108
Internship Report On ‟APARTMENT BUILDING CONSTRUCTION” Submitted as a partial fulfillment of degree of Bachelor of Technology in Civil Engineering Of Mewar University, Chittorgarh July, 2017 SUBMITTED TO: SUBMITTED BY: Sir Avinesh Kumar Mr. P Hiska HOD (Civil Engineering) B.Tech.VIII-Semester Faculty of Mewar University (Civil Engineering) Chittorgarh (Raj.) Roll No.: 150103570001 Guided By: Er. K George Chief Engineer M/s Singh Construction Co. Dimapur : Nagaland

Apartment building construction project report

Embed Size (px)

Citation preview

Page 1: Apartment building construction project report

Internship Report

On

‟APARTMENT BUILDING CONSTRUCTION”

Submitted as a partial fulfillment of degree of

Bachelor of Technology in Civil Engineering

Of

Mewar University, Chittorgarh

July, 2017

SUBMITTED TO: SUBMITTED BY:

Sir Avinesh Kumar Mr. P Hiska

HOD (Civil Engineering) B.Tech.VIII-Semester

Faculty of Mewar University (Civil Engineering)

Chittorgarh (Raj.) Roll No.: 150103570001

Guided By:

Er. K George

Chief Engineer

M/s Singh Construction Co.

Dimapur : Nagaland

Page 2: Apartment building construction project report

i

DECLARATION

In accordance with the requirements for the degree of B.Tech. programme in Civil

Engineering, in Faculty of Engineering and Technology, I present this report entitled

―APARTMENT BUILDING CONSTRUCTION‖. This report is a record of

original work done by me under the guidance of my esteemed mentor Er. K. George

and my site supervisor Er. M P Shukla.

I declare that the work presented in the report is my own work except as

acknowledged in the text and footnotes, and that to my knowledge this material has

not been submitted either in whole or in part, for a degree at this University or at any

other such Institution for the award of any type of work.

Date Name

02/07/2017 P Hiska

APPROVED BY

Name of supervisor: Er. M P Shukla Name of mentor: Er. K. George

Signature: Signature:

Page 3: Apartment building construction project report

ii

CERTIFICATE

Page 4: Apartment building construction project report

iii

ACKNOWLEDGEMENT

First of all I would like to thank each and every family, friends and individuals who

participated and supported me in completion of my final internship report.

I am very thankful to M/S SINGH CONSTRUCTION CO. For giving me the

opportunity to undertake my six months internship training in their working area. It

was a very good learning experience for me to have worked at this area. I would like

to convey my heartiest thanks to site supervisor Er. M P Shukla and its entire staff

member.

I would also thank my mentor Er. K. George for his endless support at site and in his

office by consulting me how things are done in the site and how to write this report in

outstanding manner.

I would like to thank to all the faculties of civil engineering department, Mewar

University, who brought me to my present performance and shape me like this during

the last three successive years.

Before I finish I would like to give my deepest thanks to all workers from the

contractor and the consultant side starting from engineers to daily laborers. Also for

those who do not listed in the above but support me in different areas I would like to

thank all.

P. HISKA

Page 5: Apartment building construction project report

iv

ABSTRACT

This report provides a summary to my internship practice outcome which I gained

during my internship period stay in the site of construction. Actually, I was assigned

in the construction of residential building as well as where different types of civil

construction activities were going on. At the beginning they assigned me to work with

them as office engineer and participated in the preparation of takeoff sheet for the

completed villas, apartments and other infrastructures.

Thus, in the first chapter of this report, I have briefly described the hosting company‘s

background. In line with this, I have pointed out the main aim and the supplementary

tasks that are being executed by the project and some of the designs and

accomplishments of the project as well as the works that are being supervised and

their work flow hierarchy.

In the second part, I have discussed the overall internship experience including the

procedural work flow, the different sites I was assigned to, the tasks I have been

involved in and the challenges I faced in the sites as well as the corrective measures

that was taken.

The third chapter gives the detailed report of the residential apartment building that I

was working on during my internship period. The building was under construction

when I joined and was still under construction even after I left. My main assignment

was this building construction, so I focused more on this building construction during

my internship. This chapter consists of only those reports which I had executed,

experienced and learned in site and office.

The fourth chapter explains the main benefits of the internship class in terms of

different aspects and areas. It is obvious that the internship has a plus-point in terms

of improving skills and all round development. The advantages and gains of the

internship highlighted in brief.

The final and fifth chapter explains about the winding up and suggestions on the

project that our company runs. In the site we came across many things which were

appropriate and inappropriate to work in building construction. Thus, I comment and

gave my recommendation in some conditions and workings.

Page 6: Apartment building construction project report

v

CONTENTS

CERTIFICATE

ACKNOWLEDGEMENT ......................................................................

ABSTRACT

COMPANY PROFILE ............................................................................. 1

CHAPTER 1 .............................................................................................. 2

1. BACKGROUND OF THE HOSTING COMPANY ........................................ 2

1.1 Introduction ................................................................................................... 2

1.2 Vision ............................................................................................................ 3

1.3 Mission .......................................................................................................... 3

1.4 Main objectives ............................................................................................. 3

1.5 Quality assurance .......................................................................................... 5

1.6 Fields of specialization .................................................................................. 5

1.7 Services rendering ......................................................................................... 5

1.8 Founder of the Company ............................................................................... 6

1.9 Company Address ......................................................................................... 7

1.10 Company structure ........................................................................................ 7

1.11 Organization And Management .................................................................... 7

1.12 Reference projects and services rendered by the Company .......................... 8

1.13 Company‘s machineries‘, vehicles and equipment ....................................... 8

1.14 Organizational structure .............................................................................. 10

CHAPTER 2 ............................................................................................ 12

2. OVER ALL INTERNSHIP EXPERIENCE ................................................... 12

2.1 Introduction ................................................................................................. 12

2.2 Joining the Company ................................................................................... 12

2.3 Short summary of the project ...................................................................... 13

2.4 Section of the company I was assigned to work in ..................................... 14

2.5 The work flow in the section ....................................................................... 15

DECLARATION ...................................................................................... i

....................................................................................... ii

iii

.............................................................................................. iv

Page 7: Apartment building construction project report

vi

2.6 Work piece or task I was executing ............................................................. 18

2.6.1 Office Work ......................................................................................... 18

2.6.2 Site work .............................................................................................. 23

2.6.2.1 Earthwork and Excavation ........................................................... 24

2.6.2.1.1 Setting Out.............................................................................. 24

2.6.2.1.2 Excavation .............................................................................. 24

2.6.2.2 Foundation work .......................................................................... 27

2.6.2.2.1 Isolated Footing ...................................................................... 27

2.6.2.2.2 Combined Footing .................................................................. 27

2.6.2.3 Masonry Work ............................................................................. 29

2.6.2.4 Concrete Form Work ................................................................... 29

2.6.2.5 Concrete Mixing Method ............................................................. 33

2.6.2.5.1 Hand Mixing .......................................................................... 36

2.6.2.5.2 Machine Mixing ..................................................................... 36

2.6.2.6 Batching ....................................................................................... 37

2.6.2.7 Curing of Concrete ....................................................................... 40

2.6.2.8 Structural Work ............................................................................ 42

2.6.2.8.1 Grade Beam or Plinth Beam................................................... 42

2.6.2.8.2 Reinforcement Steel Bar ........................................................ 43

2.6.2.8.3 Slab ......................................................................................... 44

2.6.2.8.4 Splicing of Bars ...................................................................... 44

2.6.2.8.5 Superstructure Beam .............................................................. 45

2.6.2.8.6 Column ................................................................................... 45

2.6.2.9 Finishing Work ............................................................................ 45

2.6.2.9.1 Plastering Work ...................................................................... 45

2.6.2.9.2 Ceiling and Wall Finishing .................................................... 46

2.6.2.9.3 Floor Finishing ....................................................................... 47

2.7 Procedure I used when I perform work tasks .............................................. 49

2.8 My Performance during Executing the Work Tasks ................................... 50

2.9 Challenges that I faced ................................................................................ 50

2.10 Measures I Took For Challenges ................................................................. 52

CHAPTER 3 ............................................................................................ 55

Page 8: Apartment building construction project report

vii

3. DETAILED PROJECT REPORT OF PLANNING AND DESIGN OF FIVE

STOREYED APARTMENT BUILDING ............................................................ 55

3.1 Introduction ................................................................................................. 55

3.2 Plan and drawing of building (Ground Floor) ............................................. 56

3.3 Plan and drawings of first to top floor ......................................................... 57

3.4 Details of beams .......................................................................................... 58

3.5 Details of Elevator (Lift) ............................................................................. 61

3.6 Details of Footing and Columns Reinforcement ......................................... 64

3.7 Foundation Layout Plan .............................................................................. 65

3.8 Estimation and Costing ............................................................................... 66

3.8.1 Methods of taking out estimates .......................................................... 66

3.8.2 Detailed Estimation and Costing of my assigned Building. ................ 66

3.8.2.1 General Abstract of Cost .............................................................. 67

3.8.2.2 Quantity Estimate for Ground Floor ............................................ 68

3.8.2.3 Quantity Estimate for First Floor to Fourth Floor ....................... 73

3.8.2.4 Abstract of Estimated Cost for Ground Floor .............................. 76

3.8.2.5 Abstract of Estimated Cost for First Floor to Fourth Floor ......... 78

CHAPTER 4 ............................................................................................ 80

4. OVERALL BENEFITS GAINED FROM INTERNSHIP ............................. 80

4.1 Overall benefits gained ................................................................................ 80

4.1.1 Improving practical skills .................................................................... 81

4.1.2 Upgrading the theoretical knowledge .................................................. 82

4.1.3 Upgrading personal communication skill ............................................ 83

4.1.4 Improving team work skill ................................................................... 84

4.1.5 Improving leadership skill ................................................................... 84

4.1.6 Understanding work ethics .................................................................. 85

4.1.7 Entrepreneur skill ................................................................................. 87

CHAPTER 5 ............................................................................................ 89

5. CONCLUSION AND RECOMMENDATION .............................................. 89

5.1 Conclusion ................................................................................................... 89

5.2 Recommendations ....................................................................................... 91

5.2.1 Recommendation to the hosting company ........................................... 91

Page 9: Apartment building construction project report

viii

5.2.2 Recommendation to the University ..................................................... 94

REFERENCE .......................................................................................... 95

APPENDIX .............................................................................................. 96

Page 10: Apartment building construction project report

ix

LIST OF TABLES

Table 1.1: List of Equipment, Vehicles & Machineries‘ of the Company ................... 9

Table 1.2 : List of Staffs .............................................................................................. 11

Table 2.1 : Format of takeoff sheet we used in the site. ............................................. 19

Table 2.2 : The format of bar schedule working paper we used at the site. ............... 20

Table 2.3 : The format of bill of quantity we used at the site. ..................................... 21

Table 2.4 : Formwork removal period at the site. ........................................................ 30

Table 2.5 : Admixture Used in the Site........................................................................ 36

Table 2.6 : Box Dimension Ratio. ............................................................................... 38

Table 2.7 : List of non-technical terms used in Site. ................................................... 52

Table 3.1 : General Abstract of Cost. .......................................................................... 67

Table 3.2 : Quantity Estimate for Ground Floor. ......................................................... 68

Table 3.3 : Quantity Estimate for First Floor to Fourth Floor. .................................... 73

Table 3.4 : Abstract of Estimated Cost for Ground Floor............................................ 76

Table 3.5 : Abstract of Estimated Cost for First Floor to Fourth Floor. ...................... 78

Page 11: Apartment building construction project report

x

LIST OF FIGURES

Figure 1.1 Company Organization Flow Chart.............................................................. 7

Figure 1.2: Company's Excavator & Grader ................................................................ 10

Figure 1.3 Company's Dumper & Roller ..................................................................... 10

Figure 2.1 : Building construction in progress (Ground Floor). .................................. 14

Figure 2.2 : The work flow in the section. ................................................................... 15

Figure 2.3 : Pit and Trench Excavation and masonry work. ........................................ 25

Figure 2.4 : Isolated Footings (Photo taken from Chishi building construction site in

Dimapur) ...................................................................................................................... 28

Figure 2.5 : Combined Footing (Photo taken from New Market building site Visit in

Dimapur) ...................................................................................................................... 28

Figure 2.6 : Masonry work at construction site in Niesato Colony (my assigned

building). ...................................................................................................................... 28

Figure 2.7 Formwork and Falsework (taken from New Market Construction Site Visit

in Dimapur). ................................................................................................................. 31

Figure 2.8 : Formwork to Footing Pads (Photo taken from New Market Construction

Site Visit in Dimapur) .................................................................................................. 32

Figure 2.9 : Formwork to Foundation Column (Photo taken from New Market

Construction Site Visit in Dimapur). ........................................................................... 32

Figure 2.10 Formwork to Elevation Column (taken from New Market Construction

Site Visit). .................................................................................................................... 32

Figure 2.11 : Tilt Drum Mixer Used in Site................................................................. 37

Figure 2.12 : Batching Box Used in Site. .................................................................... 37

Figure 2.13 : Curing by Wet Covering (taken from my assigned building site). ........ 42

Figure 2.14 : structural grade beam construction (taken from site visit) ..................... 42

Figure 2.15 : Rebar at Plinth Level at Ground Floor for Parking (taken from assigned

building at Niesato Colony) ......................................................................................... 43

Figure 2.16 : Reinforcement steel bar for beam (taken from New Market Construction

Site Visit in Dimapur). ................................................................................................. 43

Figure 2.17 : Bar Overlapping (Splicing). ................................................................... 44

Figure 2.18 : Ceiling and Wall Finishing (taken from DDSC Stadium Repairing Work

Site in Dimapur). .......................................................................................................... 47

Page 12: Apartment building construction project report

xi

Figure 2.19 : Marble Chips/Tiles (taken from DDSC Stadium Repairing Site in

Dimapur). ..................................................................................................................... 47

Figure 3.1 : Ground Floor Plan (photocopy of original building plan). ...................... 56

Figure 3.2 : Typical Floor Plan (photocopy of original building plan). ...................... 57

Figure 3.3 : Roof Beam Layout (photocopy of original building plan). ...................... 58

Figure 3.4 : Roof Beams Reinforcement Details (Photocopy of Original Building

Plan). ............................................................................................................................ 59

Figure 3.5 : Lift Elevation Detail (photocopy of Original building Plan). .................. 62

Figure 3.6 : Section of RCC Wall detailing Plan (photocopy of Original Building

Plan). ............................................................................................................................ 63

Figure 3.7 : Sections of Column Reinforcement and Footing (Photocopy of Original

Building Plan). ............................................................................................................. 64

Figure 3.8 : Foundation Layout Plan (Photocopy of Original Building Plan). ............ 65

Page 13: Apartment building construction project report

1

COMPANY PROFILE

M/S SINGH CONSTRUCTION CO. is a multi-disciplinary Construction cum

Consulting firm, a reputation for responsive, innovative yet practical design

approaches to complex Architectural & Engineering problems. Through their

experience and dedication to the construction industry M/s Singh Construction Co.

construction cum consulting firm is committed to provide with the most professional,

efficient and cost effective consultancy services. The goal of the company is to satisfy

the most demanding construction needs in Nagaland or elsewhere in the North-East

India.

Registered in the year 1981 (Registration No.- NPW/Class-I/48), M/s Singh

Construction Co., is an architectural & engineering partnership providing design,

supervision, consultancy and project management services and engineering solution

for various categories of projects. With core staff strength of all professionals in

affiliated engineering firms, and the use of the most recent information technology in

the production of contract information, the firm has over the years acquired a

thorough capability to execute medium to large scale project from feasibility through

design and contract administration to completion and project administration.

The company employs well-experienced engineers and professional, since its

inception, the primary motto of the company has been to complete its projects in time,

deliver quality products and services. The company‘s commitment to quality, cost

control and client satisfaction will be the cornerstone for its uninterrupted growth into

a reputed construction firm in a short period of time.

M/s Singh Construction Co. is a dynamic organization of innovative professionals

who share a common goal to render the best and most effective services to the

demanding construction industry, which is sensitive to both cost containment and

service levels.

M/s Singh Construction Co. is a private limited company registered and licensed

under the existing authorizing institute to conduct a wide spectrum of works in the

field of construction. Its main/head office is located in Dimapur with different

construction and projects at various regions in Nagaland.

Page 14: Apartment building construction project report

2

CHAPTER 1

1. BACKGROUND OF THE HOSTING COMPANY

1.1 Introduction

M/S SINGH CONSTRUCTION CO. is a multi-disciplinary Construction cum

Consulting firm, a reputation for responsive, innovative yet practical design

approaches to complex Architectural & Engineering problems. Through their

experience and dedication to the construction industry M/s Singh Construction Co.

construction cum consulting firm is committed to provide with the most professional,

efficient and cost effective consultancy services. The goal of the company is to satisfy

the most demanding construction needs in Nagaland or elsewhere in the North-East

India.

Registered in the year 1981 (Registration No.- NPW/Class-I/48), M/s Singh

Construction Co., is an architectural & engineering partnership providing design,

supervision, consultancy and project management services and engineering solution

for various categories of projects. With core staff strength of all professionals in

affiliated engineering firms, and the use of the most recent information technology in

the production of contract information, the firm has over the years acquired a

thorough capability to execute medium to large scale project from feasibility through

design and contract administration to completion and project administration.

The company employs well-experienced engineers and professional, since its

inception, the primary motto of the company has been to complete its projects in time,

deliver quality products and services. The company‘s commitment to quality, cost

control and client satisfaction will be the cornerstone for its uninterrupted growth into

a reputed construction firm in a short period of time.

M/s Singh Construction Co. is a dynamic organization of innovative professionals

who share a common goal to render the best and most effective services to the

demanding construction industry, which is sensitive to both cost containment and

service levels.

M/s Singh Construction Co. is a private limited company registered and licensed

under the existing authorizing institute to conduct a wide spectrum of works in the

Page 15: Apartment building construction project report

3

field of construction. Its main/head office is located in Dimapur with different

construction and projects at various regions in Nagaland.

1.2 Vision

To be the premier choice for all construction works in Nagaland and competitive

factor undertaking all types of construction work nationally.

Their vision to the future is becoming one of the leading Architectural & Engineering

constructions cum consultants in Nagaland.

1.3 Mission

Guided by their vision, they shall provide quality services exceeding client‗s

expectations while adhering to the highest standards of technical and individual

excellence through continuous improvement training and innovation.

Adding value to clients.

Nurturing and promoting talents.

Respecting employees‘ intense efforts and contribution.

To play a significant role in the construction sector.

To Increase its organizational strength by recruiting professionals, who will

have at their clearance.

Advanced, state of the art machineries.

Take an active participation in the nation‘s economic development thus

ensuring maximum customer satisfaction.

1.4 Main objectives

Unparalleled customer satisfaction and a spirit of challenge as well as change are core

components of the company.

The company core objectives are:

(i) Clients service. They add value to client‗s project through innovative solutions.

Consistency and knowledge in dealing with clients has contributed to fulfillment and

corporate success.

(ii) Excellence. They are resilient and persistent in talking on challenging goal and

setting higher performance benchmarks that helps them to excel in every way that is

meaningful to clients, employees and vendors.

Page 16: Apartment building construction project report

4

(iii) Quality. They are driven to attend to client‗s concern responsively towards

delivering commitments.

(iv) Employees. The company pursues business opportunities that will enable them to

be competitive by empowering employees to take on initiative and at the same time

promote ownership of responsibilities and accountabilities to results and performance.

Besides the above mentioned core objectives, the company has the following

objectives:

Ensuring 95% of the projects executed by the company are accomplished

within the contract time.

To play active developmental role in the construction sector.

Undertaking gravel and asphalt road projects by maximizing its capacity.

Construction of multi-purpose apartment buildings and residential houses.

Construction of rail-ways.

Constructions of hotel buildings and becoming direct stake holder in

hospitality industry.

Establishing joint-venture investment projects with various international

companies with emphasis on construction related areas.

Investing in various business activities-service trade, rental buildings, rental

helicopter Services, agricultural sector etc…

To establish baseline data for construction services and delivery related

customer complaints and reduce the complaints by 80%.

To assess our customer satisfaction level once per year to ensure continual

improvement of the service and delivery performances build the capacity of

their employees through training two times per year and at demand on quality

and environmental management and on other training identified according to

competence check list.

To conduct internal audit and management review twice per year and at

demand.

To develop suppliers to get the right materials, at the right time from right

source.

Attaining high levels of professional and technical efficiency while keeping

pace with the ever-evolving technical advances in the industry

Page 17: Apartment building construction project report

5

1.5 Quality assurance

Quality Policy

They are committed to become a leading Architectural and Engineering consultant in

the country by providing value added services in a quality conscious environment that

not only exceeds the expectation of customers, vendors‗ employees and shareholders,

but also raises the standards of excellence in industry. We are committed to achieve

our goal by continually improving people, processes and products.

Quality Objectives

To win major projects and attain premier in the industry.

To successfully execute projects undertaken.

Continues development of competence & skill based on K2N human

resources.

1.6 Fields of specialization

M/s Singh Construction Company is specialized in Architectural, Structural,

Electrical, Sanitary and Mechanical design and construction management of

commercial, residential, industrial, educational, military, sport facilities, hotel and

office buildings as well as earth and rock fill dam, concrete dams, tunnels, water and

distribution, drainage, waste water solid waste disposal, motor ways, and high ways,

air field, terminals and so on.

1.7 Services rendering

M/s. Singh Construction Company has a solid reputation for completing projects in

time, within budget and with a high standard quality. It has attracted the attention of

so many governmental institutions and private companies for its high quality

construction work and performances in road, bridge and building construction line. It

is currently executing major infrastructure projects at various parts of the state

(Nagaland).

The company owns qualified experience of any type of construction projects of:-

(i) Road construction

Urban and compound roads

Page 18: Apartment building construction project report

6

Highways

Rural and feeder roads

(ii) Bridge construction

Construction of all kinds of bridges and highway bridges

(iii) Airport

(iv) Residential and non-residential buildings

(v) Other related fields with determinate skills to perform in such a professional way

to deliver its service to the satisfaction of their customers to enable them to achieve

their goal.

The company has a vital commitment in becoming a prominent contractor having

confident in its vital experience of the different disciplines of construction to deliver

its service in a much of professional way and full necessity of the dominant

customers.

They are involved in the construction of civil engineering projects of any types, such

as:

High rise condominium, building construction works

Water supply and other related construction works

Major and minor bridge works

Culvert works

Air filed construction works asphalt and/or gravel pavements

Major road work asphalt and/or gravel pavements.

1.8 Founder of the Company

M/S Singh Construction Co. is a private company and was founded and owned by

three persons on partnership. The names of these three persons are:

1. Sarabjit Singh Panesar

2. Jaspreet Kaur Panesar and

3. Taranjit Singh Panesar.

Page 19: Apartment building construction project report

7

1.9 Company Address

The company currently maintains its office in Dimapur, Nagaland. The complete

profile as follows:

M/s Singh Construction Co.

Nepali Basti, Circular Road

District: Dimapur

Pin Code: 797112

State: Nagaland

Tel. No.: 03862-248871

E-Mail: [email protected]

1.10 Company structure

Figure 1.1 Company Organization Flow Chart

1.11 Organization And Management

In every organization, the most important asset is the people that play essential role in

the performance of the company‘s functions and responsibilities. Thus, M/s. Singh

Page 20: Apartment building construction project report

8

Construction Co. is fortunate to have highly qualified and experienced personnel.

Reciprocally, the company has aimed to provide its employees all the basic

necessities while performing their assigned tasks and at the same time equipped them

through training and seminars to enhance their capabilities. The company as

organization and the employees, because of the mutual benefits that simultaneously

being enjoyed by, has grown tremendously and has blazed a track record of fulfilling

its obligation and commitment both the customers and the community. They would

like to be on the level where they should be. Having confidence in the organization,

they aim high. The teamwork that has been developed through the years of hard work

has reaped a harvest of opportunities and wealth. They will continue to improve and

develop new concepts both in management and technology.

The firm is capable of furnishing well coordinating Architectural and civil

engineering design services by utilizing its in-house staff as well as its professional

associates. All engineering services carry the quality control assurance and guarantee

of the company‘s firm.

The company carried out any project by forming a dedicated project team. Each team

is headed by a senior design engineer and draftsmen enough to complete the project in

schedule. Design teams are dynamically managed to accommodate necessary and

fluctuating workload and tights schedules. Flexible teaming capability enable the

company to undertake large and small project with the lowest overhead costs thus

providing the best value to the client.

1.12 Reference projects and services rendered by the Company

Following are the descriptions of some of the major projects handled and constructed

by the company:

1.13 Company’s machineries’, vehicles and equipment

M/s Singh Construction Co. has given due consideration to all aspects which pertain

to the realization of high standard in all directions and that ensure the company's

competence and reliability. In this regard, the company has equipped itself with

modern and heavy duty machinery and equipment in sufficient quantity along with the

establishment of a full-fledged service workshop, and as per the regulations of the

Ministry of Works and Urban Development.

Page 21: Apartment building construction project report

9

The following table shows the quantity of some machineries, vehicles and equipment

of M/s Singh Construction Co.:

Table 1.1: List of Equipment, Vehicles & Machineries’ of the Company

Type of Equipment, Vehicles & Machineries’ Quantity

Dozers 3

Loaders 2

Excavators 2

Graders 2

Compactors (Rollers) 4

Mobile Crane 4

Tower Crane 1

Trucks 7

Mini & Long Bus 2

Truck Crane 2

Single & Double Cabin Pick-Up 3

Crusher 2

Mixer 30

Tamper 10 tonnes 6

Water Pump 12

Vibrator 16

Grinder 12

Generator Set 4

Jack Hammer 2

Drill & Cutter 32

Tool Set 22

Forklift 9

Dumper 2

Scaffolding and Formwork 4+150m2

Page 22: Apartment building construction project report

10

The following figures show some of the machinery and equipment of M/s. Singh

Construction Co.

Figure 1.2: Company's Excavator & Grader

Figure 1.3 Company's Dumper & Roller

1.14 Organizational structure

M/s Singh Construction Co. is a well-structured and adequately staffed organization

capable of handling a number of projects at a time. The company uses the combined

knowledge and experience of personnel, from directors to skilled workers, for

consistent quality project delivery. The qualified, well-trained and committed

workforce also enables it to uphold project schedules, even under adverse

circumstances. All the achievements of the company have been made possible by the

dedicated efforts of executives and qualified personnel.

Employees at Company are working towards continuing success with the help of a

committed leadership and highly motivated workforce by enduring close relationships

with clients and alliance partners. The Company is highly increasing its manpower in

all levels of responsibility and professional practice pertaining to construction work.

Page 23: Apartment building construction project report

11

This has created a relaxed and easy handling of a number of significant projects at a

time.

Besides working with freelance professionals and experts in various areas of

engineering disciplines, The Company has over 71 permanent staff with a core of 15

qualified professional civil engineers, mechanical engineers, professional surveyors

and other various disciplines. These teams are supported by a comprehensive array of

managerial, business, financial and administrative staff. Their expertise enables the

firm to offer clients a scope of services tailored to the operating requirements of

different regions, different cultures and environmental condition.

Some professional staff members with their level of education and their number is

indicated on the following table:

Table 1.2 : List of Staffs

Sl. No. Professional Staffs Qualification Total No.

1. Engineers Civil Eng., B.Sc.,

M.Sc., Degree

15

2. Surveyor Technical diploma 6

3. Construction

Superintendent

Certificate 6

4. Foreman Certificate 6

5. Material Inspector Certificate 5

6. Non-technical staff Diploma/Certificate 5

7. Operators Licensed 40

Page 24: Apartment building construction project report

12

CHAPTER 2

2. OVER ALL INTERNSHIP EXPERIENCE

2.1 Introduction

The main aim of higher educational institutions, especially technology institutions, is

producing knowledgeable, well performed, country builder, productive and talented

students. Those students, after graduation, will be working in different companies,

organizations and other working sectors all over the country. Almost all practical

engineering applications are done based on the theories and principles of different

engineering fields that have been developed progressively.

Civil engineering practical applications, i.e., design, construction and supervision

have laid down their foundation on those theories and principles of the civil

engineering studying fields. In turn those principles and theories are the backbone for

different studying fields in higher technology institutions, like Mewar University. The

most interesting part of civil engineering study is that of its theories and principles are

almost applicable in all civil engineering design, construction and super vision works.

As under graduate student, I have grasp the basic principles and theories of civil

engineering design and construction work in my last three years of studying in this

university, civil engineering department. But this theoretical knowledge is not enough

to being a qualified civil engineer at the time of graduation. Knowing the practical

work and the real situation besides the theoretical knowledge in time of studying

makes one experienced in practical and theoretical knowledge at the time of

graduation. This is why the university needs its students to have an internship

program before graduation. For that matter I was really interested with my internship

program.

2.2 Joining the Company

The University, Mewar University, has relationships and tie-ups with different

companies and organizations through the University‘s Training & Placement

Department. The university‘s Training & Placement department has different

purposes and uses in introducing the university and its student for the external world.

Page 25: Apartment building construction project report

13

The university‘s Training & Placement department presented two choices to opt any

one for every intern students.

1. Working internship program in a company which has been searched and

founded by the university‘s Training & Placement department.

2. Searching internship place by the intern student himself anywhere which

are comfortable and advantageous.

I was the intern student of the second option. Starting from July 2016 I was searching

a construction company by myself. I was also comparing different construction

companies and projects. Finally I decide to take my internship program in M/s Singh

Construction Co. in my home town, Dimapur. On contacting the company‘s HR

Manager, he agreed and allowed me to undertake my six months internship course in

their company. On 2nd

January 2017 I joined the company and I was blessed to have a

very experienced and knowledgeable mentor and a very friendly and experienced site

engineer to guide and assist me in every field of my training program right from

office works to site works. During my internship I was initially working in office

learning paper works after that I was working in site where a Residential Apartment

Building construction was in progress.

2.3 Short summary of the project

Among many projects of the Company as mentioned in the Company‘s Profile. Thus

from those listed I have been working in the Residential Apartment Building

Construction project at Niesato Colony, Dimapur, Nagaland.

Project title: M/s Singh Apartment Construction TA2016.

Project location: Niesato Colony, Dimapur.

Client: Temjen Ao.

Contractor: M/s Singh Construction Co.

Consultant: Environ Assemblers.

Cost of project: ₹ 1,23,29,230.00 (estimated).

The objective of the project is to build G+4 (five storeyed) residential apartment

building which gives high quality services.

Page 26: Apartment building construction project report

14

Figure 2.1 : Building construction in progress (Ground Floor).

2.4 Section of the company I was assigned to work in

Upon my arrival at the site I was assigned to observe and carry out tasks that were the

responsibility of an office engineer from the contractor side. I must admit the tasks I

was handed at first were somewhat not related to the responsibility of the site engineer

for they were drawing floor plan and reinforcement bars for slab. But as time went by

I started to carryout office and site engineer tasks.

My hosting company has many projects in our country as I mentioned in the company

profile. Thus from those listed I have been working in the M/s Singh Apartment

Construction TA2016 construction project. The project is to erect and construct a

mega G+4 floors building. The ground floor plan area is 8535 square feet where

around 45% of plan area is allotted for parking. The building being an apartment

building, it is designed likewise where every flat has 2BHK (two bedrooms, one hall

and one kitchen). The building being a residential building all the floors (G+1, G+2,

G+3, G+4) is designed the same with same room dimensions, specifications having

2BHK for each flat. But when I was arrived at the site the footing, foundation, and

column for the ground floor were already constructed

Page 27: Apartment building construction project report

15

On the site as per the contract different offices are provided (temporary office

buildings) in each offices varies activities carried out. Such as Consultants office,

Project manager‘s office, Administration, Finance, Office Engineer‘s, Site Engineer,

Forman‘s, Store, Guard‘s house and Surveying office.

2.5 The work flow in the section

The working flow of the consultant and the contractor has many advantages in order

to work every task closely and to solve problems arise between them. In every work

there is a work flow whatever small is the section, my working site at Niesato Colony

project the work flow was look like the chart below.

As shown in the chart every work was executed based on this flow.

Figure 2.2 : The work flow in the section.

1. Design and Supervisor team: The team includes structural engineer, architectural

engineers, sanitary engineers, electrical engineers and other experienced engineers in

other professions. The design and supervision team is a team from the consultant side

which guide every work executed in that site and gives supervision for the contractor

based on the drawing and the specification (bill of quantity).

This team mostly comes to the site when there is amiss or some miss understanding

on drawings, working techniques, drawing detailing error, and for meeting between

the three parties. The team provides continuous service to the project from start to

finish, establishing and maintaining the quality and integrity of each design.

Page 28: Apartment building construction project report

16

2. Resident Engineer: Position is responsible for multiple construction projects or a

single project of a large scale requiring multiple disciplines. This includes reviewing

design; supervising construction progress and scheduling; starting up process

systems/equipment or facilities for turning over to the owner's personnel. Supervise

field staff and contractors on the site with responsibility for quality construction in

accordance with plans and specifications. He/she also responsible for approval of

change orders, invoices, and payment applications which may include final payment.

So, the resident engineer mostly control every work as much as possible in terms of

their quality, cost and time. Testing of materials delivered at site and safety of

workers starting from managers to daily labors also the duty of the resident engineer.

3. Project Engineer: The project manager has so many responsibilities at the site and

in our site these positions is accountable for the contractor or the owner and are

appointed by the owner of the construction company. The main duty of the manager

is; manages the whole site work execution, Makes payment to sub contract workers,

Approves material request, Analyses the work processes, Executes sub-contracting

agreements, Reviews and checks the reports made by the office engineer.

4. Site Engineer: Site engineer shall be accountable for the following tasks and

responsibilities:

Studying the work plan submitted by the contactor and suggests any

modifications.

To watch and inspect the construction work and assure that it is done in full

accordance with the drawings, technical specifications and bills of quantities.

Supervising the works on site in accordance with the contract documents

and using the template and procedure established by the consultant.

Inspecting and testing materials prior to their use at site as per sample

approved by the consultant and ensuring removal of rejected material out from site.

Ensuring the correct implementation of the works according to technical

specifications, to designs and quality of materials

Checking of layout and setting out of buildings with respect to existing

structures and site levels.

Page 29: Apartment building construction project report

17

Checking and testing of completed works before they are covered by the

contractor, taking photos on a regular basis and also on account of defective work.

Ensuring that health and safety measures are adopted and followed to the

full extent.

prepare weekly report and suggest and instruct additional safety measures if

needed

Maintain a filing system for all site memos and instructions, measured

quantities of work and materials on site, reports and other documents and

correspondence pertaining to the construction activities and

Maintain a site order book to be made available for the consultants and

senior officers to write comments or defects in construction noticed during site visits

and carrying out compliance at site.

5. Foreman: A foreman is the worker or tradesman who is in charge of a construction

crew and is a skilled supervisor who is responsible to work side by side with the

project manager, property owner, and other construction design engineers in order to

complete a project in a given time limit. His job is to employ the suitable workers on

the various tasks to complete the job, and supervise all phases of the construction

project from start to end or supervise only a portion of the building process Normally

the foreman is a construction worker with many years of experience in a particular

trade who is charged with organizing the overall construction of a particular project.

Typically the foreman is a person with specialist knowledge of a given trade who has

moved into the position and is now focused on an overall management of all trades

rather than any particular specialized group.

A good foreman is the keystone of their projects since they control every work more

closely than the others like project manager, site engineer etc. the Forman also have a

duty of motivating workers and choosing good workers for every aspects of work.

6. Surveyor: In any construction a surveyor is mandatory so, in our site the surveyor

works starting from setting out to checking verticality, keeping the natural level of the

building, checking elevation of columns.

Page 30: Apartment building construction project report

18

7. Skilled and Unskilled Workers: This group includes masons, carpenter, bar

benders and the daily laborers. In our country workers of such group are appointed

only by experience these have its own advantage on the constriction. They work

everything as they ordered by withier the Forman or the site engineer.

8. Store keeper: store the sites equipment, construction materials and controls the

number of materials that came in and out of the store.

So, among these sections, I worked in different sections both in the site and in the

office of my hosting company.

2.6 Work piece or task I was executing

Actually I assigned from the university to work with consultants but consultation is

not easy task to perform especially for students because it needs experienced and

further specialized person in the field and most of the work is not parallel with civil

engineering it has different field within it. So, to know every work what civil

engineers do I try to work and share experience with company‘s Engineers‘ in

addition to consultant. And also the consultant main work at the site is controlling

time, cost, quality and safety of workers so those work needs inspection, test

conducting and taking different measures when the contractor don‗t execute it

properly. Their main work is to advice and provides abettor idea how the project will

finish with a minimum cost, time and quality.

Generally I have been working in the two sections as mentioned above. I classify the

works into office work and site work. Mostly the work I executed on the site was

supervising, working as a site engineer, surveyor and Foreman.

2.6.1 Office Work

In my six months internship period I experience Office works that are worked mostly

at the site this includes some tasks performed by office engineer and quantity

surveyor. Such as:

1. Taking off

2. Bill of quantity

3. Report writing

4. Reading and interpreting drawings

1. Taking off: This is the process of preparing / defining a detailed list of all labor

and materials necessary for the work and entering the items on properly dimensioned

Page 31: Apartment building construction project report

19

paper. The standard form used for entering the dimensions taken or scaled from

drawings to determine the accurate quantity in each trade of work, except

reinforcement steel, is called take off sheet or dimension paper. The main aim of

this sheet is for payment and cost estimation for purchasing and preparing bill of

quantity. The dimension paper used for taking off is double – ruled A4 size paper as

shown below:

Table 2.1 : Format of takeoff sheet we used in the site.

Take Off Sheet

Project:_______ Block type:___________

Client: ________

Consultant:________ Location:____________

Contractor:____________

1 2 3 4 1 2 3 4

Column 1 is used for stating the number of times an item occurs and is called the time

stating column.

Column 2 is called dimension column as it is used to enter the dimensions of the items

of works. The dimensions are entered in the order indicated below:

Length, Width, Height or thickness.

Column 3 is called squaring column. The stated dimensions in column 2 are

multiplied to determine the quantity of the work either in m, m2, m

3 or in Pcs. or No.

Whereas column 4 is called description column and description of the work item is

briefly stated. Based on the above format I have calculated the quantity of concrete in

Page 32: Apartment building construction project report

20

m2 and in m

3, formwork in m

2 and excavation in m

2. We were to use m

3 for depth

greater than 30 cm and if it is less than we use m2.

A separate sheet (Bar Schedule) is used to prepare reinforcement quantities as

shown below:

Bar schedule is used to know the amount of rebar used on the site and to tell the bar

bender that the amount of bar needed in some position of the building and its number.

The following tasks are part of the taking off (used to facilitate defining the

quantities): Describing the item, bracketing (relating the description to the quantity),

dotting on, the ampersand (ditto), waste calculations, deduction of items, correction

of dimensions (nullifying).

Table 2.2 : The format of bar schedule working paper we used at the site.

Sheet No._________

Bar Schedule Sheet

Project:________ Block Type:_______

Client:_________ Date:____________

Consultant:________ Location:_________

Contractor:________

_________ ____________ __________

Contractor Site Supervisor Consultant

Ite

m

Loca

tion

Dr

.

N

o.

Sha

pe

Diamet

er

Length

No.

Of

Bars

No.

Of

Floor

s

No.

of

Me

mb

ers

Leng

th

∑L for each

diameter

Total length

Weight in Kg/m

Total weight in Kg

2. Bill of Quantity: The traditional purpose of bills of quantities is to act as a uniform

basis for inviting competitive tenders, and to assist in valuing completed work. Bills

of quantity are first designed to meet the needs of estimators, although some

Page 33: Apartment building construction project report

21

estimators say the bill format has changed to assist the consultants, in cost planning

exercises through the widespread use of elemental bills.

A contractor can also make use of the bill of quantities in many ways, for example:

1. To plan material purchasing (note the danger in ordering from a bill: the contractor

should always order materials from drawn information and the specification, making

the contract administrator aware of any differences)

2. Preparing resourced programmes.

3. Cost control during the contract to ensure work is within budget.

4. Data collection during construction for bonus systems and feedback information

for estimators.

It is the format which is used in a bill of quantity to list (include) a short description of

the specification along with its measuring unit, quantity and unit prices to determine

the total Cost for each trade of item. In the site the bill of quantity is done by

consultant with the contract document but at site we work it again for payment.

Table 2.3 : The format of bill of quantity we used at the site.

Project_________

____________ ___________

Client Contractor

Item Description Unit Quantity Unit price

(Rate)

Amount

There are four clearly defined steps in preparation of Bill of Quantities:

Taking off

Squaring

Abstracting

Page 34: Apartment building construction project report

22

Writing the bill off quantity

Report Writing

Reporting is a controlling / informative mechanism which will help in evaluating the

status of a project. It entails us how we are accomplishing our set targets at the onset

of a project. It will also help decision makers to follow the status of the project

without being present physically on the site. The reports should explain the history of

the project. It should be realistic and self-explanatory. Numbers in a report are far

important than number crunching. Putting numbers for a report writer like 10% or

90% may be simple but the meaning for the decision makers is very vital. Putting

wrong figures knowingly or unknowingly are devastating.

Types of Report:

The types of reports to be submitted in a project depends on project type; complexity;

working habit etc.

In our project we work the following reports

Weekly report and

Monthly report

Weekly Progress Report: This is the lowest report form. (lowest means the level of

view of the project is high). In short - it evaluates the accomplishment of the weekly

plan and puts the next week schedule. This report will show the achievement/

drawbacks of the project at the broadest level and help the project manager ( PM) or

Resident Engineer (RE) to solve the shortcomings at the grass root level.

Major Contents of a Weekly Report: Project data ,Accomplishment of weekly Plan,

Weekly labor and Machinery Deployment, Material Delivered to the site, major

Problems of the week , Solutions given to the major problems, Anticipated problems

to be solved for the next week , next week plan and so on.

Monthly Progress Report: This is a report with a view of many eyes. This will be

thoroughly seen by second level observers. The contractor, the client and the

Consultant‗s representative will make an in depth view of the report to have full

information about the project status. This is a report where major bottle necks of the

project will be narrated and the performance of the parties will be vividly seen.

Major Contents of Monthly Progress Report: Accomplishment of monthly Plan,

Monthly labor and Machinery Deployment, Material Delivered to the site, major

Page 35: Apartment building construction project report

23

Problems of the month , Solutions given to the major problems, Anticipated problems

to be solved for the next month , next month plan, Contractual matters -Delay

Notifications (if any) ,variations ( if any) and so on.

Reading and Interpreting Drawings: Drawings are the means by which the designer

conveys the physical, quantitative, and visual description of the project to the

contractor. The drawings are a two-dimensional representation of the physical

structure that meets the objectives of the owner. They are also known as plans or

blueprints

In our site there were 4 types of drawing;

1. Architectural drawing

2. Structural drawing

3. Sanitary drawing

4. Electrical installation drawing

These drawings are the main language between the architect, designer and any worker

at the site or office to build the model in position as specified by the designer and the

client, based on the agreement. Thus, to work as an engineer in the construction site it

is mandatory knowing drawings and any other specification. Drawings are the most

common means of communication for all types and sizes of project. Thus, I

understand each drawing and knew every symbol abbreviation for every section and I

was able to communicate with different workers using it.

2.6.2 Site work

The site work was the very important task for me because the internship main

objective lies over here and I have gained so much of knowledge from the site like

communication skill, handling workers, management skill etc. within six months I

have the ability to see many works from the project.

The work tasks I executed at site were:

Supervising of works

Inspecting the worked element and how they work

Checking the work based on the given check list

Testing materials

The site work in general overlay over the supervision part so I have been working as

supervisor based on the given check list that our company give to us. Every work

must be checked weather it was executed based on the methodology that the

Page 36: Apartment building construction project report

24

contractor provides to the consultant or not. If not the contractor must report the case

why they didn‗t execute upon it.

2.6.2.1 Earthwork and Excavation

Before carrying out any work on any site the site will be inspected where necessary in

conjunction with the engineer. Before starting any work, the site will be surveyed in

cooperation with the engineer's representative to establish existing ground levels, and

these agreed ground levels shall form the basis for the calculation of quantities of any

subsequent excavation and filling.

2.6.2.1.1 Setting Out

Setting out is the process of laying down the excavation lines and center lines etc. on

the ground, before excavation is started. The setting out is done correctly with proper

measuring tape and accurate leveling instrument.

The steps in marking points can be summarized as follows;

Establish reference points;

Fix wooden pegs and batten boards around the site to be excavated.

Make the center line of the walls;

Mark the plinth lines;

By stretching strings, check right angles by forming triangles with sides

3, 4 and 5 units long or by measuring the diagonals;

If all dimensions are correct and all corners are right angel, the cutting

Lines are marked on the ground using limes.

I didn‘t saw this work but I tried to grasp some knowledge and ideas by asking the

engineers how it was worked and its main procedures.

2.6.2.1.2 Excavation

Excavation is the first step of construction. It refers to the process of removing soil or

rock from its original location, typically in preparation for constructing foundations,

basements, and underground utility lines and for grading of the ground surface.

Excavated material required for backfill or grading fill is stockpiled on the site for

subsequent use. Excavation work I have seen was including bulk excavation, pit

excavation and trench excavation. The main aim of the excavation work is to remove

organic soils or unwanted soil for the safety of the building from chemical attacking.

Excavation shall be carried out to the lines, levels, width, depth and grades and shown

Page 37: Apartment building construction project report

25

on the drawings, directed by the Engineer or as appropriate to the works to be placed

in the excavation.

Pit excavation: It is an excavation made for foundation footing pad with column by

considering working space of 200 up to 300mm to each side of the dimension.

Trench excavation: It is an excavation made for constructing foundation walls stone

masonry with leaving working area for both sides of the wall of specified width on the

plan.

This depth is filled by the stone masonry which placed on 5cm thick lean

concrete

Stone masonry should be laid with specified mortar, well filled joint

The stone should be hard, sound, free from crack and weathering

It should be freshly quarried from an approved quarry

It is not round surface

Figure 2.3 : Pit and Trench Excavation and masonry work.

Bulk excavation: It is an excavation made for making the ground level or an

excavation made for filling selected material. Or we can say that bulk excavation

means removing black cotton soil because as you know black cotton soil is very

expansive and it has a low bearing capacity therefore we must remove it from the site

and the area is back filled with selected materials.

Fill: Fill work will follow the erection of foundation column. Bulk, pit and trench

excavations need to be back filled with a better soil type, which will have better

Page 38: Apartment building construction project report

26

compaction character and would bring the minimum required proctor density. In order

to attain the minimum standard as mentioned on the Bill of Quantity, they deploy

appropriate machineries.

Niesato Colony area had shown that the natural excavated soil alone wouldn‗t attain

the compaction density based on the tested value. The soil should have to be blended

with a granular material like red ash. The excavated soil was deposited somewhere

close to the project site and it was blended there with the red ash to be borrowed from

outside. The blending process involves different machineries like loader, excavator,

and dump trucks. After blending, it was transported to the right place it has filled. The

dump trucks dump it within the site laid out, and then the loader spread it to the

required thickness, which is at every 20mm. Eight ton roller self-equipped with water

sprinkling device ram and vibrate it well. This was done to the bulk fill area. For the

pit the same blended fill was utilized, but the machines that compact was different

than the bulk fill area. Here the roller wouldn‗t apply rather it was performed by frog

compactors. Water was sprinkled by hose in order to increase the PI of the fill, so that

it was compacted to the required stage. The final levels of fill was adjusted, graded

and prepared to receive bedding to lay on fill.

Cart Away: This is the disposing off extra excavated material away from the

construction site. Cart away is calculated by deducting the back fill from the total

volume of soil excavated.

𝑉 = 𝑇. 𝑆 - 𝐵. 𝐹

𝑉 =(𝑇. 𝐸 + 𝑃. 𝐸 + 𝐵. 𝐸)- 𝐵. 𝐹

Where,

T.S =total soil,

B.F =back fill

T.E = soil obtained from trench excavation

P.E = soil excavated from pit excavation

B.E = Bulk Excavated soil

Page 39: Apartment building construction project report

27

N.B:-since cart away is measured by meter cube, all the other soil amounts are

changed to meter cube.

2.6.2.2 Foundation work

In my internship practice, I have practiced the two main shallow foundation types,

isolated footings and combined footings. A foundation is part of a structure which is

in direct contact with the ground to which the loads are transmitted. Since foundation

is constructed bellow the floor finished level, it is included as one part of the sub

structures of the building. Foundations are normally placed below the ground level.

The soil or rock surface on which a building rests is called the foundation bed.

Foundations have the following purposes:

To distribute the load of the structure over a large bearing area so as to bring

intensity of loading with the safe bearing capacity of the soil lying underneath.

To load the bearing surface at a uniform rate so as to prevent unequal

settlement.

To prevent the lateral movement of the supporting materials.

To secure a level and firm bed for building operation.

To increase the stability of the structure as a whole.

To ensure safety against undermining and protection against soil movements.

To provide even surface for the structure to rest etc.

2.6.2.2.1 Isolated Footing

Isolated footings are footings which carry a load from a single column. Reinforcement

is provided in the form of steel bars and is placed in both directions. Under normal

conditions, square & rectangular footings are economical for supporting columns &

wall. Figure is shown in figure 2.4.

2.6.2.2.2 Combined Footing

The following pictures show combined footing before concert cast and after cast:

A combined footing is usually used to support the columns of unequal loads. In such

case, the resultant of the applied loads would not coincide with the centroid of the

footings and consequently the soil pressure would not be uniform. Combined

foundation is an efficient foundation solution is when there are two interior columns

which are so close to each other that the two isolating footings stress zones in the soil

areas would overlap. Figure is shown in figure 2.5.

Page 40: Apartment building construction project report

28

Here at the bottom we can see the pictures that I took from site visits

.

Figure 2.4 : Isolated Footings (Photo taken from Chishi building construction site

in Dimapur)

Figure 2.5 : Combined Footing (Photo taken from New Market building site Visit

in Dimapur)

Figure 2.6 : Masonry work at construction site in Niesato Colony (my assigned

building).

Page 41: Apartment building construction project report

29

2.6.2.3 Masonry Work

Masonry are works that are executed by laying building material units such as stone,

brick and HCB of specified dimension by providing a binding material such as

mortar. I got the opportunity to see masonry work above the plinth beam of the

building. The masonry below the plinth beam was built of non-modular bricks and

above the plinth beam also the non-modular bricks were used. Stone used for masonry

work shall be hard and sound, free from vents, cracks, fishers, discoloration or other

defects that will adversely affect strength or appearance. After constructing masonry

wall, the plinth beam was constructed directly over it. It gives an appearance of

additional stability to the building and also the clearance from the ground level as

shown in figure 2.6.

Note that stone wall is measured by volume and the masonry wall over lied in a c-5

lean concrete.

2.6.2.4 Concrete Form Work

As fresh concrete is in plastic state when it is placed for construction purpose so, it

becomes necessary to provide some temporary structure to confine and support the

concrete till it gains sufficient strength for self-supporting. This temporary structure is

called form work. Concrete formwork serves as a mold to produce concrete elements

having a desired size and configuration. It is usually erected for this purpose and then

removed after the concrete has cured to a satisfactory strength. In some cases,

concrete forms may be left in place to become part of the permanent structure. For

satisfactory performance, formwork must be adequately strong and stiff to carry the

loads produced by the concrete, the workers placing and finishing the concrete, and

any equipment or materials supported by the forms.

In the site the form work material we use was plywood material which had a good

surface finish.

Plywood is used extensively for concrete forms and provides the following

advantages:

It is economical in large panels.

It is available in various thicknesses.

It creates smooth, finished surfaces on concrete.

Page 42: Apartment building construction project report

30

The general step used to construct a formwork in the site is:

Prepare the false works in the desired position and level.

Preparing the form work in a desired shape based on the drawing or the size of

the structure that is going to be cast.

Painting with a releasing agent if needed.

Nailing it with appropriate bracing element and false work.

The type of formwork that was utilized on our site was a combination of ply wood,

bamboo and timber (eucalyptus) where necessary. The purpose of employing ply

wood, bamboo and timber is to make sure that quality concrete with perfect alignment

would result. For horizontal structures like reinforced concrete slab the ply wood

without being cut was placed. At the same time for the beams they use plywood form

work for the soffit and timber or plywood for the sides. For vertical reinforced

concrete structures ply wood formwork with timber false work was used. As most of

the elevation columns assume uniform size, the ply wood was cut in size and was

produced in a manner it could be easily fixed and dismantled. The bracing was done

from timber and nailed perfectly to confine the fresh concrete. Reinforced concrete

slabs and beams formwork was supported and fixed on eucalyptus pops and props.

Dismantling of the formwork commenced after the allowable dates have elapsed since

the day of the concrete casting. Accordingly column and side formworks will be

dismantled after 16 hours elapsed from the concrete casting and other soffit

formworks should stay in position until the concrete gets cured. The dates of

dismantling for the soffit formworks were shortened by the use of fast curing concrete

admixtures. The use of these admixtures will allow them to move fast forward with

the construction and immediate utilization of the formwork on other successive

structures.

Table 2.4 : Formwork removal period at the site.

Vertical column, walls and beams 24 hour

Soffit work to slab and beam 24 to 28 Days

Props to slab and beam 14 Days

Page 43: Apartment building construction project report

31

Figure 2.7 Formwork and Falsework (taken from New Market Construction Site

Visit in Dimapur).

Formworks to Footing Pads: Most of the pads which have larger and similar size

were made via plywood formworks. Those of pads with a smaller size were made via

together fixed timbers of locally available type. Such formworks was dismantled and

directly fitted to their similar type pads, successively as shown in figure 2.8.

Formworks to Foundation Column: A Foundation column with similar cross-

section and height was identified and their respective formworks were made ready, in

a manner that they could be able to use them in rotation as shown in figure 2.9.

Formwork to Elevation Columns: same as explained in Foundation Columns. The

only exception here was the height of the columns. Since the height of the columns in

some of the blocks is different than the others, the formwork preparations were

consider this fact as shown in figure 2.10.

Page 44: Apartment building construction project report

32

Figure 2.8 : Formwork to Footing Pads (Photo taken from New Market

Construction Site Visit in Dimapur)

Figure 2.9 : Formwork to Foundation Column (Photo taken from New Market

Construction Site Visit in Dimapur).

Figure 2.10 Formwork to Elevation Column (taken from New Market Construction

Site Visit).

Page 45: Apartment building construction project report

33

Formwork to Grade Beams: together sawn timbers of locally available type were

made ready for all internal and external surfaces of the Grade Beams.

Formwork to Suspended slabs and beams: Plywood formwork was made available

to all these parts of the structure.

2.6.2.5 Concrete Mixing Method

Concrete: Concrete is a composite consisting of the dispersed phase of aggregates

(ranging from its maximum size coarse aggregates down to the fine sand particles)

embedded in the matrix of cement paste. This is a Portland cement concrete with the

four constituents of Portland cement, water, stone and sand. These basic components

remain in current concrete but other constituents are now often added to modify its

fresh and hardened properties.

This has broadened the scope in the design and construction of concrete structures. It

has also introduced factors that designers should recognize in order to realize the

desired performance in terms of structural adequacy, constructability, and required

service life. These are translated into strength, workability and durability in relation to

properties of concrete.

In addition, there is the need to satisfy these provisions at the most cost effective price

in practice. Since our building is a reinforced concrete structure the concrete work

was commenced every day for constructing/development of every part of the building.

Constituents of Concrete: The constituents of modern concrete have increased from

the basic four (cement, water, stone, and sand) to include both chemical and mineral

admixtures. These admixtures have been in use for decades, first in special

circumstances, but have now been incorporated in more and more general applications

for their technical and at times economic benefits in either or both fresh and hardened

properties of concrete.

Cement: Cement may be described as a material with adhesive and cohesive

properties that make it capable of bonding mineral fragments (‗aggregates‘) into a

compact whole. In this process, it imparts strength and durability to the hardened

mass called concrete. The cements used in the making of concrete are called hydraulic

cements so named, because they have the property of reacting chemically with water

in an exothermic (heat generating) process called hydration that results in water

Page 46: Apartment building construction project report

34

resistant products. The products of hydration form a viscous cement paste, which

coats the aggregate surfaces and fills some of the void spaces between the aggregate

pieces.

The cement paste loses consistency (‗stiffens‘) on account of gradual loss of ‗free

water‘, adsorption and evaporation, and subsequently ‗sets‘, transforming the mixture

into a solid mass. If the consistency of the cement paste is either excessively ‗harsh‘

or excessively ‗wet‘, there is a danger of segregation, i.e., the aggregate tends to

separate out of the mix; this will adversely affect the quality of the hardened concrete

and result in a ‗honeycomb‘ appearance. The freshly set cement paste gains strength

with time (‗hardens‘), on account of progressive filling of the void spaces in the paste

with the reaction products, also resulting in a decrease in porosity and permeability.

Aggregate: Since aggregate occupies about three-quarters of the volume of concrete,

it contributes significantly to the structural performance of concrete, especially

strength, durability and volume stability. In general, aggregates in concrete have been

grouped according to their sizes into fine and coarse aggregates.

The separation is based on materials passing or retained on the nominally 5 mm

(ASTM No. 4) sieve. It is common to refer to fine aggregate as sand and coarse

aggregate as stone. Traditionally, aggregates are derived from natural sources in the

form of river gravel or crushed rocks and river sand. Fine aggregate produced by

crushing rocks to sand sizes is referred as manufactured sand.

Water: Water has a significant role to play in the making of concrete — in mixing of

fresh concrete and in curing of hardened concrete. In order to ensure proper strength

development and durability of concrete, it is necessary that the water used for mixing

and curing is free from impurities such as oils, acids, alkalis, salts, sugar and organic

materials.

Water that is fit for human consumption (i.e., potable water) is generally considered to

be suitable for concreting. However, when the portability of the water is suspect, it is

advisable to perform a chemical analysis of the water.

Admixtures:

Admixtures are defined as materials other cement, water and aggregate that are used

as ingredients of concrete and are added to the batch immediately before use or during

Page 47: Apartment building construction project report

35

mixing. These day concrete I being used for so many purposes in different condition.

In these conditions ordinary concrete may fail to exhibit the required quality or

durability or workability. In most cases admixture is used to modify the property of

the ordinary concrete so as to make it suitable to any condition.

Admixtures are additives that are introduced in a concrete mix to modify the

properties of concrete in its fresh and hardened states. Fast curing admixtures allow

curing the concrete within 3 to 5 days after the date of pouring the concrete. Such

application will only be made after the conduct of the test and the satisfaction of the

Resident Engineer.

The amount of the admixture to be added varies in accordance to the manufacturer‗s

specification. All relevant documents and specifications will be available before

conducting the mix design and test for approval. After the satisfaction of the

Supervisor the Contractor will execute the successive duties.

If the use of admixtures ensures the early curing of the concrete structure, the date of

removal of the formwork will be dictated accordingly.

In our site two type of admixture has been used. This are:

a) Nito bond

Nito bond is used for bonding fresh to old concrete especially for beam after it is

suspended for 24 hours. Its color description is supposed to be white and green. There

is another agent called Epoxy which has a capacity to harden after 30 minutes.

b) Rheomix

Rheomix is another type of admixtures used in the site. It is used for bonding old

poured concrete with fresh poured concrete especially for plastering, slab, stair case

and normal beam. Its color appears to be white. It will be mixed with water before

used. And its mix ratio goes like this with two steps.

The first step said to be primary coat uses a ratio with water one to four (1:4). The

second and the final step said to be secondary coat uses a ratio with water one to one

(1:1).

Page 48: Apartment building construction project report

36

Table 2.5 : Admixture Used in the Site.

Admixture name Use Dosage

Epoxy resin concrete

bonding agent

(NITOBOND EP)

For bonding of fresh wet

concrete to existing

cement surface.

By spraying over the joint

(not specified).

High performance super

plasticizing admixture,

accelerator (CONPLAST

SP 430)

To provide excellent

acceleration of strength

gain at early stage and

major increase in strength

at all age by significantly

reducing water demand in

a concrete mix.

Ranges from 1litter per

100 kg cement material.

Concrete Mixing Method: Through mixing of materials is essential for the

production of uniform concrete. The mixing should ensure that the mass becomes

homogeneous, uniform in colors & consistency. There are two methods adapted for

mixing concrete.

Hand Mixing and

Machine Mixing.

2.6.2.5.1 Hand Mixing

Hand mixing is practiced for small scale unimportant concrete works. As the mixing

cannot be through & efficient, it is desirable to add 10% more cement to compensate

the inferior concrete produced by this method.

2.6.2.5.2 Machine Mixing

Machine mixing obviously gives better and uniform mixes than hand mixing and

because of this reason, it is generally recommended. There are different types of

concrete mixers such as, Tilting drum mixer, non-tilting drum type, pan mixer type,

truck mixer, plant mixer etc.

Page 49: Apartment building construction project report

37

It is seen from experiment that the strength of concrete will increase with increasing

time of mixing, but for mixing time beyond 2 min, the important in compressive

strength is not very significant.

The following figure shows one of the mixer machines called tilt drum mixer which

we used in site:

Figure 2.11 : Tilt Drum Mixer Used in Site.

2.6.2.6 Batching

Prior to the mixing of ingredients it is essential to measure the materials accurately to

ensure the right proportions. The concrete may be batched either by weight or by

volume. The batching is done by using batching box which is shown in the following

figure:

Figure 2.12 : Batching Box Used in Site.

Page 50: Apartment building construction project report

38

The following table shows the ratio and box dimension of different concrete classes:

Table 2.6 : Box Dimension Ratio.

CONCRETE

CLASS

RATIO BOX

DIMENSION

USES

C-5 1:4:6 16*40*50 Lean Concrete

C-25 1:2:3 18*40*50 Pad, Slab, Beam,

Stair, Column,

Shear wall.

C-30 1:2:3 16*40*50 Grade Beam,

Column, Shear

Wall.

Methodology: The concrete work involves three types of concrete grades; C-5, C-20,

C-25. Except for the lean concrete to the rest of the concrete types we are going to

employ ordinary Portland cement of ACC Cement. For the later prepare test cubes

and sample was taken for different curing schedules.

Fast curing concrete admixture for all horizontal but suspended reinforced concrete

structures was introduced. The use of this admixture will bring down the date of cure

to a considerable standard. Taking the advantage of this shortened date of curing, the

formworks can be relocated in a speedy manner to the next successive job.The

required grade cement was purchased and stored in advance.

The secure of such important materials at the earliest possible time would have an

enormous advantage. A store was constructed out of Corrugated iron sheet (both the

wall and the roofing).

A platform elevated from the natural ground level was made from dry eucalyptus in a

very close spacing in one direction. A thick polyethylene sheet was placed on top of

the wood and then the cement is stored. Gravel was available around Dimapur town.

Page 51: Apartment building construction project report

39

The mix design will comprise of the employment of fine aggregate altogether with

approved sand quality. The concrete work requires machine intensive approach, so

that relevant output could be implied.

A stationary mixer of 750lit capacity and mobile mixer of 2500lit capacity were

deployed for the batching of the concrete.

The mobile mixer was self-loading, self-watering and self-shooting, with the help of

extra shooter produced on site. The stationed mixers will be supplied with dumper and

the output also will be conveyed by the same to the specific place. As they are going

to use fast curing admixture, the workability of the concrete increases, before the

setting time begins.

As the curing date will be shortened the project will be advantaged from time. The

uplifted structures was essentially were supported by the mobile crane. Such

mechanized approach is essential to fulfill the interest of the project to complete the

task within the specified period of time.

The maximum concrete work capacity within a day was 165m3/day. The concrete

casting was stopped where allowable distances are covered with respect to the

structural elements.

The continuation was performed by creating a strong bondage methodology. Such

bondage points do not exceed more than 1/3 distance from the nearest beam. Joints

were treated with special chemicals like epoxy, so that harmonized structural concrete

was established.

Lean concrete(C-5): It poured and placed in position on a surface which presupposes

trimming. The mix was made by utilization of 150kg cement /m3 of concrete in

minimum. The cement use for such work was PPC.

Footing Pad(C-25): After the form work is done concrete was mixed using the ratio

of 1:2:3 ratios. The capacity of the self-feeder mixer was satisfy alone this amount.

Since the mixer is reaching close to the pads and equipped with own shooter the

pouring was easy.

Foundation Column(C-25): It basically follows the finish of the footing pads.

Forthwith the casting of the footing pad concrete and the placement of rebar and

Page 52: Apartment building construction project report

40

fixing of formwork, the same number of footing columns as the footing pads was

casted. Concrete was poured by labor receiving from the dumpers.

Grade Beam(C-25): Following the finish of masonry wall lean concrete will be

poured in order to maintain even and level surface. Forthwith the placing of

reinforcement bar and the formwork the concrete were poured. Where the casting of

the concrete could not be finalized within the day proper joining places will be

maintained like keeping the distance, 1/3 of the grade beams length.

Ground Slab(C-20): c-20 grade of concrete was applied on ground slabs. After the

works underneath are finalized and the horizontal level is maintained, the placement

of the reinforcement bar mesh was take place.

The next thing that will come is casting of the concrete. As all ground slabs are

surrounded with grids of the grade beams, it was simple to cast on each grid,

following the guide of level given by the grade beam.

Elevation column(C-25): The same procedure was followed as the foundation

columns. Though the height in some of the blocks is different than the others, the

casting was monolithic.

Suspended Slabs and Beams(C-25): The concrete casting of suspended slabs and the

adjoining beams executed at the same time. Before the casting of the concrete the

placement and tying of the concrete spacers were carefully done, in order to ensure

the required concrete cover. Dusts and other detrimental dirt were getting removed.

After making sure that all surfaces are clean and the temporary structures are stiff

enough the casting was induced.

The library and the dining block suspended slabs and adjoining beams are of huge

volume. Therefore, highly mechanized casting was deployed to carry out the duty. For

the sake of minimizing the joints, the output of the work there was escalated. Into this

effect, mobile crane and the self-feeder mixer were used. Working of extended extra

hour was also observed.

2.6.2.7 Curing of Concrete

The curing of concrete is a reaction between the type of cement in the concrete and

the water. This reaction between cement and water is known as hydration .when the

Page 53: Apartment building construction project report

41

concrete sets and gains strength through this process. So curing is very importance for

the following main reasons:

It is known that all the properties of good concrete are related to perfect setting of

cement. It is also know that the process of setting involves complex hydration

reaction, which requires a lot of water. A good quality of water is added to the

concretes while making the mix.

After placing the concrete, some water from the concrete may be lost due to

evaporation. Hence the first and foremost purpose of curing is to provide enough

quantity of water for cement to hydrate the set completely.

To prevent formation of surface cracks due to rapid loss of water while the concrete

is fresh and concrete.

Another purpose of curing is to maintain a proper temperature in and around

the concrete during the setting process. This is because both freezing and drying

temperatures hamper the process of setting of cement in a normal manner.

The most important purpose of curing is to ensure the concrete of good quality

when set, strong enough to stress, hard to abrasion and resistant to chemical attacks.

Such a concrete is quite durable.

Different method of procedures has been adopted for curing in the site. These are:

Spraying of water

Pounding of water

Wet covering

Sprinkling water on concrete

Page 54: Apartment building construction project report

42

Here we can see a figure which shows wet covering of a column:

Figure 2.13 : Curing by Wet Covering (taken from my assigned building site).

2.6.2.8 Structural Work

2.6.2.8.1 Grade Beam or Plinth Beam

We can see the construction of a grade beam in the following figure.

Figure 2.14 : structural grade beam construction (taken from site visit)

Page 55: Apartment building construction project report

43

It has a direct contact with the foundation columns and is constructed above the

masonry wall. The reinforcement and provision of detailing is similar to other types of

beams. It is used to carry and transfer super structural loads to the foundations.

Figure 2.15 : Rebar at Plinth Level at Ground Floor for Parking (taken from

assigned building at Niesato Colony)

2.6.2.8.2 Reinforcement Steel Bar

In the following figure we can see steel bars of beam:

Figure 2.16 : Reinforcement steel bar for beam (taken from New Market

Construction Site Visit in Dimapur).

Page 56: Apartment building construction project report

44

Reinforcement steel bars play great role in making reinforced concrete structure more

strong and durable. All reinforcement is free from loose mill scale, loose rust, oil and

grease, or other harmful matter, which might prevent the proper adhesion to concrete.

As necessary reinforcements cleaned by wire brushing. The reinforcement must

always be cleaned before placed in position or before concrete poured.

2.6.2.8.3 Slab

Slab is a plane horizontal structural element used to support live loads and equipment

loads and transfer these loads to the supporting beams or walls. Slabs can be one way

or two way depending on the ratio of the long span to the short span if the ratio of the

long span to the short span is greater than two, the slab is said to be one way; but if

this ratio is less than two, the slab is said to be two way. When a slab is one way, the

bending is one directional and when it is two way, the bending is two directional.

Slabs can be categorized into three; solid, flat, or ribbed. Solid slab is made of

reinforced concrete. In case of our site we are able to see construction of solid slab.

2.6.2.8.4 Splicing of Bars

Reinforced concrete can function as a structural material only if there is a perfect

bond (adhesion) between the concrete and the reinforcing bars. This bond allows two

lengths of reinforcing bars to function as one continuous bar through lap splices.

Sometimes it becomes impossible to get required length of bar or it is required to

make use surplus small length of bar and may be the drawing recommend to splice

bar at that position. Then it is necessary to give a suitable lap of bar as shown in the

figure over each other to develop full strength.

Figure 2.17 : Bar Overlapping (Splicing).

Page 57: Apartment building construction project report

45

When splicing or overlapping was provided in reinforcing steel they must be away

from the section which have maximum stress. I.e. bar was spliced in the site for

bottom reinforcement at the support and for top reinforcement at the center in a length

of four times the larger diameter of bar for every structure.

2.6.2.8.5 Superstructure Beam

A beam is a structural element that is capable of withstanding load primarily by

resisting bending. The bending force induced into the material of the beam as a result

of the external loads, own weight, span and external reaction to these loads is called a

bending moment.

Beams generally carry vertical gravitational forces but can also be used to carry

horizontal loads i.e. loads due to an earth quake or wind .The loads carried by a beam

are transferred to columns walls which then transfer the force to adjacent structural

compression members.

2.6.2.8.6 Column

Column is a vertical structural member transmitting axial compression load with or

without moments. The cross sectional dimension of a column are generally

considerably less than its height. Column supports mainly vertical loads from the

floors and roof and transmits this load to the foundation.

2.6.2.9 Finishing Work

2.6.2.9.1 Plastering Work

Plastering work is the end work to bring construction decoration with plaster, such as

a layer of plaster on an interior wall or exterior walls. The process of creating plaster

work called plastering. It has been used in projects to fill rough and uneven surface.

Cement mortar is a mixture of water, cement and sand which is used for plastering

purpose on the site.

There are three types plastering these are:

First coat: Is used to create a rough surface for the next coat to adhere effectively. It

is made with a ratio of 1:4 i.e. 1 Bag of cement and 4 Box of sand. 1 up to 2 days of

curing is needed for it to attain sufficient strength.

Page 58: Apartment building construction project report

46

Second coat: It covers most of the body of the coating and creates a good base for the

next coating. Misalignment of HCB, Beam or any other structure can be balanced by

the second coating type.

On average it has a thickness of 1.5 cm. It is made with a ratio of 1:3 i.e. 1 Bag of

cement and 2 Box of sand. One week of curing is needed for this type of coating

to attain sufficient strength and adhere effectively.

Third coat: On average it has two up to four millimeters of thickness. This stage of

coating is the last and outermost part. It should have smooth and uniform appearance

as its aesthetic value is great importance. It‘s made with a ratio of 1:1 i.e. 1 Bag of

cement and 1 Box of coarse sand. It should be cured successively with great attention

until it gets enough strength.

2.6.2.9.2 Ceiling and Wall Finishing

Gypsum chuck: It can be considered as both internal walls finishing and ceiling

finishing process. Gypsum chucking is performed over well plastered wall or roof

after all the moisture get dried.

It is applied only for internal walls since it is easily failed by dampness.

Gypsum chucking means painting a thick gypsum paste, gypsum with water, to create

a smooth and good looking surface. It also helps to decrease paint consumption of the

wall by filling all the voids and creating a smooth surface.

Application procedure: Mixing: -To mix add the water into clean container then add

the powder gypsum onto the water and mix slowly until mix is homogeneous to avoid

foaming.

Paint the paste repeatedly through by squeezing over the wall or roof to have a final

smooth surface. The following picture shows gypsum work of ceiling and wall

finishing:

Page 59: Apartment building construction project report

47

Figure 2.18 : Ceiling and Wall Finishing (taken from DDSC Stadium Repairing

Work Site in Dimapur).

2.6.2.9.3 Floor Finishing

Floor finish is one of the last steps of a construction. Among the floor finishing factor

that will influence the selection of floor finishing are as follows:

Function of the floor

Price

Maintenance

Comfortable

We can see marble chips after laying in the bottom figure:

Figure 2.19 : Marble Chips/Tiles (taken from DDSC Stadium Repairing Site in

Dimapur).

Page 60: Apartment building construction project report

48

A good finishing will have the following characteristic:

Look attractive

Safe and comfortable

Long lasting and able to prevent high temperature and fungi-chemical

corrosion

Types of floor finishing

There are different floor finish exercised in the site these are:

Terrazzo tile

Ceramics

Marble chips/tiles

PVC tile/plastic tiles

Marble flooring: Marble flooring is one of the most expensive floor finishes.

Properties:

Made of sedimentary rocks

Different sources – Granite, Marble

Durable, Water proof and Good aesthetical appearance

Available in different dimensions and colors

Construction: The construction of marble flooring follows the following procedure

The casted concrete surface has to be chiseled.

this is done to create bondage between the surfaces

Spread cement screed over the chiseled surface and level it

Pour cement paste (cement with water) over the screed and fix the marble

keeping the level.

Marble flooring has to be cured and cleaned before use

Marble Chips/ Tiles: The marble chips floor finish is a little bit different from the

floor finish laying methods that is lay here and there. After the marble chips lay it will

be fully covered with mortar to the extent that even the top surfaces of marble chips

are not visible and after 21days the top covering of the mortar will be

polished/washed with washing machine.

Page 61: Apartment building construction project report

49

2.7 Procedure I used when I perform work tasks

The site work I performed was controlling how the work was going on and

supervising the work based on the given check list which was given to us from the

company‘s office. The checklist for site supervisors is issued in order to ensure a

uniform system of supervision of building construction projects and as a result ensure

the quality of construction. In the checklist the responsibilities, liabilities and

limitations of the supervisor are briefly mentioned in the steps to the general terms.

Details of construction are specified in the drawings, technical specifications and in

the general and special conditions of the contract. The duty of mine was to ensure that

the construction works are executed in accordance with the contract requirements. In

the application of the checklist the details specified in the contract document always

precede before the application and use of it. There were also tables and forms in the

checklist that helped to record the incidences affecting the work and as references. In

addition the standard technical specifications were used as reference on the

preparation of the checklist and shall always have precedence over the checklist.

Therefore, I worked most of my time at site to become more familiar with site works

and to get more practical knowledge. Site work in general includes every kind of

work executed at the site starting from setting out till finishing works based on the

given specification and methodology. The site work that I have been trough in the six

months internship period was in the sub structure work and super structure work

exclusively. A normal building consists of two parts in general this are the super

structure and the sub structure.

Any structure below the ground floor slab level including the basement, retaining

walls, ground slab, grade beam, and foundation is called a substructure. In most of the

cases, substructure work can be categorized as earthwork, concrete work and masonry

work. I have seen that how the excavation was done, concrete pouring, masonry work

and back filling.

Super structure is the part of a building which extend above the grade beam or

everything above the sub structure includes slab (1st floor slab), column, walls, roof

etc. the purpose of the super structure is to enclose and divide space as well as spread

load safely in to the sub structure.

Page 62: Apartment building construction project report

50

2.8 My Performance during Executing the Work Tasks

Absolutely good! The reason behind this performance was that I integrated with all

workers within a short time and get involved in different site works to gain more

knowledge about the working environment in the site and improved myself with more

site works and office work. Since the site work was very repetitive I was working in

different section to get involved and pass through different piece of works. Especially

the work tasks I was performing in the office work were very impressive because I

didn‗t have any knowledge about the quantity works, cost and report writing etc. In

general in the last six months I performed all my duties sincerely and nicely and got

knowledge of the practical world and relate it with the theory I have learned in the

class in the last three years. Also I transformed myself to another level of skill, ethics,

knowledge and leadership using this internship class and I performed it well.

2.9 Challenges that I faced

Construction projects are complex and time-consuming undertakings that require the

interaction and cooperation of many different persons to accomplish. The construction

industry is typically divided into specialty areas, with each area requiring different

skills, resources, and knowledge to participate effectively in it. In order to integrate

and work closely in each section it is a challenging task to one person especially when

he/she is fresh or beginner. In fact some challenges may be solved by me but some are

above my limit and even the workers at the site also.

During the course of the six months internship program at the company, it was

expected that I face some sort of difficulties. Indeed I was challenged to some extent.

These challenges were not due to my lack of initiation towards performing the task I

was given instead it was simply a matter of experience in the field. And that was

something that could be solved by continually engaging one‘s self to the activities in

the course of time. But there were also some challenges that could have been

corrected by the company and what I did or should have done wouldn‘t have brought

that much difference.

Around the first month through the program, I was a bit confused. This was due to the

fact that the employees of the company were obviously more experienced than I was

and already understood the easiest ways that enabled them to accomplish their

respective tasks in a proper manner.

Page 63: Apartment building construction project report

51

During the course of time, there were occasions where I was given full responsibility

on a specific task, for instance preparing a quantity from for a given project, and at

first I didn‘t feel I was up to the task but through time I learned to accept challenges

with confidence.

While attending my routine site visits, I had to interact with the professionals that

were stationed at those sites. And these professionals, even though their knowledge of

the construction world was to a great extent, had to use these layman terms while

performing their usual activities that were not clear to me at the time. It could be said

that they were communicating with a whole different vocabulary. Almost every

construction machinery had its own name and every process was identified with a

description different from what I had previously learned.

Being able to meet the expected arrival time at the company was a bit hard to get used

to at first. I am sure no one found this particular case of challenge easy at first.

Especially if one was stationed within the office for the majority of the internship

program, it was hard getting used to spending that much time after attending the

company that early.

During those site visits, I had trouble engaging the attention of the working men while

I was trying to inquire about the different things that I had observed.

While I was faced with such speed bumps, I obviously had to look for alternatives that

may greatly reduce the challenges I was facing. And these measures did help in way

that made the work flow easier to conduct;

Through time, I had to bring myself to learn the manners by which activities

were conducted so that there won‘t be any gap created because of me.

Regarding the arrival time to the company, I simply brought myself to get

used to the fact and engaged myself in activities so that I didn‘t have to waste

time just by sitting around in the office doing nothing.

Developed my confidence in the matter of accepting a responsibility by

volunteering to execute different tasks and managing to complete these tasks

to the requirements set by my superiors.

When it came to understanding the terms that were used on the construction

site by the professionals, all i could do was learn these terms by continuously

trying to use them in a discussion and inquiring whenever necessary.

Page 64: Apartment building construction project report

52

Being able to command the attention of the site workers was a bit hard at first

but through time and after a discussion or two about the tasks conducted on

the site, it got a lot easier.

In general I have faced the following challenges in the internship period.

Communication problem with workers in the office and at the site.

Shortage of working drawings like structural, architectural, sanitary, electrical

and some other details.

Weather condition of the site.

Shortage of knowledge in some portion of the work at the site.

Underestimation by workers such as engineers, Foreman.

Unsatisfactory answers for questions from engineers.

Safety facility.

2.10 Measures I Took For Challenges

Communication challenge was the most dangerous challenge from all challenges

because of that it blocks me from finding more knowledge from skilled workers and

other persons those are closed to the site work. Their language at the site was mostly

an Italian word that makes me more confused and it was uneasy to know those words

within a few days. At last I was able to understand those words through experience

and by working with the employees. Those words are:

Table 2.7 : List of non-technical terms used in Site.

Technical Word Word Used in Site Meaning

Stirrup Staffia Shear resistance members

of columns, beams and

shears walls.

Plumb bob Tumbi It is used for checking

verticality of structural

members.

Footing pad bars Girila Reinforcement bar mesh

under footing pad

Page 65: Apartment building construction project report

53

Bottom soffit Phondo Used as a formwork for

beams and slabs at the

bottom.

Side board Sponda Used as a formwork for

beams and slabs on

vertical sides.

Brace Mekesecha Support a vertical side

formwork of a beam and

column diagonally.

Scaffolding Kebeleto Used as a support of

formworks of a slab and

beam at the bottom.

Tee Khuri Support a formwork of a

beam.

Profile Line Used for setting out works.

String Rooshi Used to maintain

alignment.

Yoke Kabja Used to fix the formworks

together in their position

Trowel Corni Used to apply and spread

mortar or plaster.

Spade Pharwa Used to dig soil.

Tape Phita Measuring instrument.

Page 66: Apartment building construction project report

54

Those are the main site language I able to understand but there are some others

language they used to communicate that I didn‗t able understand it still.

Drawing shortage: since I have been working in the consultant side we, asked

together the resident engineer. And he gives as in soft copy and hard copy as we want

within a week.

Weather condition of the site: since I‗m fresh to such work I have been in a big

nuisance particularly in the first month to adopt this kind of working environment.

The main challenge was the sun light and dustiness of the site due to construction

equipment. I bought a hat from the market that was suitable for sunlight and I wear a

sun glass to combat the hot condition.

Shortage of knowledge in some portion of works like quantity, bill of quantity, taking

off, bar schedule and report writing was some challenges I have faced in the site. To

solve these problems I try to ask workers at the site and read related literature to know

more about this works. Lastly I knew how to work those things.

The underestimation and the answer were not solved throughout the month with some

workers but I try to communicate friendly with some workers to make myself clear

and to know more knowledge from workers. And the answering problem was aroused

due to that the contractors have no idea about how the building is designed and some

shortage of knowledge about the design. We ask the design supervision team when

they come for supervision and monthly meeting of the tree parties and know how the

structural design was designed and some other misunderstanding.

Page 67: Apartment building construction project report

55

CHAPTER 3

3. DETAILED PROJECT REPORT OF PLANNING

AND DESIGN OF FIVE STOREYED

APARTMENT BUILDING

3.1 Introduction

In this chapter a Detailed Project Report (DPR) of G+4 (five storeyed) Residential

Apartment Building on which I was entrusted to carry out the works has been

discussed which I had done at site and office during my six months internship

training. The building construction site is located at Niesato Colony, Dimapur:

Nagaland. The planned site is also well connected to other major places nearby as it is

situated near National Highway running from Assam to Kohima. The highway is

traversed by local city auto rickshaw throughout the day, giving better connectivity to

the place. Moreover, airport and railway station of Dimapur is just 20 minutes and 10

minutes‘ drive from the site. Dimapur has a monsoon influenced humid subtropical

climate characterized by very hot summers and cool winters. The maximum rainfall

recorded is about 24.9cm in the month of August. The area faces an absolute

maximum temperature of 42ᵒC during summers and a minimum of 6ᵒC during chilly

winters. The maximum recorded wind velocity is 93 Km/hr. during the month of

March.

The detailed planning and design of the building as per requirements of residential

building has been discussed in further topics to come.

When I joined the Company in the month of January, the earthwork and foundation

works were already done at site, the columns were left for curing, and the ground

floor work was going on. But my mentor briefed me ‗what‘ and ‗how‘ the works of

earthwork and foundation works were done.

I couldn‘t stay till the completion of the building as I had to leave as my six months

internship period came to an end. The building was still under construction till the

time of writing this project report. In this project report writing, I wrote only which I

executed, experienced and learned from my six months internship period.

Page 68: Apartment building construction project report

56

3.2 Plan and drawing of building (Ground Floor)

The plan and drawing of the proposed G+4 residential apartment building that I was

working on during my internship was designed by Aling Lotha. This building project

was executing by the company I was working with, M/s Singh Construction Co.

The plan of the proposed apartment is shown below:

Figure 3.1 : Ground Floor Plan (photocopy of original building plan).

Page 69: Apartment building construction project report

57

From the plan it is seen that the centre to centre distance between two walls of a room

is 12ft. The building apartment is of 2BHK flat. The plan area of the building is 87ft.

x 87ft. The ground floor has a parking space area of 87ft. x 36ft. Each footing is

isolated footing.

3.3 Plan and drawings of first to top floor

The plan and design of the typical floor plan/drawing is shown below:

Figure 3.2 : Typical Floor Plan (photocopy of original building plan).

Page 70: Apartment building construction project report

58

The building being an apartment building, design all the floors from first to top floor

are the same. The room dimensions are all same. The apartment flat is typically a

2BHK flat (two bathrooms, one hall and one kitchen).

3.4 Details of beams

The drawings of the roof beam layout and beams details are shown below:

Figure 3.3 : Roof Beam Layout (photocopy of original building plan).

Page 71: Apartment building construction project report

59

Roof beam reinforcement detail plan:

Figure 3.4 : Roof Beams Reinforcement Details (Photocopy of Original Building

Plan).

Page 72: Apartment building construction project report

60

All the construction work at site was strictly executed as per the drawings given by

the engineer. The site engineer who was supervising me taught me how to read and

execute the plan and drawings in the site. In office my mentor taught me how to

design the building components like beams, slab, column, staircase, lift and so on as

per the IS Code specifications.

From the design detailing plans as shown above, the depth of the Roof-Beam and

Plinth-Beam is given as 14inches and 12inches respectively. The width for both the

Roof-Beam and Plinth-Beam is given as 10inches. But not in the case of Plinth-Beam.

The following points for each type of beam are concluded as:

(i) Roof Beam (RB1):

The roof beam at the end support section have high shear as compared with the mid-

section of the beam. So for this reason to overcome this shear extra reinforcement has

to be provided in the compression zone of the beam. From the drawing it is seen that

for Roof-Beam at end support section 6 nos. (3 at compression zone & 3 at tension

zone) of main bar of 16mm dia. reinforcement bar is provided and also 8 mm stirrups

at a centre to centre distance of 6inches are provided.

The roof beam at the middle section of the building has fewer shear and lesser

moments, for these reasons the reinforcement at the compression zone of the mid-

section of the beam is provided with lesser number of reinforcement bar. From the

drawing it is seen that 5 nos. (2 at compression zone & 3 at tension zone) of main bar

of 16mm dia. reinforcement bar is provided and also 8 mm stirrups at a centre to

centre distance of 6inches are provided. Both of those types of Roof-Beam are

represented as RB1.

(ii) Roof- Beam (RB2):

This beam is same as the RB1. All the diameter, type of steel, spacing of bar and

stirrups are the same for the cases of End Support Section and Mid-Section as seen in

the case of RB1, except that the diameter of the centre Reinforcement bar provided at

the compression zone of this beam is smaller. The diameter of centre reinforcement

bar in compression zone in this beam is 20mm. This type of Roof-Beam is

represented as RB2.

Page 73: Apartment building construction project report

61

(iii) Tie-Beam (TB-1):

Tie Beam is also called Plinth Beam. This beam is provided at the bottom of the

building. The brickwork of the superstructure starts from this beam. The depth and

width of this beam is 12inches and 10inches respectively.

For End Support Section, the beam is provided with 6 nos. of 16mm dia.

reinforcement bars. 8mm Stirrups at a c/c distance of 6inch are provided.

For Mid-Section, the beam is provided with 5 nos. of 16mm dia. reinforcement bars

(2 in compression & 3 in tension zone). 8mm Stirrups at c/c distance are provided.

These types of Tie-Beam are represented as TB1.

3.5 Details of Elevator (Lift)

The G+4 apartment building had an Elevator (Lift) which connects all the floors of

the building. Although I couldn‘t see the work complete as I had to leave the training

as my training period came to end.

The dimensions of the Lift are:

Width of Entrance – 800mm

Height of Car inside – 1600mm

Width of Car inside – 1100mm

Height of total Fin. Hoist Way – 2000mm

Width of total Fin. Hoist Way – 1900mm

To carry the load, moment and shear due to this Lift, the wall section had to be

provided with RCC (Reinforced Cement Concrete) and designed accordingly. The

height between successive floor levels of the building was 1500mm.

The design drawings of the section of RCC wall is shown below:

Page 74: Apartment building construction project report

62

Figure 3.5 : Lift Elevation Detail (photocopy of Original building Plan).

Page 75: Apartment building construction project report

63

Figure 3.6 : Section of RCC Wall detailing Plan (photocopy of Original Building

Plan).

It was unfortunate that I couldn‘t see how the Lift work execution would take place as

the Lift were to be installed after most of the building superstructure were completed.

And as a matter of fact the Lift would not be installed yet as the building were still

under construction till the time of writing this project report.

Page 76: Apartment building construction project report

64

3.6 Details of Footing and Columns Reinforcement

All the loads of the structure is transferred to beams and from beams it is transferred

to columns and from columns it is transferred to column footings and from footings to

the soil beneath. So the columns and footings has to be designed so as to withstand

the loads with minimum cost.

The plan and cross-section of the Footing and Column Reinforcement is shown

below:

Figure 3.7 : Sections of Column Reinforcement and Footing (Photocopy of

Original Building Plan).

Page 77: Apartment building construction project report

65

The details of columns reinforcements and footings are shown in above figure. All the

dimensions of columns are the same of 12‖x16‖. All the column footings are of same

dimensions of which the heights of the lean concrete is 5‖, first footing is 10‖ and

second footing is 18‖. The height of foundation from ground level is 7‘. The cross-

sectional area of footing is 8‘x7‘. The height of the room is 10‘.

3.7 Foundation Layout Plan

The Foundation Layout Plan is shown below:

Figure 3.8 : Foundation Layout Plan (Photocopy of Original Building Plan).

Page 78: Apartment building construction project report

66

The foundation layout of the building in which I was working was built strictly

according to the plan shown above. In this building plan all the footings are of same

size and shape. There are 64 (sixty four) column footings in total.

3.8 Estimation and Costing

The estimation and costing was the first thing that I was taught in my internship

period. My mentor taught me very well how to do estimation and costing of the

buildings, bridges and roads. The estimation of buildings and bridges are very much

related. We did the costing of the building by taking the current market price of the

materials used.

3.8.1 Methods of taking out estimates

The calculations of quantities of materials can be done using various methods of

estimates. The application of an individual method depends upon the design and

shape of the building. The different methods are as under:

1. Centre line method.

2. Crossing method.

3. Out to out and in to in method.

4. Bay method.

5. Service unit method.

The two most extensively used common method in estimation is:

1. Centre Line Method

2. Out to out and in to in Method (Long wall and Short wall Method)

1. Centre Line Method: This method is suitable only if the offsets are symmetrical and

the building is more or less rectangular in shape. The centre line of the building is

determined carefully after doing deductions for repeated measurements (as explained

in the next problem). This centre line acts as length for the complete calculations of

the estimate. If the deduction is not cared for the results of estimates may be wrong.

All the walls should have the same section.

2. Out to out & In to in Method: This method is also called Long wall and short wall

method. This method is most practicable under all circumstances and is generally

followed in the P.W.D. for computing the quantities of various items.

3.8.2 Detailed Estimation and Costing of my assigned Building.

The building which was assigned to me was a G+4 (five storeyed) apartment building

at Niesato Colony in Dimapur, Nagaland. The apartment was designed by Aling

Page 79: Apartment building construction project report

67

Lotha and was checked and verified by Loguseng Semp of Environ Assemblers,

Dimapur. This building project was executing by the company I was working with,

M/s Singh Construction Co. In making this Estimation, my mentor assisted me. He

taught me very well. He gave me so much knowledge in estimating the building from

theory and practical point of view for which I am highly obliged to him.

3.8.2.1 General Abstract of Cost

Proposed Construction of M/s Singh Apartment Construction TA2016.

Table 3.1 : General Abstract of Cost.

Sl.

No.

Particulars Amount

(INR)

1.

2.

3.

4.

5.

Cost Of Building

a) Ground Floor

b) First Floor

c) Second Floor

d) Third Floor

e) Fourth Floor

Total Civil Cost:

Add 10% for Water Supply & Sanitation on (F)

Add 9% for Electrification on (F)

Add 5% for Contingency on (F)

Add 2.5% for Work Charged Establishment on (F)

Grand Total:

(A)

(B)

(C)

(D)

(E)

(F)

₹ 35,08,523.71

₹ 15,59,476.44

₹ 15,59,476.44

₹ 15,59,476.44

₹ 15,59,476.44

₹ 97,46,429.47

₹ 9,74,642.95

₹ 8,77,178.66

₹ 4,87,321.48

₹ 2,43,660.74

₹ 1,23,29,233.30

Say : ₹ 1,23,29,200.00

(Rupees One Crore Twenty Three Lakhs Twenty Nine Thousand Two Hundred)

only

Page 80: Apartment building construction project report

68

3.8.2.2 Quantity Estimate for Ground Floor

CALCULATION OF QUANTITIES ESTIMATE FOR GROUND FLOOR.

Table 3.2 : Quantity Estimate for Ground Floor.

It

e

m

N

o.

Description of Item N

o Dimensions in

metre

Quantity Remarks

Lengt

h

(metre

)

Bread

th

(metr

e)

Heigh

t

(metr

e)

1

2

3

4

5

SUB-HEAD I.

EARTHWORK

Surface dressing

and setting

foundation plan

Earth work in

excavation

(a) Column footings

(b) Panel walls

(considering first as

if there is no

column)

Outer sides………..

Inner sides………...

Deduct the length

covered by the

column footing

Outer sides………..

Inner sides………...

Earthwork in

filling in foundation

trench by loose earth

Sand Gravel filling

up to plinth

(a) For Main walls

(b) For passage way

(c) For staircase row

(d) center room

SUB-HEAD II.

CONRETE WORK

Cement concrete

M10

(a) For Mat concrete

of column footings

1

64

8

8

28.96

2.44

28.96

24.39

2.44

2.13

28.96

2.13

0.60

0.60

0.60

0.60

-

2.13

1.00

1.00

1.00

1.00

Total

838.68 Sq m

708.48 Cum

46.85 Cu m

40.90 Cu m

46.85 (-ve)

40.90 (-ve)

876.81 Cum

28.96=26.52 +

2.44

28.96=26.52 +

2.44

24.39=26.52 –

2.13

3.35=3.67 +

0.31

4.27=4.57- 0.31

2.54=2.44+.10

Offset=0.05

th of excavation (approx.) 175.36 Cum

36

6

6

1

64

3.35

3.35

4.27

4.27

2.54

3.35

4.27

3.35

4.27

2.23

0.60

0.60

0.60

0.60

Total

0.13

242.41

51.50

51.50

10.94

356.35Cu m

47.13 Cu m

Page 81: Apartment building construction project report

69

It

e

m

N

o.

Description of Item No Dimensions in metre Quantity Remarks

Lengt

h

(metr

e)

Breadt

h

(metre

)

Heigh

t

(metr

e)

6

(b) For foundation

of Panel walls

(without columns)

Long walls………...

Short walls………...

Cement Concrete

M15(1:3:6) RCC

work including

shuttering but

excluding

reinforcement

(a)Column footings

(i) Lower portion of

column…………….

(ii) Trapezoidal

portion……………..

(b)Columns………..

(c) Beams (TB1)

Outer sides………...

Inner sides…………

(d) Beams (RB)

Outer sides………..

Front & back

sides…………

(e) Roof Slab

(including staircase,

skylight, Lift areas

first)………………..

Deduct: (i) staircase………..

(ii) skylight………..

(iii) skylight……….

(iv) Lift…………….

(v) Waste chute……

8

8

64

64

64

1

1

2

4

1

1

tot

9.44

9.46

2.44

0.60

0.60

2.13

0.15

0.15

Total

0.25

6.80

6.81

60.74 Cu m

83.16

9.44=(26.52+

2.44)–

(2.44x8)

9.44==(26.52-

2.44)–

(2.44x6)

4.99=1.29+

0.40+0.25+

3.05

23.65=26.52-

0.41-6x0.41

26.93=26.52+

0.41

26.83=26.52+

0.31

0.10=1.22-

0.25/2

2.14=2.51-

0.25/2 - 0.25

15cm bearing

( ) ( )

x0.46

78.37

0.41

23.65

24.35

23.65

24.35

26.93

4.32

4.32

1.10

1.98

2.14

21.48

m

0.31

0.31

0.31

0.36

0.36

26.83

3.42

3.42

2.01

1.83

1.83

21.96

m

Total

4.99

0.25

0.25

Total

0.25

0.25

Total

0.10

0.10

0.10

0.10

0.10

0.10

0.10

Total

161.53Cu m

40.59 Cu m

58.65

60.39

119.04Cu m

68.11

70.13

138.24Cu m

72.25 Cu m

1.48 (-ve)

2.96(-ve)

0.89(-ve)

0.36(-ve)

0.39(-ve)

0.39(-ve)

66.17 Cu m

Page 82: Apartment building construction project report

70

It

e

m

N

o.

Description of Item No Dimensions in

metre

Quantity Remarks

Lengt

h

(metr

e)

Breadt

h

(metre

)

Heig

ht

(metr

e)

7

(f) R.C. Lintel over

doors and windows

Windows, W1

W1 & D (combined)

W2

W3

W4

W5

Outer doors

For Inside walls –

Over doors, D

Toilet doors D1

Trap Door

(g) Balcony

(h) Staircase:

Base of toe wall…...

Waist slab of flights.

Landing (Lower)…..

Landing (at 1st floor)

Steps (without

reinforcement)……..

Railing at staircase...

Hand rail…………

25cm thick DPC

(1:2:4)

Outer wall…………

Inner wall………….

Deduct the length

covered by:

Column……………

Outer door openings

Inner door openings

Toilet door openings

Deduct parking

openings

7

2

6

2

2

2

8

6

6

1

6

1

2

1

1

18

2

2

8

8

64

10

6

6

1.50

2.80

1.30

2.40

3.65

1.40

1.30

46.40

1.3

1.2

1.3

3.97

2.80

2.69

2.80

2.80

1.40

2.69

2.69

0.20

0.20

0.20

0.20

0.10

0.20

0.10

0.10

0.10

0.10

1.67

0.25

1.40

1.55

1.35

0.25

0.08

x0.012

0.10

0.10

0.10

0.10

0.10

0.10

0.10

0.10

0.10

010

Total

0.10

0.20

0.15

0.15

0.15

0.17

0.60

Total

0.21

0.11

0.16

0.10

0.15

0.03

0.21

0.08

0.07

0.01

1.13 Cu m

3.98 Cu m

0.14

1.13

0.65

0.57

0.53

0.26

0.07

42.12 Cu m

1.50=1.20+

1.30

2.80=1.50+

1.30

3.65=3.35+

0.30

1.40=1.1+

0.30

1.3=1+0.3

1.2=0.9+0.3

1.3=1+0.30

3.97=3.67

+0.30

1.55=1.40+

0.15

Bearing in

20cm wall

26.72=26.52

+0.20

26.32=26.52

-0.20

Grand Total (a) to (h) 572.8 Cu m

26.72

26.32

0.41

1.00

1.00

0.90

0.20

0.20

0.31

0.20

0.10

0.10

-

-

Total

-

-

-

-

42.75

42.11

84.86 Sq m

8.13 (-ve)

2.00 (-ve)

0.60 (-ve)

0.54 (-ve)

Page 83: Apartment building construction project report

71

It

e

m

N

o.

Description of Item No Dimensions in metre Quantity Remarks

Lengt

h

(metr

e)

Breadt

h

(metre

)

Height

(metre

)

8

9

Long side………….

Short side………….

SUB-HEAD III.

BRICKWORK

1st class brickwork

in cement mortar

(1:6) in foundation

and plinth (first

consider as if there

are no columns)

Long walls………...

Short walls………...

Deduct the length

covered by columns

Long side………….

Short side………….

1st class brickwork

if 20cm thick

cement mortar

(1:6) in

superstructure wall

(20cm)

Outer side long wall

Front side short wall

Front shortest wall

Center shortest wall

Deduct:

Column lengths

Wall openings

Wall openings

Doors……………

Deduct Windows:

W1………………...

W2………………...

W3………………...

W4………………...

Deduct Lintels…….

8

8

8

8

2

2

1

2

28

1

2

10

9

6

2

2

1

26.32

9.74

26.93

26.21

0.41

0.31

26.72

26.32

4.26

3.26

0.41

4.26

3.36

1.00

1.2

1.00

2.10

3.35

46.40

0.2

0.2

0.20

0.20

0.20

0.20

0.20

0.20

0.20

0.20

0.31

0.20

0.20

0.20

0.20

0.20

0.20

0.20

0.20

-

-

Total

1.05

1.05

1.05

1.05

Total

3.05

3.05

3.05

3.05

3.05

3.05

3.05

2.10

1.50

0.70

1.20

1.20

0.10

Total

42.11 (-ve)

15.58 (-ve)

15.90 Sq m

45.24

44.03

2.76 (-ve)

2.08 (-ve)

84.43 Cu m

32.60

32.11

2.60

3.98

10.85 (-ve)

2.60 (-ve)

4.10 (-ve)

4.20 (-ve)

3.24 (-ve)

0.84 (-ve)

1.01 (-ve)

1.61 (-ve)

0.93 (-ve)

41.91 Cu m

9.74=10.97-

041-2x0.41

1.05=0.6 +

0.6-0.15

2.67=26.52

+0.20

26.32=26.52

-0.20

4.26=4.57 -

0.31

46.40 is the

total length

from 6(f)

Page 84: Apartment building construction project report

72

It

e

m

N

o.

Description of Item N

o Dimensions in

metre

Quantity Remarks

Lengt

h

(metre

)

Bread

th

(metr

e)

Heigh

t

(metr

e)

10

11

12

13

14

Half brickwork of

10cm thick in

cement mortar (1:3)

with H.B. wire

netting

Short length wall

Long length wall

Deduct: Doors

D…………………..

D1…………………

Deduct Lift Door

Deduct Trap Door

SUB-HEAD IV.

FLOORING

7.5cm thick

terraced flooring in

lime concrete

(1.5:2:7) over a

brick flat…………..

Deduct Columns….

25mm thick

Terrazzo work with

Italian marbles for

floors…………….

Deduct:

Skylights

Skylights

Lift & waste chute

column

Supplying, fitting

and fixing

porcelain tiles for

dado of toilet…….

Tor Steel

Reinforcement

(a) Footing @0.6%

of concrete

(b) Column @1.2%

of concrete

(c) Beams @1% of

concrete

32

5

6

6

1

1

1

36

1

2

2

1

36

6

3.35

4.16

1.00

0.90

1.90

1.30

26.11

0.41

26.21

4.98

2.26

3.92

0.41

3.37

0.10

0.10

0.10

0.10

0.10

0.10

26.21

0.31

10.56

3.39

0.86

1.83

0.31

3.57

3.05

3.05

2.10

2.10

2.00

1.00

Total

-

-

-

-

-

-

-

Total

-

32.70

6.34

1.26 (-ve)

1.13 (-ve)

0.38 (-ve)

0.13 (-ve)

34.14 Cu m

684.34

4.58 (-ve)

276.78

33.47 (-ve)

3.89 (-ve)

7.17 (-ve)

4.58 (-ve)

227.67 Sq m

72.19 Sq m

76.08q

38.23q

23.36q

382.22 quintals

76.08q

38.23q

23.36q

161.53x

x78.5q

40.59x

x78.5q

29.79x

x78.5q

Total

Page 85: Apartment building construction project report

73

It

e

m

N

o.

Description of Item No Dimensions in

metre

Quantity Remarks

Lengt

h

(metr

e)

Bread

th

(metr

e)

Heigh

t

(metr

e)

(d) Slab @0.8% of

concrete……………

(e) Lintel @0.6% of

concrete…………..

(f) Balcony @0.8%

of concrete………..

(g) Staircase @0.8%

of concrete…………

(h) within floor of

parking @0.8% of

concrete……………

66.17x

x78.5q

1.13x

x78.5q

3.98x

x78.5q

42.12x

x78.5q

276.30x

x78.5q

Total

41.55q

0.53q

2.50q

26.45q

173.52q

382.22 quintals

3.8.2.3 Quantity Estimate for First Floor to Fourth Floor

CALCULATION OF QUANTITIES ESTIMATE FOR FIRST FLOOR.TO FOURTH

FLOOR

Table 3.3 : Quantity Estimate for First Floor to Fourth Floor.

It

e

m

N

o.

Description of Item N

o Dimensions in

metre

Quantity Remarks

Lengt

h

(metre

)

Bread

th

(metr

e)

Heigh

t

(metr

e)

1

SUB-HEAD I.

CONCRETE

WORK

Cement concrete

(1:2:4) for RCC

work including

shuttering but

excluding

reinforcement

(a) Columns:

For 1st Floor……….

For 2nd

Floor……….

For 3rd

Floor……….

For 4th

Floor……….

(b)Beams:

For 1st Floor……….

For 2nd

Floor……….

64

0.41

0.31

2.69

21.88 Cu m

21.88 Cu m

21.88 Cu m

21.88 Cu m

138.24 Cu m

138.24Cu m

2.69=(3.05+

0.10) – 0.46

Beam depth

Same as 1st Floor………...

Same as 1st Floor………...

Same as 1st Floor………...

Same as 1st Floor………...

Same as 1st Floor………...

Page 86: Apartment building construction project report

74

It

e

m

N

o.

Description of Item N

o Dimensions in

metre

Quantity Remarks

Lengt

h

(metre

)

Bread

th

(metr

e)

Heigh

t

(metr

e)

2

3

For 3rd

Floor……….

For 4th

Floor……….

(c) Slab:

For 1st Floor……….

For 2nd

Floor……….

For 3rd

Floor……….

For 4th

Floor……….

Slab of Staircase

roof………………...

(d) Lintel over

Doors & Windows:

For 1st Floor……….

For 2nd

Floor……….

For 3rd

Floor……….

For 4th

Floor……….

(e) Balcony at:

1st Floor…………....

2nd

Floor…………...

3rd

Floor……………

4th

Floor……………

(f) Staircase for:

1st Floor…………....

2nd

Floor…………...

3rd

Floor……………

4th

Floor……………

7.5cm thick (av.)

lime terracing on

roof………………...

SUB –HEAD II

BRICKWORK.

1st class brickwork

(1:6) in

superstructure wall

For 1st Floor……….

For 2nd

Floor……….

For 3rd

Floor……….

For 4th

Floor……….

Same as 1st Floor………...

Same as 1st Floor………...

Same as 1st Floor………...

Same as 1st Floor………...

Same as 1st Floor………...

Same as 1st Floor………...

138.24 Cu m

138.24 Cu m

66.17 Cu m

66.17 Cu m

66.17 Cu m

66.17 Cu m

1.48 Cu m

2.26 Cu m

2.26 Cu m

2.26 Cu m

2.26 Cu m

7.96 Cu m

7.96 Cu m

7.96 Cu m

7.96 Cu m

42.12 Cu m

42.12 Cu m

42.12 Cu m

42.12 Cu m

1116.00 Cu m

722.53 Sq m

83.82 Cu m

83.82 Cu m

83.82 Cu m

83.82 Cu m

335.28 Cu m

1

4.32

3.42

0.10

2 times of Ground Floor

= 2x1.3…………………..

Same as Ground Floor…..

Same as Ground Floor…..

Same as Ground Floor…..

2 times of Ground Floor

= 2x3.98…………………

Same as 1st Floor………...

Same as 1st Floor………...

Same as 1st Floor………...

Same as Ground Floor…..

Same as Ground Floor…..

Same as Ground Floor…..

Same as Ground Floor…..

1

23.93

96.83

Total

-

2 times as brickwork in

Ground Floor = 2x41.91

Same as 1st Floor………...

Same as 1st Floor………...

Same as 1st Floor………..

Total

Page 87: Apartment building construction project report

75

It

e

m

N

o.

Description of Item N

o Dimensions in

metre

Quantity Remarks

Lengt

h

(metre

)

Bread

th

(metr

e)

Heigh

t

(metr

e)

4

5

6

7

Half brickwork of

10cm thick

For 1st Floor……….

For 2nd

Floor……….

For 3rd

Floor……….

For 4th

Floor……….

SUB-HEAD III.

STEELWORK.

Tor steel

reinforcement

(a) Column @1.2%

of concrete…………

(b) Beams @1% of

concrete……………

(c) Slab @0.8% of

concrete……………

(d) Lintel @0.6% of

concrete…………..

(e) Balcony @0.8%

of concrete………..

(f) Staircase @0.8%

of concrete…………

Skylight:

(a) Adjacent to

staircase & Lift ……

(b) Adjacent to

Kitchen ……………

Elevator (Lift) Car

inside ……………...

2 times as Ground Floor

= 2x36.14 ……………….

Same as 1st Floor………...

Same as 1st Floor………...

Same as 1st Floor………...

Total

72.28 Cu m

72.28 Cu m

72.28 Cu m

72.28 Cu m

289.12Cu m

87.52x

x78.5q ………..

552.96 x

x78.5q ……...

264.68x

x78.5q ………

9.04x

x78.5q …………

31.84x

x78.5q ………..

168.48x

x78.5q ………

Total

82.44q

434.07q

166.22q

4.26q

20.00q

105.81q

812.80 quintals

33.47

7.77

41.24 Sq rm

3.8 Sq rm

2

4

1

4.98

rm

2.26

rm

1.9

rm

3.36

rm

0.86

rm

2 rm

-

-

Total

-

Page 88: Apartment building construction project report

76

3.8.2.4 Abstract of Estimated Cost for Ground Floor

(Note: Rates are as per the Market Price in Nagaland in the year 2016-17.)

Table 3.4 : Abstract of Estimated Cost for Ground Floor.

Item

No.

Description of

Item

Quantity Unit Rate (₹) Unit of

Rate (₹)

Amount (₹)

1

2

3

4

5

6

7

SUB-HEAD I.

EARTHWORK

Surface dressing

and setting

foundation plan

Earth work in

excavation for

foundation and

trenches

Earthwork in

filling in

foundation

trench by loose

earth

Sand Gravel

filling in plinth

level with local

sand

SUB-HEAD II.

CONRETE

WORK Cement concrete

M10 with grade

stone ballast

Cement concrete

M15(1:3:6) RCC

work including

shuttering but

excluding

reinforcement

25cm thick DPC

(1:2:4)

838.68

876.81

175.36

356.35

60.74

572.80

15.90

Sq m

Cu m

Cu m

Cu m

Cu m

Cu m

Sq m

40.00

30.00

20.00

365.00

2480.00

2700.00

83.00

Sq m

Cu m

Cu m

Cu m

Cu m

Cu m

Sq m

33547.00

26304.30

3507.20

130067.00

150635.20

1546560.00

1319.70

Page 89: Apartment building construction project report

77

Item

No.

Description of Item Quantity Unit Rate (₹) Unit of

Rate (₹)

Amount (₹)

8

9

10

11

12

13

14

SUB-HEAD III.

BRICKWORK

1st class brickwork

in cement mortar

(1:6) in foundation

and plinth

1st class brickwork

if 20cm thick

cement mortar (1:6)

in superstructure

wall (20cm)

Brickwork of 10cm

thick in cement

mortar (1:3) with

H.B. wire netting in

every third layer

SUB-HEAD IV.

FLOORING

7.5cm thick

terraced flooring in

lime concrete

(1.5:2:7) over a

brick flat soling

25mm thick

Terrazzo work with

Italian marbles

Supplying, fitting

and fixing

porcelain tiles for

dado for other than

white

SUB-HEAD V.

STEELWORK

Tor Steel

Reinforcement

84.43

41.91

36.14

679.76

227.67

72.19

382.22

Cu m

Cu m

Cu m

Sq m

Sq m

Sq m

Quintal

1810.00

1918.00

846.00

415.00

780.00

245.00

2290.00

Cu m

Cu m

Cu m

Sq m

Sq m

Sq m

Quintal

152818.30

80383.38

30574.44

282100.40

177582.60

17686.55

875436.69

Total Amount of Ground Floor : ₹3508523.71

Page 90: Apartment building construction project report

78

3.8.2.5 Abstract of Estimated Cost for First Floor to Fourth Floor

Table 3.5 : Abstract of Estimated Cost for First Floor to Fourth Floor.

Item

No.

Description of

Item

Quantity Unit Rate (₹) Unit of

Rate (₹)

Amount (₹)

1

2

3

4

5

6

7

SUB-HEAD I.

CONCRETE

WORK

Cement concrete

M15 (1:2:4) for

RCC work

including

shuttering but

excluding

reinforcement

7.5cm thick (av.)

lime terracing on

roof

SUB –HEAD II

BRICKWORK.

1st class brickwork

(1:6) in

superstructure wall

Brickwork of

10cm thick

SUB-HEAD III.

STEELWORK.

Tor steel

reinforcement

Skylight

Elevator (Lift)

(a) Car

inside……..

(b) Lift

mechanical gears

including hoisting

hooks……

1116.00

722.53

335.28

289.12

812.80

41.24

3.8

Cu m

Sq m

Cu m

Cu m

Quintal

Sq rm

Sq rm

2700.00

220.00

1810.00

846.00

2290.40

178.00

25455.00

Cu m

Sq m

Cu m

Cu m

Quintal

Sq rm

Sq rm

3013200.00

158956.60

606856.80

244595.52

1861637.12

7340.12

96729.00

248590.00 For total height of building

Total Amount of First Floor to Fourth Floor : ₹ 6237905.76

Page 91: Apartment building construction project report

79

Total estimated cost of all the floors = (3508523.71 + 6237905.76) = ₹ 9746429.47

Add 10% cost of building for Water Supply & Sanitation = 974642.95

Add 9% cost of building for Electrification = 877178.66

Add 5% cost of building for Contingency on = 487321.00

Add 2.5% cost of building for Work Charged Establishment on = 243660.74

Total : 2582803.83

Estimated cost of the five storeyed building = 9746429.47 + 2582803.83

= ₹ 1,23,29,233.30

= ₹ 1,23,29,230.00 (say)

(Rupees One Crore Twenty Three Lakhs Twenty Nine Thousand Two Hundred

only)

Page 92: Apartment building construction project report

80

CHAPTER 4

4. OVERALL BENEFITS GAINED FROM

INTERNSHIP

Internship is a class healed at site to provide an enhanced understanding of the outside

working environment before the student graduate. The main aim of this practice

(internship) is to teach students communication with different workers or employees,

to improve practical skill what they learned in classrooms, upgrading the theoretical

knowledge in addition to the class, improve their leadership skill, team playing skill

and etc.

In my six months stay in M/s Singh Construction Co., Dimapur, with Environ

Assemblers consultant I have acquire much knowledge in different tasks as explained

below in different section. This different knowledge got me a good performance in the

internship period and I gain experience that helps me after the graduation in the

upcoming working era of mine.

4.1 Overall benefits gained

It is obvious that student learn a lot and gain much when exposed to practical

scenario. Likewise all what I know and learn has got the real practical interpretations.

The engineering course that I have taken in our university is a pillar on my internship

programs. The theoretical knowledge always assists to understand practical situations

easily. Because these course guides for me to

Know construction material

Select construction material

manage construction work

Know working schedules

Upgrade leadership skill.

The site work especially for construction work is more a matter-of-fact than

theoretical but I had known much the theoretical only before the internship program

because of this gap challenges are the beginning point to gain knowledge, or to fit the

Page 93: Apartment building construction project report

81

career goals. This internship program gives me an advantage to face these challenges

and system of implementation of construction work.

4.1.1 Improving practical skills

This type of skill are gained when one person experience the theoretical knowledge in

practices theoretical education may or may not exactly apply on the field as practical

skills.

The aim of the internship is to address more practical knowledge for student. So, I

found a practical knowledge at the site as much possible within the six months. The

knowledge we have learned in the classroom is helpful to get those practical or real

work in the site and totally different from the actual knowledge gained from the class.

Thus I found some knowledge in the site which helps me to work with the site

environment or site peoples.

Some of the practical knowledge I gain from the internship class was:

Construction of formwork and false work for some reinforced concrete

structure. In any construction work the first stage before casting of concrete is

designing and constructing of form work. As I explained in the work

procedure the formwork and false work must be stiff and must resist the fresh

concrete till the concrete gain its strength. Thus the construction stage of form

work was new to me since I‗m new for the practical world now I gain practical

knowledge about how it is worked and erected.

Bar bending, positioning, splicing and tying, according the specified drawing.

After the formwork and false work is ready the bar bending, positioning and

tying work goes next. This work is done based on the working drawing

provided in the working drawings (structural drawing) by the design team of

that specified structure. In most case it was new for me to see such work since

it is a practical work only performed at the site.

Surveying on building construction. We conduct the surveying class in the

field for its lab session of the course in the normal class. But we don‗t know

about how it is going to be in building construction in particular and in which

particular stage of the construction work it used either the super structure or

sub structure.

Page 94: Apartment building construction project report

82

Casting and pouring of reinforced concrete structure and equipment used for

casting. Concrete is a vital material in any construction of reinforced concrete

and is the main constituent or ingredient of any reinforced concrete structure.

Thus it is mandatory to know this material in practice including how it is

treated, placed (poured), mixed and the equipment used for those work. I got

the practical knowledge in terms of those listed aspects of concrete.

Different construction equipment (machines) and their use in construction site.

Many of great structures before are a product of numerous human power and

countless days inspired by great powers. Machines are capable of handling

tough work which may be beyond the scope of human labor to be performed.

They can be expected to work with fair degree of effectiveness even under

adverse weather, climate or topographical conditions. I generally know how

equipment‗s are used in the site including their specific purpose.

4.1.2 Upgrading the theoretical knowledge

The internship class is not only depending on the practical aspect but it also help

students to upgrade or increase knowledge on already that they have. I try to integrate

the practical knowledge with that of the theory learned in the class in different place

in order to get more knowledge than the theory we learned on the class. I got the

internship class very interesting in terms of upgrading a theoretical knowledge and I

learned from the site some theories that we haven‗t learn in the class room by

searching different related literature. Some of those are:

Gain how concrete could be produced and used.

Visualizing structural and architectural drawings

Improving which type of construction material should be use

Increasing awareness about the department course.

Quantity surveying

Structural design of shear wall and its advantage

Construction equipment

Report writing

I learned those things in exclusive cause it is hard to read and understand everything

from books and asking some peoples at site to those things ashamed me. Generally I

Page 95: Apartment building construction project report

83

change myself alit bit after the internship period in my knowledge than before I took

it.

4.1.3 Upgrading personal communication skill

Communication is sharing or exchanging information or ideas with others in order to

get some messages and knowledge. The communications systems within the building

design and construction enterprise has taken on a large role in the achievement of

profitability and efficiency. A basic understanding of communication systems is

beneficial to all building professionals and trades, as they all play a part in the success

of the construction. Construction is one of the places that require a good

communication skill either managing every trade of work or asking what is going on

over there. So, communication is an important way of learning, which can be defined

formally as the act, process, or experience of gaining knowledge or skills and sharing

what we know. Cool communication is important in the real constructions world and

it can appear in different forms as speaking, writing, and listening. In the site the most

things I gain is due to communication with other workers like engineers, skilled and

non-skilled workers, Forman etc. in some place/case it is very difficult to talk workers

and ask them what we want because of that they underestimate us and sometimes

they are not eager to tell. But I improve and know how to communicate with different

classes of workers in the site.

Good communication is the life blood of the engineering profession. Even though, it

takes many forms, such as speaking, writing and listening, it has the following

advantages such as:

handling information,

persuading people and

improving relationships with others

In the construction company, working with any individual peacefully was gained from

interpersonal communication that is asking questions and listening effectively to the

answers in the great way to show respect for their experience and ability.

Finally, to communicate effectively, it is essential to choose the suitable medium.

Selecting the right communication channel is like shopping in the right store. If you

select the wrong store, you will not get the items you want. Similarly, if you select the

wrong communication channel, you will not get the result you want.

Page 96: Apartment building construction project report

84

4.1.4 Improving team work skill

Team work skill for construction work Team works, especially for engineers, involve

in every piece of task and achieving good team work skill is essential for Effective

completion of tasks and increasing productivity. This skill already exists in my

personality in the campus due to different assignment and project works that I work

together with students. But this skill is more than this in the construction site. In the

construction site the work is already a team work and it needs more closeness of

workers to solve problems arise in different aspects, misunderstanding in the drawing

or working methodology and consult every work. We the students at the site also

works together as a team to get more understanding and share ideas. More or less I

improved my team work status by working together with different professionals,

student and workers as a whole in the civil engineering works and consulting.

Even if tasks are done individually by the respective person at different section of the

construction company, there are times at which different individuals come together to

work for common goal of the company for increasing productivity. The most

important point in team playing skill is just reach an agreement from different points

on the work to be done.

Furthermore, to have a common understanding on the task that is to be accomplished,

I have always tried to listen carefully to those individuals with whom I am working.

After listening others idea, I tried to provide an idea which is very constructive for the

task being done.

Team work, especially for engineers, involve in every piece of task. Thus, generally

some qualities of a good team working skill I gained are as follows:

Cooperative and help other

Active participant

listen actively is another essential for teams to function effective

speaking and expressing my thought and ideas clearly, directly, honestly and

with respect for the work of the team

4.1.5 Improving leadership skill

Leadership is the process of influencing individuals or groups to accomplish an

organizational goal or mission. I have seen how each worker is controlled and

organized to perform its day to day activities. Among all other managements I have

Page 97: Apartment building construction project report

85

seen that human resource management is the most important one. I have actually

observed the method of controlling the working time and amount of work done by

each worker so that the work proceeds according to the work plan (schedule).

Leadership is a skill to guide, control and monitor people. For effective leadership I

understood that personal values like confidence, effective communication and

devotion are very important.

In order to be good Leadership the following criteria should be fulfilled.

Those are:-

Be technically proficient (skilled with different knowledge‗s).

Seeking self-improvement.

Seek responsibility and take responsibility for your actions.

Make sound and timely decisions.

Know your people and look out for their well-being.

Keep your workers informed.

Develop a sense of responsibility in your workers.

Ensure that tasks are understood, supervised, and accomplished.

Use the full capabilities of your organization.

Listening to others.

Being organized.

Able to communicate clearly and efficiently.

In the site it was impossible for us to lead anything because we go to the site to learn

about the site work and we didn‗t have enough ability to handle such works in such

short time but we have learned how to become a good leader and the main signal of a

good leader.

Finally, what I take hold of is becoming a leader isn‗t easy because it takes a

conscious commitment and consistent effort to develop one‗s leadership skills. But on

the positive side, anyone who is willing to make the effort can become a good leader.

4.1.6 Understanding work ethics

Ethics defines morality and determines the meaning and rational justification of the

right way to live, correct values as well as correct ways of treating others. As workers

made to specialize in different fields, specific codes of conduct were expected from

Page 98: Apartment building construction project report

86

each worker. In today‘s complex world, Ethical conduct of workers is very important

for developing healthy working environment and increasing productivity.

The concept of work ethics may be summarized as the overall quality in one‗s

behavior towards appreciating the process of work flow and performing rather well on

the job so that this work flow will not be jeopardized in the long run. During my

internship program, I could say that I have managed to do my side of the job

description with a high spirit and enthusiasm so that there was a smooth flow of

activities both in the office and on construction site. Work ethics involve such

characteristics as honesty, responsibility, reliability, accountability and etc.

Punctuality is one of the major issues that could be raised when talking about work

ethics and on my side I tried meet this criteria by attending to my working station in

time so that there will not be any delay on the activities planned for that day. The

behavior that one shows towards his peers and colleagues is also one manifestation of

the concept of work ethics. Personally, I always respected and gave priority the

employers of the company. Elements of work ethics that worth mentioning are:-

punctuality, honesty, reliability, office discipline, corporation and responsibility.

We as a student should follow the rules and regulations set by the company and avoid

complaining any work load, activity or assignment that may arise on the site or office.

It is a pleasure of supervisors if we have a good work ethics and we are responsible

for any given tasks. Since the aim of internship is to let students know the outside

environment pertinent to their field, which includes of such the above dealt qualities,

I, with great interest, tried to meet my responsibilities and work ethics that I was

supposed to fulfill by my side.

Generally, I can say I have gained the potential benefits by taking the Engineering

Internship Program.

There are two common types of ethics. These are Personal ethics and Work ethics.

Personal ethics: All human beings as rational creatures are expected to exhibit

certain personal principles of ethics. These principles of personal ethics are values

which are expected to be possessed by all individuals in their life, and contribute a lot

for a smooth interaction among individuals and peaceful coexistence of a society.

Principles of personal ethics include:

Page 99: Apartment building construction project report

87

Concern for the well-being of others,

Honesty,

Fairness and

Obeying to the law.

Work Ethics: Work ethics refers to the standards or a set of moral principles for

regulating behaviors of a certain defined profession. In order to consider that an

activity to be a profession, it should be carried out by one who has advanced

education, knowledge, and skills. Thus, for developing healthy working environment

and increase productivity, ethical work conducts are important medium.

The following are some of the common professional ethical principles which are

apply in the construction environment: these are:

Impartiality,

Punctuality

confidentiality

Accountability,

Transparency and openness,

Integrity,

Avoiding probable or apparent conflict of interests,

respecting the work ethics,

combating corruption and

Presenting the report on time.

4.1.7 Entrepreneur skill

Entrepreneurship can be defined as the process of involving the creation of new

enterprises. Entrepreneurship can also be defined as the process of involving the

creation of new enterprises and that the entrepreneur is the founder. He or she is the

person who perceives the market opportunity and then has the motivation, drive and

ability to mobilize resources to meet it. A construction project mainly requires large

human, financial, physical (material and equipment) institutional (management)

resources. Entrepreneurship is special human talent that helps manage those factors of

production such as labor machinery and capital and takes risks of making loses. An

entrepreneur is required to establish meaningful relationship between activity and

authority which is intimately related to planning function. This type of skill is a

Page 100: Apartment building construction project report

88

capacity to create your own share company with other. In our site the contractors or

the consultant are a good example or a role model for me to become an entrepreneur

and work my own bossiness rather working in organization as employed. But to

become an entrepreneur especially in our country takes a time to know the business

well and a capacity to work such work need more money that we already have before.

Meanwhile, I got some advantages regarding the entrepreneurship skill and I have a

dream and motivation to become one of the greatest entrepreneurs in our country in

the upcoming years in the construction industry or any other working areas as a

whole.

The major characteristics of entrepreneurs that I have observed in the construction

place include the following:

Self-confident multi-skilled

Innovative skills

Results-orientated

A risk-taker

Total commitment

Self-Motivated

Communication skills

Management skills

Ability to work independently and as part of team work

Page 101: Apartment building construction project report

89

CHAPTER 5

5. CONCLUSION AND RECOMMENDATION

5.1 Conclusion

The internship is a bridge between the theoretical knowledge and the practical or the

reality work at the field of construction or civil engineering work. We all who take the

internship class go to companies that already working either as a consultant or a

contractor. The responsibilities of the hosting company are to teach students and

shape them in the six months as real site workers. My hosting company was a

consultant and construction team and they helped me take the internship session in

their company in acquiring different knowledge in different positions. They

collaborate with the contractors to teach us in that section and they believe that the

civil engineering work is more important for us than the consulting office.

This program played an important role to break the conventional thought that field

works can be only implemented by students who hold a degree or people who have an

experience in building construction. We were able to acquire a high level of

confidence to deal with problems that arise in a building construction.

Since I took my internship session in the consulting and construction side M/S

SINGH CONSTRUCTION CO. I got opportunity to work in the different party of the

construction work which helped me to gain more knowledge by seeing what they

work in their own office and what are their main responsibilities to the client and also

each other.

M/S SINGH CONSTRUCTION CO. is general a construction cum consultancy

company in Dimapur, Nagaland, with state-wide projects and operate in the fields of

road, bridge, building construction and infrastructure development. Behind every

company‘s construction project, there is a strong commitment and promise of a

dedicated management and professional team that strive to meet the highest level of

quality construction. Since I was working with the side of this construction company,

I have understand

The overall organization of the company and the work flow

The tasks of the engineers and other employees.

Page 102: Apartment building construction project report

90

The challenges of the works that will face the engineers and their solutions.

Management of human resource and the overall site and project activity.

More over working with skilled and experienced engineers and foreman gives me

great quality and made confidential.

Working with a consultant team gets me more knowledge than that of the contractor

in case that the consultation work includes the duty of the site engineers and in the

consultant office there are different office that are more important for me to upgrade

my knowledge in different aspects of work. The consultant team by its nature includes

designer team including structural engineers, architects, sanitary, electrical and

mechanical engineers, the contract administration and supervision team includes site

coordinators, supervisors and quantity workers and the financial office. This helps me

to get more knowledge than the contractors.

From the design team especially from the structural designers I got some clues about

how to design and the phases and different procedure in the designing of any structure

starting from the roof to the footing. The architects also helped me to know every

symbols used in any drawing and room orientations, how each room of the specified

space can be together without being disturbed by one another. In the sanitary and

electrical engineers also help us by teaching us about the riser diagram and

installation of each junction in place for a building.

They help me to understand what is going to be when I work in the consultant office.

The contractors also avail practical knowledge for us to improve our practical

knowledge status in the field. And also the contractors make us more familiar with

site works starting from communication skill, handling of different site works

equipment utilization manpower control to finishing of the work within the time

scheduled by the client.

However, this internship program was not free from challenges. The most challenge

was the amount of money allocated to the project was insufficient to handle all the

expense of the students during the internship experience and shortage of resource for

student like computer, class rooms for student only and any other problem exist. But

they come up with the challenges and teach us how we must gown to be in the field

after the graduation.

Page 103: Apartment building construction project report

91

The most interesting part of my internship program was that the atmosphere I was

doing was suitable. The hugeness of the project, the enrichment of the company with

machineries, equipment and man power, experienced engineers and other situations

has lead me to be confidential, well experienced and skilled. Some of the benefits that

I gain due to internship program are:

Practical skills

Upgrading of theoretical knowledge and able to use it for practical work.

Developing of communication skill.

Developing skill of team work.

Improving personal ethics and knowing work ethics.

Being able to do different tasks.

Overall the internship program laid sound foundation for us to start our career. We are

proud to be able to contribute towards nation building during the country's extremely

critical period of the history. It will be definitely sensible to scale this practice up and

to replicate in other disciplines as well.

5.2 Recommendations

5.2.1 Recommendation to the hosting company

Most works in the site needs careful attention and successive supervision of works but

the in some case the site works goes improperly due to different causes. This kind of

carelessness is not good for ether the consultant or the contractor. Therefore I suggest

supervisors and site engineers to take a care full look after the work executed on the

site and the work that will be executed.

In the site there are works which are performed in the way that were not to be

performed. Such works leads to safety problem, loose of human power if its degree is

high and economy if it is ordered to demolish it.

Thus I recommend for the company the following:

Testing of material before it delivered to the site and after it delivered and also

when it is in use for construction.

It is better to use steel form work than wood (plywood) formwork as it is very

repetitively used, stiff, not flammable easily and removed easily without damaging

the concrete structure.

Page 104: Apartment building construction project report

92

Use thicker eucalyptus false work in order to avoid the bulging of concrete

The mixing is very local and it must be mixed using mixing plant and the

proportion must be redesigned by using laboratory tests since the project is very huge

and is constructed a high raised building.

Bar staggering around support also need a special attention or re designing

because of that it hard to compact using vibrator through it.

The soil blended at the site must be as it is specified in the laboratory result

and the equipment used for blinding must be effective in the mixing process.

Compacting of the soil more than 20cm in pit and other excavation is

improper and it doesn‗t full fill the needed density. So, compaction must be in each

20cm layer as specified.

A cover material could be used for curing for any casted concrete structure

until it attains its strength.

Formwork should remove easily without damaging the concrete surface.

Addition of water for concrete casting should be known not by guessing.

Exaggerated design of some structural part of the building also uneconomical

and must be studied its requirement before provide it.

Use modern machinery or equipment for high productivity and to finish works

on time.

At the casting of column opening must be prepared at 1.50m for the columns

which are above 2.5m height.

Curing to be done properly.

After casting concrete of a column its formwork should be removed after 24

hours, but in our site they remove the column within 12-14 hours.

Ignoring the student suggestion is also a problem in the site which is

unreasonable and illogical. The sources of this kind of ignorance mainly arise from

under estimating of the student it must also avoid unless and otherwise it has a reason.

Safety work around the site

Human life is irreplaceable, which is susceptible of minor infections. Now days it has

become common to hear accidents on the construction industry. The more the

accidents are becoming redundant the responsibility of the contractors and the

attention to give to safety of the workers is progressing to be paramount. Therefore, it

cannot be denied to work on increasing the safety condition of the site. The most

Page 105: Apartment building construction project report

93

effective way of avoiding risks is the preventive strategy. As the health professionals

use to say ―prevention is better than cure‖, it is more than reasonable to be abide by

such motto. Less concerned safety rule, regulation and training are among the

problem in the site.

Safety of all working staffs and visitors should be observed to a highest care.

Infliction of injury shall be minimized. For this prior readiness is very important. The

safety management will be carried out with a special superintendent to be assigned on

site. The superintendent will be assisted with a dresser to be employed for the site.

Safety of the workers and visitors will be managed in the following strategies;

Preventive Strategy: Success would only be possible if there are workers, who can

give their potential output without fear of any unforeseen risks. While they are

striving to achieve the targeted result, they may not be focused on their safety matters.

This has to be taken care of by others, devoted for the same purpose. The preventive

strategy involves the following elements:

Orientation: - All working and visiting people must be oriented about safety and the

care they have to take once they are within the territory of construction. Falls from

scaffoldings, suspended slabs, roofs, ladders, lift holes, stairs, pits and the like are the

potential risks that the workers should be aware of. Orientation must include on how

to work with machines and equipment, the possible accident they may inflict and what

rules and procedures they have to follow when working with.

Signage: - Important signs that could remind people who are moving within the

working location should be situated in a place where everybody can see or look.

Firm Temporary Works: - All temporary works like scaffoldings and ladders should

be made strong, so that they are able to withstand the possible load to come upon

them.

Temporary guards: Temporary guard rails should be made in places where there are

open spaces where a person might fall down.

Lighting: - Appropriate lighting must be delivered, if there need to work on the night

times.

Page 106: Apartment building construction project report

94

Helmets: - Wearing of helmets must be mandatory for some staffs, supervisors and

visitors as mentioned on the contract document. Such should be made ready available

on site, with the appropriate coloring.

Accident Administration

After involving the above stated methods of prevention of accident, there could arise

different disastrous calamities within the project, which necessitate the application of

most serious and acute acting administration.

First Aid: - A dresser, who has relevant professional background will be assigned on

site for any possible first aid.

Secondary Treatment: Some accidents may require secondary treatment as a result

of infliction serious injury.

5.2.2 Recommendation to the University

The student goes to the internship class are owned by the university and are given to

the companies that use or teach us throughout the six months. So, before and after we

go to the companies the University must fulfill the following:

Evaluating and supervising student as they are in the site by sending mentors

on time.

Giving courses that are appropriate for the site work before the internship class

is commenced like report writing, quantity survey etc.

Organizing students those reside in the same place to create a team playing

skill and provide group working environment in order to share ideas.

Working with the companies closely to address more knowledge to the

student.

Mostly those listed problem challenges the student at site and if the university can

erase these challenges the intern student can do every work without being stressed and

worries. I would like to thank the Mewar University, Rajasthan, for introducing the

six months internship in our course of engineering, which most of the universities do

not offer. This internship was a bridge between the theoretical knowledge and the

practical or the reality work at the field of construction or civil engineering work.

Page 107: Apartment building construction project report

95

REFERENCE

1. B.N. Dutta, “Estimating And Costing In Civil Engineering Theory And Practice

Including Specifications And Valuations”, Twenty-Sixth Revised Edition, 2007.

2. Dr. B.C. Punmia, Er. Ashok Kumar Jain, Dr. Arun K. Jain, “R.C.C. Designs

(Reinforced Concrete Structures)”, Tenth Edition, 2006.

3. Dr. K.R. Arora, ―Soil Mechanics and Foundation Engineering‖, Seventh Edition,

2015.

4. IS: 456-2000, ―Indian Standard Plain and Reinforced Concrete - Code of practice

(Fourth Revision)”, July 2000.

5. M. Chakraborti, “Estimating, Costing, Specification & Valuation In Civil

Engineering”, Fourteenth Edition, 2007.

6. P.N. Khanna, ―Indian Practical Civil Engineers’ Handbook”, Engineers‘

Publishers, New Delhi, 2008.

7. S. Ramamrutham, R. Narayan, “Theory of Structures”, New Ninth Revised and

Enlarged Edition, 2014.

8. Shashi Bhushan Suman, “Design of Concrete Structures”, Third Edition, 2015.

9. www.scholar.google.com

10. www.wikipedia.com

Page 108: Apartment building construction project report

96

APPENDIX

γc partial safety factor for concrete

γs partial safety factor for steel

C-5 concrete that have 5 MPa compressive strength

C–20 concrete that have 20 MPa compressive strength

fck characteristic compressive strength of concrete

fcd design compressive strength of concrete

ft. feet

m metre

q quintal

rm running metre

Sq ft square feet

Sq rm square running metre

Sq m square metre