55
MM-T5-05 A STORM DRAIN SUCCESS STORY: TWO TUNNELS & A LANDSLIDE RANDALL G. BERRY, PE NASTT’s 2015 No-Dig Show

ASCE San Ramon Canyon Storm Drain 6 4-15

Embed Size (px)

Citation preview

MM-T5-05

A STORM DRAIN SUCCESS

STORY:

TWO TUNNELS & A LANDSLIDE

RANDALL G. BERRY, PE

NASTT’s 2015 No-Dig Show

• Project Background / Needs

• Project Solutions - Overview

• Trenchless Methodologies

• Project Solutions - Details

AGENDA

San Ramon Canyon Storm Drain Rancho Palos Verdes, Los Angeles Co, CA

Project

Location

Pacific

Ocean

San Ramon Canyon Storm Drain

McCarrell Cyn SD

2014 NASTT

San Ramon Cyn SD

2015 NASTT

25th Street January 19, 2010

Localized 100-Year (rain gauge)

San Ramon Cyn – Background

25th Street

San Ramon Cyn

San Ramon

Cyn

Tarapaca Landslide

San Ramon

Cyn

PVDE Switchbacks

2’ - 5’ Erosion

Per year – lower

PVDE Switchback

Slide

Bluff

Erosion

Storm Blow Back

Ex. Outlet

San Ramon Cyn SD – Overview

Hydrology Map

• Watershed =

184 Acres

• Q100 =

262 CFS

48” pipe required

54” pipe installed

> 100-yr

protection

25th Street

Inlet

Structure

Slide

Location of Upstream Inlet

Historic Flood Path Proposed SD

Existing SD

100’ fire break

L = 300’

S= 38%

Pacific

Ocean

Why steel pipe storm drain mainline? • High velocities = 45 feet per second (fps)

• Sediment and cobble laden flows

No room & too steep (10%) for desilting basin

“Returning the River to the Sea” concept

Beach replenishment & less inlet maintenance

Why steel pipe storm drain mainline? • Considered pipe: RCP, HDPE, and CCFRPM

(fiberglass) pipe, but all eliminated due to poor

resistance to long-term scouring & cobble impacts

• Chose: 54” Dia. Permalok Steel Pipe w/ epoxy

coating & lining = push joint = no welding in field

• But during construction we

changed to field-welded

spiral wound steel pipe -

saved $630K split by city

and contractor ($315k)

“Slant Drain” Tunnel

Launch

Pit

“Slant Drain” Tunnel - Rotohead

80” Dia -

Front of

jacking train

Direction

Correction

Flaps

Laser

Target

Ron

Dragoo

(RPV)

“Slant Drain” Tunnel Launch Pit

80” Jacked Steel Sleeve

& 54” Jacked / Welded /

Lined Steel Pipe

• Inclinometer (Geokon

Model 6400): Between

launch pit and mobile

homes to monitor

potential horizontal

movement

• Extensometer (Geokon

Model A3, MPBX): At

25th Street crossing

over tunnel alignment

to monitor potential

vertical movement

Bluff Protection – “Geobrug”

“Slant Drain” Tunnel - Outlet

Cost savings credit #2:

Using tieback anchors

instead of soldier plies (as

was used on McCarrell

Cyn SD, at right)

Savings = $214k split for

$107k credit to city

McCarrell Canyon SD Outlet

Outlet Structure – Tieback Anchors

“Slant Drain” Tunnel - Outlet

Outlet Structure

54” Welded Steel Pipe

With Epoxy Lining

& Velocity Reducer Rings

Open

Trench

Seepage

Flow Dam

-prevents

bedding

zone

acting as

conduit to

bluff face

Upstream Inlet

Receiving Pit

Launch Pit

Long Tunnel – Rib & Lagging

L = 2,200’ S= 14%

Long Tunnel – Rib & Lagging

25th St

45’ deep

Launch

Pit

90’ deep

At Lower

Switchback

Rib & Lag Tunnel - Launch Pit

Rotohead

Multiple

Muck Carts

Rib & Lag Tunnel – Launch Pit

Train

Rotohead Emerging at Inlet Structure

Inlet Structure:

•CIDH Piles

•Grade Beam

•Soil Anchors

Completed

Inlet

Structure,

Access

Road

& Canyon

Fill

Tarapaca Slide – Gravity Buttress Fill

Head Scarp

PVDE

Switchbacks

Long Tunnel

Launch Pit

Long Tunnel

Launch Pit

Phase Begin End

PSR & Pre-Design April 2009 June 2011

Design Phase July 2011 October 2012

Bid Phase December 2012 January 2013

Construction Phase April 2013 September 2014

Line Item True Cost (% Change) Engineer’s Estimate

Original Construction Bid $15,140,000 (-1.7%) $15,400,000*

Post Award Value

Engineering** -$422,676 (-2.8%)

Project Change Orders*** +$ 731,874 (+5.6%) (1.72 % related to original design)

Final Construction Costs $15,449,198

Pre-Construction Soft Costs $950,919

Construction Soft Costs $1,350,995

Total Project Cost = $17,751,112 NOTES:

* Engineer’s (base) estimate (without a 10% contingency)

** Value engineering in pipe material & outlet structure shoring/construction yielded net credits to the city

*** Change orders included approx +$600k to enhance PVDE roadway and drainage (not in original design), +$260k in

changes related to the original design and a <$130k> credit to cover city staff weekend/OT work.

Environmental Clearances:

• U.S. Army Corp of Engineers

(Section 404 of the Clean Water Act)

• Calif Department of Fish and Wildlife

(1602 – Streambed Alteration Agreement)

• U.S. Fish and Wildlife Services

• California Coastal Commission- federal

consistency determination

• Los Angeles Regional Water Quality Control

Board - 401 certification

• City of Rancho Palos Verdes –

CEQA Lead agency

Project Team City of Rancho Palos Verdes:

• Michael Throne, PWD

• Ron Dragoo, Principal Engineer

Harris & Associates:

• Randall Berry, PM

• Liz Reyes, Deputy PM

KOA Corporation:

• Alan Braatvedt, City’s PM/CM

• Mike Jenkins, City’s CM

Ninyo & Moore:

• Jim Barton & Daniel Chu,

Geotechnical Engineering

L. H. Woods:

• Michael Ireland, Prime

Contractor

Drill Tech:

• Derek McDonald,

Tunnels/tiebacks

SFC Consultants:

• Saundra Jacobs, Environ.

BGB Design Group:

• Art Guy, Landscape Architect

KDM Meridian:

• Richard Maher, Survey &

Movement Monitoring

THE END

Southern Chapter APWA 2014

“Project of the Year” Award

“Innovation” Category

National APWA 2015

Small City “Project of the Year” Award

“Disaster / Emergency Repair” Category

Questions

&

Answers

Randall G. Berry, PE

[email protected]