31
Case Study: One Jackson Square Philip Murray, PE Karl Rubenacker, PE, SE April 23 RD , 2015 ASCE Structures Congress 2015

2015 Structures Congress - One Jackson Square

Embed Size (px)

Citation preview

Case Study: One Jackson SquarePhilip Murray, PE

Karl Rubenacker, PE, SEApril 23RD, 2015

ASCE Structures Congress 2015

Project Team• Hines• KPF • SLCE• GMS• Flack & Kurtz• RA Consultants• Vollmer• Cerami• Hunter Roberts

ASCE Structures Congress 2015

New Building Information• Luxury Residential

Development• Condominium • ~ 3 dozen Apartments• 56,000 SF Residential• 9,000 SF ground floor

retail• 11 Stories

ASCE Structures Congress 2015

Subway Map

ASCE Structures Congress 2015

Site Background Information• NYC Subway Eighth Ave.

Line 1932• NYC Sells Lot to Private

Developer 1948• Attempt at Development

1980• Parking Lot Until this

Project

ASCE Structures Congress 2015

20’

Site Plan

Site

Subway

ASCE Structures Congress 2015

Allowable Bldg Area

30’

Challenges

• Subway tunnel below two-thirds of site

• MTA substation next door

• >250,000 Riders pass under site each day

ASCE Structures Congress 2015

More Challenges

• Historic Landmark District• Neighboring URM Buildings • Active Community• Straddles 2 Zoning Districts• Six-sided Irregular Lot

ASCE Structures Congress 2015

Solutions• Sensitivity to NYCTA Issues

during design• Care during construction• Structure vertical load

within allowable• No lateral load imposed

on tunnel• Isolation of the building

from Subway Vibration

ASCE Structures Congress 2015

NYC Transit Approval Process

• Multiple meetings w/NYCTA staff• Multiple drawing & calculation

submittals• Adjustments to design• Duration ~ 9 months

ASCE Structures Congress 2015

Subway Protection Measures

• Preconstruction survey• Monitoring during construction• Limitation on equipment• Lateral support during excavation• Limitation on construction

ASCE Structures Congress 2015

Monitoring

• 15 points in tunnel• Twice/week during foundation work• Once/story during superstructure work• 3 months & 6 months after topping

out

ASCE Structures Congress 2015

Typical Floor Plan

ASCE Structures Congress 2015

Shear walls

Subway Roof Plan

ASCE Structures Congress 2015

Subway Structure – Foundation Interaction

ASCE Structures Congress 2015

Subway Structure Analysis

ASCE Structures Congress 2015

Foundation Plan

ASCE Structures Congress 2015

24” Dia Caisson In 30” Dia Sleeve

24” Dia Caisson

Foundation Cross-section

ASCE Structures Congress 2015

Springs

Caissons

Caissons

• 24 inch round caisson, reinforced concrete core

• Socketed into the bedrock• Fixed top & bottom• Approx 40 kip lateral load• Approx 750 kip vertical load• Bedrock ~ 45’ below grade

ASCE Structures Congress 2015

Caissons

ASCE Structures Congress 2015

Isolation Springs and Bearings

ASCE Structures Congress 2015

Isolation Spring

Isolation Lateral Bracing

Isolators

• Spring assembly pads used to isolate the building laterally from the subway tunnel

• Reduces acoustic transmission, for residential viability

• Lateral bearings provide resistance to base shear

ASCE Structures Congress 2015

Column Isolation

ASCE Structures Congress 2015

Spring Assembly Pads

ASCE Structures Congress 2015

Lateral BearingDetail

ASCE Structures Congress 2015

Lateral Bearings

ASCE Structures Congress 2015

Engineering Data

• Building weight ~ 22,000 kip• Seismic base shear ~ 1000 kip (R=3)• Building period ~ 0.9 sec/cycle• Wind base shear ~ 500 kip• Wind base shear ~ 250 kip

ASCE Structures Congress 2015

Superstructure Data

• Concrete flat plate• Irregular column layout• Typically 8” slab thickness• Punching shear reinforcement• Transfer floor 16” thick

ASCE Structures Congress 2015

Construction

ASCE Structures Congress 2015

ASCE Structures Congress 2015

Thank You

ASCE Structures Congress 2015