All about Construction Cash Allowances

Version 1.2

Page 2: All About Construction Cash Allowances v1.2

By Peter Vander Klippe

Page 3: All About Construction Cash Allowances v1.2

What is a Construction Cash Allowance?

Page 4: All About Construction Cash Allowances v1.2

Cash Allowances are funds set aside for work that will be detailed later

Page 5: All About Construction Cash Allowances v1.2

Why should you care?

Page 6: All About Construction Cash Allowances v1.2

Why care #1: Cash Allowances are part of most CCDC* contracts

Page 7: All About Construction Cash Allowances v1.2

*CCDC = Canadian Construction Documents

Committee

Page 8: All About Construction Cash Allowances v1.2

*Almost every construction contract in Canada is based on a

CCDC contract

Page 9: All About Construction Cash Allowances v1.2

Why care #2: They allow you to tender sooner

Page 10: All About Construction Cash Allowances v1.2

Example: A retail project that was part of a larger

program

Page 11: All About Construction Cash Allowances v1.2

The client was bundling the refrigeration

installation

Page 12: All About Construction Cash Allowances v1.2

(So that they could get the best price)

Page 13: All About Construction Cash Allowances v1.2

But they needed to get started on the

construction ASAP

Page 14: All About Construction Cash Allowances v1.2

So they included a refrigeration installation

Cash Allowance

Page 15: All About Construction Cash Allowances v1.2

The amount was estimated based upon

previous costs

Page 16: All About Construction Cash Allowances v1.2

After they received the pricing on the

refrigeration installation bundles

Page 17: All About Construction Cash Allowances v1.2

The work was assigned to the contractor

Page 18: All About Construction Cash Allowances v1.2

With no additional mark up for overhead or profit*

Page 19: All About Construction Cash Allowances v1.2

*this won’t work if your estimate is too low

Page 20: All About Construction Cash Allowances v1.2

Work started on site sooner then if we had to wait for the final price

Page 21: All About Construction Cash Allowances v1.2

Why care #3: They provide flexibility

Page 22: All About Construction Cash Allowances v1.2

You can use Cash Allowances to be more

flexible

Page 23: All About Construction Cash Allowances v1.2

This works best for scope near the end of the

project

Page 24: All About Construction Cash Allowances v1.2

Like landscaping, furniture, and security.

Page 25: All About Construction Cash Allowances v1.2

You can defer some decisions to later in the

process

Page 26: All About Construction Cash Allowances v1.2

So if a deal is found on used furniture you can sod instead of seed the

lawn

Page 27: All About Construction Cash Allowances v1.2

Or if you decide to use keys instead of swipe cards you can afford a

patio

Page 28: All About Construction Cash Allowances v1.2

Or if you exceed your budget you can use some

of the Cash Allowance

Page 29: All About Construction Cash Allowances v1.2

No patio or Sod

Page 30: All About Construction Cash Allowances v1.2

Staying within your

budget

Page 31: All About Construction Cash Allowances v1.2

Things to watch out for when using Cash

Allowances

Page 32: All About Construction Cash Allowances v1.2

Watch out for multiple specific Cash Allowances

Page 33: All About Construction Cash Allowances v1.2

This can limit your flexibility and run against

approval thresholds

Page 34: All About Construction Cash Allowances v1.2

Example:

Page 35: All About Construction Cash Allowances v1.2

You have three Cash Allowances

Page 36: All About Construction Cash Allowances v1.2

$10,000 for security

Page 37: All About Construction Cash Allowances v1.2

$50,000 for landscaping

Page 38: All About Construction Cash Allowances v1.2

And $140,000 for refrigeration installation

Page 39: All About Construction Cash Allowances v1.2

For a total of $200,000

Page 40: All About Construction Cash Allowances v1.2

Contract is awarded, contractor starts work

Page 41: All About Construction Cash Allowances v1.2

And it turns out that it is going to take a lot more

security work

Page 42: All About Construction Cash Allowances v1.2

To connect this system to the client’s other buildings requires

upgrading the existing system

Page 43: All About Construction Cash Allowances v1.2

The new security estimate is $25,000

Page 44: All About Construction Cash Allowances v1.2
Page 45: All About Construction Cash Allowances v1.2

But, thankfully concurrent to this,

Page 46: All About Construction Cash Allowances v1.2

The pricing came in for the refrigeration

installation

Page 47: All About Construction Cash Allowances v1.2

And the layout was revised, reducing the

number of cases

Page 48: All About Construction Cash Allowances v1.2

Which reduced the refrigeration installation

to $125,000

Page 49: All About Construction Cash Allowances v1.2
Page 50: All About Construction Cash Allowances v1.2

So now we have:

Page 51: All About Construction Cash Allowances v1.2

$25,000 for security

Page 52: All About Construction Cash Allowances v1.2

The same $50,000 for landscaping

Page 53: All About Construction Cash Allowances v1.2

And $125,000 for refrigeration installation

Page 54: All About Construction Cash Allowances v1.2

For a grand total of $200,000

Page 55: All About Construction Cash Allowances v1.2

BUT

Page 56: All About Construction Cash Allowances v1.2

When you tell your contractor about this

Page 57: All About Construction Cash Allowances v1.2

He demands $2,250 extra in overhead and profit

Page 58: All About Construction Cash Allowances v1.2
Page 59: All About Construction Cash Allowances v1.2

He says that managing a security company is a lot

more work

Page 60: All About Construction Cash Allowances v1.2

So he included a 20% markup in his bid for the security Cash Allowance

Page 61: All About Construction Cash Allowances v1.2

And only a 5% markup for the refrigeration installation Cash

Allowance

Page 62: All About Construction Cash Allowances v1.2

So because we are shifting $15,000 from 5% to 20% markup, he wants

his cut

Page 63: All About Construction Cash Allowances v1.2

And to make it worse

Page 64: All About Construction Cash Allowances v1.2

Your client lets you know that as the security costs

has risen by 150%

Page 65: All About Construction Cash Allowances v1.2

He needs his CEO to sign off on the change

Page 66: All About Construction Cash Allowances v1.2
Page 67: All About Construction Cash Allowances v1.2

This could all be avoided

Page 68: All About Construction Cash Allowances v1.2

Make sure it is clear that there is only one Cash

Allowance

Page 69: All About Construction Cash Allowances v1.2

Watch out for hidden Cash Allowances

Page 70: All About Construction Cash Allowances v1.2

It can get complicated if Cash Allowances are not

clearly identified

Page 71: All About Construction Cash Allowances v1.2

Example

Page 72: All About Construction Cash Allowances v1.2

The mechanical sub-consultant ran out of time

prior to tender

Page 73: All About Construction Cash Allowances v1.2

And instead of designing the reverse osmosis

system

Page 74: All About Construction Cash Allowances v1.2

A drawing note was included that instructed the contractor to carry a $15,000 Cash Allowance

Page 75: All About Construction Cash Allowances v1.2

Possible outcome #1: Waste of funds

Page 76: All About Construction Cash Allowances v1.2

2 bids are disqualified as they didn’t include this

Cash Allowance

Page 77: All About Construction Cash Allowances v1.2

One of these bids that was $45,000 lower then the awarded contractor

Page 78: All About Construction Cash Allowances v1.2
Page 79: All About Construction Cash Allowances v1.2

Possible outcome #2: Contractor claim

Page 80: All About Construction Cash Allowances v1.2

The contractor awarded the job missed this Cash Allowance in his estimate

Page 81: All About Construction Cash Allowances v1.2

(This often happens as missing something lowers

your price)

Page 82: All About Construction Cash Allowances v1.2

So when the Supplemental Instruction is issued for the reverse

osmosis system

Page 83: All About Construction Cash Allowances v1.2

The contractor submits a claim for the work at

$17,345 + 10% markup

Page 84: All About Construction Cash Allowances v1.2
Page 85: All About Construction Cash Allowances v1.2

Possible outcome #3: Double dipping

Page 86: All About Construction Cash Allowances v1.2

The contractor technically did include the cash

allowance in his price

Page 87: All About Construction Cash Allowances v1.2

But do to staffing changes at the

contractor’s company

Page 88: All About Construction Cash Allowances v1.2

The new representative for the contractor submits

the claim anyways

Page 89: All About Construction Cash Allowances v1.2

And the contract administrator isn’t aware

of this Cash Allowance

Page 90: All About Construction Cash Allowances v1.2

So the claim is approved

Page 91: All About Construction Cash Allowances v1.2

The contractor also invoices for 100% of his

base work

Page 92: All About Construction Cash Allowances v1.2

And as the contractors invoice doesn’t itemize

the Cash Allowance

Page 93: All About Construction Cash Allowances v1.2

He is paid for both the Cash Allowance and the

draw

Page 94: All About Construction Cash Allowances v1.2

Which gives the contractor $30,000 for $15,000 worth of work

Page 95: All About Construction Cash Allowances v1.2
Page 96: All About Construction Cash Allowances v1.2

Summary

Page 97: All About Construction Cash Allowances v1.2

Cash Allowances can be extremely useful*

Page 98: All About Construction Cash Allowances v1.2

*if used correctly