the-art toll collection system. A structure is provided at this location to house the control system for the ITS.

Toll Plaza

Page 11: Bandra worli sea link,Mumbai,Maharashtra,India

Engineering Challenges 1) Laying of foundation 2) Heavy spans 3) Design of concrete tower 4) ground stabilization

Challenges Encountered

Page 12: Bandra worli sea link,Mumbai,Maharashtra,India

Working during monsoon

Logistics

Psychological conditioning

Page 13: Bandra worli sea link,Mumbai,Maharashtra,India

Change in design of the bridge

Change in the contractors and the delay caused by them.

Page 14: Bandra worli sea link,Mumbai,Maharashtra,India

Some of the Experts Involved

Page 15: Bandra worli sea link,Mumbai,Maharashtra,India

Estimated savings in Vehicle Operating Costs (VOC): Rs. 100 Crores per annum.

Considerable savings in travel time (20 to 30 minutes) due to increased speed and reduced delays (23 signals avoided).

Stress free driving. Reduced accidents. Reduction in traffic on existing roads because of

traffic diversion to the Sea Link.

PROJECT BENEFITS / OTHER FEATURES

Page 16: Bandra worli sea link,Mumbai,Maharashtra,India

Reduction in Carbon Monoxide and Nitrogen Oxide Levels in Mahim, Dadar, Prabhadevi and Worli along existing roads.

Reduced noise pollution in Mahim, Dadar, Prabhadevi and Worli along existing roads.

No adverse effect on fisheries, marine life and livelihood of fisherman.

Landscaping along the approaches and waterfront promenade enhance the environment and add green spots to the city.

Project benefits continued..

Page 17: Bandra worli sea link,Mumbai,Maharashtra,India

Night Lit view of BWSL

Page 18: Bandra worli sea link,Mumbai,Maharashtra,India

The cost of the Bandra-Worli Sea Link Project originally (July 1999) estimated at Rs.665.81 crore was revised (August 2004) to Rs.1,306.25 crore.

Though the project was originally expected to be completed by March 2003, the expected date of completion is now stated to be April 2008.Delay were mainly due technical changes brought up by new consultants .

Conclusion Report

Page 19: Bandra worli sea link,Mumbai,Maharashtra,India

The Company changed the design of the Worli bridge to “Cable stay” from “Arch bridge” to align with the bridge at Bandra, a decision, which could have been taken at the initial stages itself.

Against a commitment of Rs.580 crore by way of grants, the State Government had provided only Rs.100 crore till June 2007.

Page 20: Bandra worli sea link,Mumbai,Maharashtra,India

The selection process of Consultant for the design and project management work was defective, as the Company did not verify the technical parameters as projected by the Consultant.

The Company did not levy Liquidated Damages amounting to Rs.12.80 crore on the Contractor (HCC) as per conditions of the contract despite wrongful stoppage of work by them for 18 months and non-achievement of milestones due to poor progress of work.

Page 21: Bandra worli sea link,Mumbai,Maharashtra,India