RIVERS, DEVELOPMENT & PEOPLE - A CASE STUDY OF POLAVARAM DAM 14-15 November, 2011 St Ann’s Generalate, Tarnaka, Hyderabad Bharath Bhushan Mamidi Centre for Action Research & People’s Development

Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Embed Size (px)

DESCRIPTION

Polavaram dam is a classic example of dams designed and implemented only to suit the growing power of contractor politician class in India. This dam threatens to affect around 400,000 people, mostly the indigenous people of Andhra Pradesh, Chhattisgarh, Odisha, and Telangana states. It is challenged by two state governments and several citizen groups and there are many cases pending in Supreme Court of India. There are allegations by memebers of ruling party and opposotion parties of large scale corruption. Tenders for the head works have been cancelled with intervention of State High Court for reasons of irregularities and fraudulent practices of the contractors. The Polavaram project is in violation of The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, which provides for “land for land” in command area for the affected people under irrigation projects and protection to ensure that “all benefits, including the reservation benefits available to the Scheduled Tribes and the Scheduled Castes in the affected area shall continue in the resettlement area”. Government of Andhra Pradesh is implementing this project which is in violation of the National Tribal Policy which states that “any project which displaces more than 50,000 tribal people should not be taken up”. It is an illegal project as it lacks even today the mandatory approvals including- Clearance for revised costs by the Expenditure (Finance) Committee; CEA’s clearance for power component; Approvals from Grama Sabhas in the submergence areas in Odisha and Chhattisgarh states required even in the case of construction of dykes and protection bunds; Approval of Forest Conservation Act for submergence areas in Odisha and Chhattisgarh states (dykes etc including); Techno-Economic clearance from the CWC; CWC approval for dam design and operation schedule; Planning Commission’s approval for revised costs. Unfortunately the Government of India is planning to declare this a national project in the current Parliament sessions (February 2014).

Citation preview

Page 1: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

RIVERS, DEVELOPMENT & PEOPLE - A CASE STUDY OF POLAVARAM DAM

14-15 November, 2011St Ann’s Generalate, Tarnaka, Hyderabad

Bharath Bhushan MamidiCentre for Action Research & People’s Development

Page 2: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Polavaram Dam – Complex problem

Polavaram project is an example of large scale dams leading to conflicts of varied nature

It has adverse implications to several sections

It is entrenched in controversies about its legitimacy and corruption besides inter-state and intra-state conflicts

Governance: Complex issues of large dams that cannot be left to a few contractors, engineers and politicians

Offers an example to explore the role of people in defining development designs of the state governments

There could be diverse views

Page 3: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Polavaram dam – history of tragedy & people’s resistance

Salient features of the dam - Government claims

Varied dimensions of Polavaram Dam- Sources of conflict and concerns

Polavaram dam – options and approaches

Response of varied sections of society

Space for people in development & governance- Areas of concern

Page 4: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Salient features of the dam - Government claims

Benefits Irrigation of 7.20 lakh acres in East Godavari, West Godavari,

Vishakapatnam and Krishna Districts Diversion 80 TMC of Godavari water to Krishna Delta. Water supply of 23.44 TMC for industrial and drinking water purposes in

Vishakapatnam district Generation of 960 MW of Hydro Electric Power Navigation facilities, development of pisciculture and tourism

Losses Submergence of 276 villages in AP alone Displacement of 195,357 people in three states (1991 census). Half of

them are tribals. Average size of household is 4.07 persons Loss of 52,624 ha land (3833 ha forest land including 1740 ha in

Papikonda sanctuary) is lost due to submergence and other works

Page 5: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Polavaram Dam- Sources of conflict and concerns

Scheduled area, R&R in tribal areas Tribal displacement- cultural genocide Threat to Eastern Ghats: forest, wildlife Transparency and people’s consent- EIA Reports and Public

Hearings Whose needs? Project sans benefits- a duplicate project Allegations of corruption How safe is the dam, threat of dam break Violation of law and norms Inter-state & Intra-state conflicts

Page 6: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Scheduled area, R&R in tribal areas

National Tribal Policy states that “any project which displaces more than 50,000 tribal people should not be taken up”. R&R of STs should be in scheduled area

National Policy of 2003 on R&R recommends “to minimize displacement and to identify non-displacing or least displacing alternatives”

R&R Policy 2005 of GoAP stressed “the need to minimize large-scale displacement to the extent possible”

Hon’ble High Court of Orissa dt 22/3/2006 directed that no area situated in the territory of Orissa be submerged

State govts cannot respond to the Polavaram project without approval of Tribal Advisory Council (TAC) for diversion of forest and scheduled area land

Project needs clearance of National Commission for the SCs and STs

TAC in AP on 27/2/2006 has recommended relocation of the STs in schedule area only and the R&R for them shall be land to land

Gram Sabha consent is required as per PESA Act 1996

Page 7: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Tribal displacement- cultural genocide

• Around 3 lakh population in 400 villages of three states

• Predominantly tribal and Dalit population

• Cultural genocide of Koya tribe

• Conflicts and inter-tribal strife is a serious threat in the region that is already burning due to violence in Dandakaranya region

• Tribals of this region are now internally displaced people

Page 8: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Threat to Eastern Ghats: forest, wildlife

Loss of forest is not merely 3833 Ha but thousands of ha due displacement of tribals

Tribals refuse to be relocated and resort to uphill migration -felling 80,000 ha forest

Several villages in Chintur mandal have earmarked pockets of forest area for relocation of their villages

Eastern Ghats faces a disaster –loss to forest cover, wildlife, survival of forest dependent people

Page 9: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Lack of transparency & people’s

consent • Two neighbouring states are not consulted

• People threatened of displacement in 3 states are not informed

• EIA Reports of 1985, 1990, 2005 are not shared with affected people

• Bulky volumes in English for Adivasi people

• EIA reports hiding dam safety reports of NIH

• Manufactured consent, state repression

Page 10: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Project sans benefits- a duplicate project

Chagalnadu LIS 35,000

Torrigedda Pumping Scheme 23,000

Existing Yeleru ayacut 70,000

Tadipudi & Pushkaram LIS ayacut 186,000 + 206,000 acres 392,000

TOTAL EXISTING AYACUT 520,000

Land lost to Polavaram reservoir 120,000

Land lost for excavation of canals 35,000

Land lost to industrialization & urbanization 30,000

LAND LOST DUE TO THE PROJECT 185,000

Proposed Irrigation by Polavaram Project- Notional 720,000

Less : existing ayacut 520,000 acres, and

land lost to the project 185,000 acres

705,000

Net benefits under Polavaram Project 15,000

Page 11: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Misuse of public money- allegations of corruption

Cost of the project : increased from Rs 9072 crores in 2005 to Rs 16000 crores in 2010

Dam full of Corruption – allegations by both ruling and opposition parties. Congress leaders K Keshav Rao, MP and P Shankar Rao Textiles Minister, TDP party demands for enquiries

TDP, TRS demand cancellation of tenders and enquiry

Is the dam value for money

Page 12: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Is the dam a ticking time bomb?

Prof Sivaji Rao, Shri T Hanumantha Rao, and NIH Roorkee reports warn of dam break possibilities

Estimates of NIH indicate that around 4 million lives are at threat due to dam break

EIA Report 2005 did not disclose key information pertaining to dam break analysis

Page 13: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Brazen violation of law & norms – a case of fence eating the crop

Polavaram project lacks key approvals of several Ministries mandatory for undertaking the project

• Clearance for revised costs by the Expenditure (Finance) Committee • Clearance from CEA for power component• Approvals from Grama Sabhas in the submersion areas in Orissa and

Chattisgarh states required even in the case of construction of dykes and protection bunds.

• Approval of Forest Conservation Act for submersion areas in Orissa and Chattisgarh states (dykes etc including)

• Techno-Economic clearance from the CWC• CWC approval for dam design and operation schedule• Approval for revised costs from the Planning Commission• etc

Page 14: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Inter-state conflicts

Inter-state objections because of

Polavaram project is in breach of Bachawat Award, should be re-examined

Design of the dam & its operation schedule is to be decided by CWC in consultation with Orissa & Chhattisgarh

Final order of the Bachawat award says submergence in Cgarh and Odisha should not exceed FRL 150 ft due to all effects including back water effect

Joint surveys regarding submergence, EIA and related studies on wildlife as per AP- Cgarh agreement of 12/6/2006, were not conducted

Consent of Gram Sabha of Schedule V area is required for submergence

No public hearings conducted in Odisha and Chhattisgarh states

30 km long embankments at a cost of Rs 393 crore in Odisha and similar dykes in Cgarh also require land acquisition, Public Hearing, etc

Page 15: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Intra-state conflicts

• Submergence area is predominantly in Telangana region without any benefits of irrigation

• Irrigation benefits to Andhra region

• Coastal Andhra region agitating for national status for the project

• Uttara Andhra leaders demand separate state question to be postponed till completion of Polavaram Dam

Page 16: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Polavaram dam – Options & approaches

Damn the dam- No to dam• Gram Sabha resolution from several villages• Appeals, post card campaign• Protests at Public Hearing, Dharnas against land acquisition

Alternative designs • No displacement alternatives by experts: Shri T

Hanumantha Rao and Shri M Dharma Rao• Central Empowered Committee constituted by the Hon’ble

Supreme Court stressed the need for Second Thought to examine alternative designs (15/11/2006)

Page 17: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Responses of varied sections of society

NGOs, networks: Agitation, awareness, mobilization, Legal battles• Critique, field studies by from mid 80s: CEC, Aranyika, G-BAG,

SAKTI, SAMATA, GRAMYA etc• Networks of NGOs

Political parties• Pro-Polavaram parties- Chiranjeevi of PRP/Cong, Congress party, • Pro-Polavaram but with lesser height – CPM• Pro-Polavaram but anti-corruption- TDP• Anti-Polavaram partly - TRS

State governments (Odisha & Chhattisgarh)- V Schedule, back waters effect, Bachawat award, dykes

Page 18: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Space for people in development & governance- Areas of concern

Water wars- Babli Dam (AP-Maharashtra), Almatti (AP-Karnataka), Cauveri (TN, Karnataka, Kerala), Mullai Periyar (TN-Kerala), etc

What is the role of government of India- CWC, Bachawat Award

Law, development and people: Enforceability of law & awards

How to strengthen people’s resistance against destructive projects

Page 19: Rivers, development & people - Case study of Polavaram dam by Bharath Bhushan Mamidi

Thanks

M Bharath Bhushan,

Centre for Action Research & People’s Development

[email protected]