Upload
american-society-of-civil-engineers-orange-county-branch
View
173
Download
2
Tags:
Embed Size (px)
Citation preview
MM-T5-05
A STORM DRAIN SUCCESS
STORY:
TWO TUNNELS & A LANDSLIDE
RANDALL G. BERRY, PE
NASTT’s 2015 No-Dig Show
• Project Background / Needs
• Project Solutions - Overview
• Trenchless Methodologies
• Project Solutions - Details
AGENDA
Hydrology Map
• Watershed =
184 Acres
• Q100 =
262 CFS
48” pipe required
54” pipe installed
> 100-yr
protection
25th Street
Inlet
Structure
Slide
Why steel pipe storm drain mainline? • High velocities = 45 feet per second (fps)
• Sediment and cobble laden flows
No room & too steep (10%) for desilting basin
“Returning the River to the Sea” concept
Beach replenishment & less inlet maintenance
Why steel pipe storm drain mainline? • Considered pipe: RCP, HDPE, and CCFRPM
(fiberglass) pipe, but all eliminated due to poor
resistance to long-term scouring & cobble impacts
• Chose: 54” Dia. Permalok Steel Pipe w/ epoxy
coating & lining = push joint = no welding in field
• But during construction we
changed to field-welded
spiral wound steel pipe -
saved $630K split by city
and contractor ($315k)
“Slant Drain” Tunnel - Rotohead
80” Dia -
Front of
jacking train
Direction
Correction
Flaps
Laser
Target
Ron
Dragoo
(RPV)
• Inclinometer (Geokon
Model 6400): Between
launch pit and mobile
homes to monitor
potential horizontal
movement
• Extensometer (Geokon
Model A3, MPBX): At
25th Street crossing
over tunnel alignment
to monitor potential
vertical movement
“Slant Drain” Tunnel - Outlet
Cost savings credit #2:
Using tieback anchors
instead of soldier plies (as
was used on McCarrell
Cyn SD, at right)
Savings = $214k split for
$107k credit to city
McCarrell Canyon SD Outlet
L = 2,200’ S= 14%
Long Tunnel – Rib & Lagging
25th St
45’ deep
Launch
Pit
90’ deep
At Lower
Switchback
Phase Begin End
PSR & Pre-Design April 2009 June 2011
Design Phase July 2011 October 2012
Bid Phase December 2012 January 2013
Construction Phase April 2013 September 2014
Line Item True Cost (% Change) Engineer’s Estimate
Original Construction Bid $15,140,000 (-1.7%) $15,400,000*
Post Award Value
Engineering** -$422,676 (-2.8%)
Project Change Orders*** +$ 731,874 (+5.6%) (1.72 % related to original design)
Final Construction Costs $15,449,198
Pre-Construction Soft Costs $950,919
Construction Soft Costs $1,350,995
Total Project Cost = $17,751,112 NOTES:
* Engineer’s (base) estimate (without a 10% contingency)
** Value engineering in pipe material & outlet structure shoring/construction yielded net credits to the city
*** Change orders included approx +$600k to enhance PVDE roadway and drainage (not in original design), +$260k in
changes related to the original design and a <$130k> credit to cover city staff weekend/OT work.
Environmental Clearances:
• U.S. Army Corp of Engineers
(Section 404 of the Clean Water Act)
• Calif Department of Fish and Wildlife
(1602 – Streambed Alteration Agreement)
• U.S. Fish and Wildlife Services
• California Coastal Commission- federal
consistency determination
• Los Angeles Regional Water Quality Control
Board - 401 certification
• City of Rancho Palos Verdes –
CEQA Lead agency
Project Team City of Rancho Palos Verdes:
• Michael Throne, PWD
• Ron Dragoo, Principal Engineer
Harris & Associates:
• Randall Berry, PM
• Liz Reyes, Deputy PM
KOA Corporation:
• Alan Braatvedt, City’s PM/CM
• Mike Jenkins, City’s CM
Ninyo & Moore:
• Jim Barton & Daniel Chu,
Geotechnical Engineering
L. H. Woods:
• Michael Ireland, Prime
Contractor
Drill Tech:
• Derek McDonald,
Tunnels/tiebacks
SFC Consultants:
• Saundra Jacobs, Environ.
BGB Design Group:
• Art Guy, Landscape Architect
KDM Meridian:
• Richard Maher, Survey &
Movement Monitoring
THE END
Southern Chapter APWA 2014
“Project of the Year” Award
“Innovation” Category
National APWA 2015
Small City “Project of the Year” Award
“Disaster / Emergency Repair” Category