71
Wellesley High School Project Update for Annual Town Meeting April 2010

Wellesley High School Project

Embed Size (px)

Citation preview

Page 1: Wellesley High School Project

Wellesley High School Project

Update for Annual Town MeetingApril 2010

Page 2: Wellesley High School Project

Summer 2009 Construction of 3 off site parking lots

with porous pavement for WHS staff State Street lot expanded to 31

spaces; 26 for faculty, 5 for Brook path walkers

Tennis court lot expanded to 33 spaces

Basketball courts turned into 60 tandem spaces with 5 single spaces

Page 3: Wellesley High School Project

State Street lot expanded

Page 4: Wellesley High School Project

Summer 2009 cont. Construction of 5 new classrooms in old

school from lecture hall space to handle increased enrollment

Page 5: Wellesley High School Project

Upper part of lecture hall demolished. Steel beams to support new classrooms

Page 6: Wellesley High School Project

Corridor to 5 new classrooms

Page 7: Wellesley High School Project

New classroom

Page 8: Wellesley High School Project

Summer 2009 cont. Construction fence up, scaffolding around edge

of school adjacent to construction fence House at 57 Seaver St. moved across site to

Rice Street location Air filters installed on air intakes of old school Work to bring utilities on site begins

Page 9: Wellesley High School Project

Scaffolding around edge of old school to provide protected corridor

Page 10: Wellesley High School Project

September 2009 Old parking lot cleared (removal of planters,

trees, asphalt) Work continues on sewer and water Official Groundbreaking 9/29/09

Page 11: Wellesley High School Project

Groundbreaking

Page 12: Wellesley High School Project

October 2009

Trailers set up on site Concrete footings work begins Asbestos and lead abatement on 2

remaining Seaver St. houses (#53 & #55)

Continued work on sewer and water

Page 13: Wellesley High School Project

Trailer complex on edge of Rice Street

Page 14: Wellesley High School Project

Site viewed from Rice Street

Page 15: Wellesley High School Project

Seaver Street house-lead abatement before demolition

Page 16: Wellesley High School Project

November 2009

2 Seaver St. houses demolished Concrete footings continue

Page 17: Wellesley High School Project

Concrete Foundation:Formwork is being installed, and reinforcement bars and anchor bolts are being set to pour concrete foundation walls, piers, and footings.

Page 18: Wellesley High School Project

Rebar in place as concrete is poured.

Page 19: Wellesley High School Project

November 2009 cont.

Pile driving begins on 11/9 252 steel H piles vibrated in during

school day and hammered to completion after school

Depth of 40-60 feet Piles in areas A and B, remainder of

building (C and D) has concrete spread footings

Page 20: Wellesley High School Project

Area reference plan of new schoolRice Street

Front offices, gym, locker

rooms

Auditorium, arts, science

wing

2 academic wings

cafeteria, classes above

Page 21: Wellesley High School Project

Equipment on site for pile driving.

Page 22: Wellesley High School Project

H Pile lifted into place

Page 23: Wellesley High School Project

Vibrating pile into place

Page 24: Wellesley High School Project

December 2009

Piles completed with little impact on function of school

Concrete footings continue Begin review of thousands of steel

drawings with architect and Turner

Page 25: Wellesley High School Project

January 2010 Foundation completed including all pile

caps and spread footings Piles excavated to install pile caps Forms placed with rebar for pile caps and spread

footings Concrete poured Cured with heat (as needed due to weather) Waterproofed Insulation installed Backfilled

Page 26: Wellesley High School Project

Piles driven to completed depth.

Page 27: Wellesley High School Project

Pile Caps:Piles are being excavated in order to form pile caps.

Page 28: Wellesley High School Project

Pile Caps:Following excavation, piles are stoned to subgrade before placing forms with rebar and pouring concrete for pile caps.

Page 29: Wellesley High School Project

Concrete Foundation:Concrete is poured into forms with rebar in place.

Page 30: Wellesley High School Project

Forms in place for concrete pour.

Page 31: Wellesley High School Project

Pile Cap

Page 32: Wellesley High School Project

In order for the concrete to cure properly in winter months, heating coils with concrete blankets are set on it.

Here are the heating coils.

Page 33: Wellesley High School Project

Here are the concrete blankets.

Page 34: Wellesley High School Project

Concrete blankets.

Page 35: Wellesley High School Project

Waterproofing:Concrete foundation walls and brick shelves are waterproofed. Procor waterproofing is sprayed on and rigid insulation is set in place.

Page 36: Wellesley High School Project

Spread footing section with waterproofing sprayed on and insulation in place.

Page 37: Wellesley High School Project

Backfilling:Due to the cold weather, it is important to remove the frost layer before backfilling with structural soil/fill.Here is unsuitable frost layer.

Page 38: Wellesley High School Project

Backfilling:Area following backfill with structural soil/fill.

Page 39: Wellesley High School Project

View from Seaver Street side of site.

Page 40: Wellesley High School Project

January cont.

Applied for construction permit Rest of project out to bid

Page 41: Wellesley High School Project

February-March Construction permit issued Crane arrives on site in multiple

pieces, is assembled and inspected by third party

Steel erection begins mid-March starting with Building C, followed by D, B, A

Utility work resumed with better weather in late March

Page 42: Wellesley High School Project

Steel: March-September 2010

2000 tons of structural steel in plan 10,000 individual pieces

Beams & Columns Plates Angles Lintels

Page 43: Wellesley High School Project

Architect rendering of steel structure

Page 44: Wellesley High School Project

Steel erection began 3/12/10

Page 45: Wellesley High School Project

Steel erection in Building C, adjacent to back of old school

Page 46: Wellesley High School Project

Crane in action

Page 47: Wellesley High School Project

View from Seaver Street side of site

Page 48: Wellesley High School Project

Work begins on third floor

Page 49: Wellesley High School Project

View from lecture hall classroom in old school

Page 50: Wellesley High School Project

Looking forward into 2010-12 Installation of metal deck, followed by

concrete Then exterior skin with goal of being

weather tight by early 2011 Building substantially complete by

March 2012 Then commissioning of systems,

move from old school Open for students September, 2012

Page 51: Wellesley High School Project

Additional comments

Project is on time and within budget MSBA closely monitoring project; both

budget and progress of construction GMP (guaranteed maximum price)

signed by PBC in March Outreach continues to neighbors and

parents on progress and impact on school function

Page 52: Wellesley High School Project

View from above

Photos taken by Turner Construction from WHS tower

Page 53: Wellesley High School Project

October 29, 2009

Page 54: Wellesley High School Project
Page 55: Wellesley High School Project
Page 56: Wellesley High School Project

November 14, 2009

Page 57: Wellesley High School Project
Page 58: Wellesley High School Project
Page 59: Wellesley High School Project

December 9, 2009

Page 60: Wellesley High School Project
Page 61: Wellesley High School Project
Page 62: Wellesley High School Project

January 11, 2010

Page 63: Wellesley High School Project
Page 64: Wellesley High School Project
Page 65: Wellesley High School Project

March 16, 2010

Page 66: Wellesley High School Project
Page 67: Wellesley High School Project
Page 68: Wellesley High School Project

March 31, 2010

Page 69: Wellesley High School Project
Page 70: Wellesley High School Project
Page 71: Wellesley High School Project