National Guard Black Belt Training National Guard Black Belt Training UNCLASSIFIED / FOUO UNCLASSIFIED / FOUO Module 45 Quick Changeover

NG BB 45 Quick Change Over

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: NG BB 45 Quick Change Over

National GuardBlack Belt Training

National GuardBlack Belt Training

UNCLASSIFIED / FOUO

UNCLASSIFIED / FOUO

Module 45

Quick Changeover

Page 2: NG BB 45 Quick Change Over

UNCLASSIFIED / FOUO

UNCLASSIFIED / FOUO

2

CPI Roadmap – Improve

Note: Activities and tools vary by project. Lists provided here are not necessarily all-inclusive.

TOOLS

•Brainstorming

•Replenishment Pull/Kanban

•Stocking Strategy

•Process Flow Improvement

•Process Balancing

•Standard Work

•Quick Change Over

•Design of Experiments (DOE)

•Solution Selection Matrix

• ‘To-Be’ Process Mapping

•Poka-Yoke

•6S Visual Mgt

•RIE

ACTIVITIES• Develop Potential Solutions

• Develop Evaluation Criteria

• Select Best Solutions

• Develop Future State Process Map(s)

• Develop Pilot Plan

• Pilot Solution

• Develop Full Scale Action/

Implementation Plan

• Complete Improve Gate

1.Validate the

Problem

4. Determine Root

Cause

3. Set Improvement

Targets

5. Develop Counter-

Measures

6. See Counter-MeasuresThrough

2. IdentifyPerformance

Gaps

7. Confirm Results

& Process

8. StandardizeSuccessfulProcesses

Define Measure Analyze ControlImprove

8-STEP PROCESS

Page 3: NG BB 45 Quick Change Over

UNCLASSIFIED / FOUO

UNCLASSIFIED / FOUO

3

Changeover Definition

The amount of time taken to change

equipment from the Last Good Part of a

process to the First Good Part of the

next process

Clock Time, not Labor Time!

Page 4: NG BB 45 Quick Change Over

UNCLASSIFIED / FOUO

UNCLASSIFIED / FOUO

4

Traditional vs. CPI Thinking

Traditional Thinking Changeovers cause downtime

Changeovers cause poor utilization, defects & scrap

Big Batch Size desirable - “The Bigger, the Better” (less changeovers)

CPI Thinking Quick changeovers decrease downtime

Well designed changeovers decrease waste

Quick changeovers (with small batches) IncreasesFlexibility

Page 5: NG BB 45 Quick Change Over

UNCLASSIFIED / FOUO

UNCLASSIFIED / FOUO

5

Why Quick Changeover?

Shorter Changeover Times

More Frequent Changeovers

Smaller Batch Sizes

Shorter Lead Times

Increased Combat Capability!

Page 6: NG BB 45 Quick Change Over

UNCLASSIFIED / FOUO

UNCLASSIFIED / FOUO

6

Internal vs. External

The first task is to recognize that there

are two essentially different components

of any changeover, Internal Activities

and External Activities.

Page 7: NG BB 45 Quick Change Over

UNCLASSIFIED / FOUO

UNCLASSIFIED / FOUO

7

Changeover Activities

Internal Activities

An activity that must be performed while the machine or process is turned off (no product)

Example – Refuel plane on the ground

External Activities

An activity that can be performed while the machine or process is turned on (producing product)

Example – Refuel plane in the air

Page 8: NG BB 45 Quick Change Over

UNCLASSIFIED / FOUO

UNCLASSIFIED / FOUO

8

Improvement Steps

1. Identify changeover activities and document the process (time each step).

2. Separate Internal activity from External activity

External ExternalInternal

Page 9: NG BB 45 Quick Change Over

UNCLASSIFIED / FOUO

UNCLASSIFIED / FOUO

9

Internal vs. External Quiz

Possible CT Scan Changeover Steps:1. Machine is turned off as scan ends

2. IV is removed from the patient

3. Patient is moved off of scan bed

4. Patient is removed from CT scan room

5. New Patient is identified off of CT scan schedule

6. New Patient is brought into CT scan room

7. Patient identification is verified

8. CT Scan procedure is explained to patient

9. Type of Scan is verified from Physician Orders

10. IV is started on new Patient

11. Patient is placed on CT scan bed

12. CT Scan machine is turned on and scan begins

Adapted from “A Lean Guide to

Transforming Healthcare”, Zidel, 2006

Which are

Internal &

Which should

be External?

Page 10: NG BB 45 Quick Change Over

UNCLASSIFIED / FOUO

UNCLASSIFIED / FOUO

10

Internal vs. External Quiz

Possible CT Scan Changeover Steps:1. Machine is turned off as scan ends

2. IV is removed from the patient

3. Patient is moved off of scan bed

4. Patient is removed from CT scan room

5. New Patient is identified off of CT scan schedule

6. New Patient is brought into CT scan room

7. Patient identification is verified

8. CT Scan procedure is explained to patient

9. Type of Scan is verified from Physician Orders

10. IV is started on new Patient

11. Patient is placed on CT scan bed

12. CT Scan machine is turned on and scan begins

Internal

External

Adapted from “A Lean Guide to

Transforming Healthcare”, Zidel, 2006

Page 11: NG BB 45 Quick Change Over

UNCLASSIFIED / FOUO

UNCLASSIFIED / FOUO

11

Improvement Steps

1. Identify activities and document the process.

2. Separate Internal from External activity

3. Convert Internal to External

Page 12: NG BB 45 Quick Change Over

UNCLASSIFIED / FOUO

UNCLASSIFIED / FOUO

12

Prepare operating conditions prior to changeover

Preheat molds or dies

Prepare Patient or Care-givers

Prepare service materials or providers

Pre-adjust parts

Use intermediary sets

Preset tools

Position dies

Standardize necessary functions

Change the fewest parts possible

Minimize or eliminate adjustments

Converting Internal to External

Page 13: NG BB 45 Quick Change Over

UNCLASSIFIED / FOUO

UNCLASSIFIED / FOUO

13

Improvement Steps

1. Identify activities and document the process.

2. Separate Internal from External activity

3. Convert Internal to External

4. Reduce all remaining activities.

Page 14: NG BB 45 Quick Change Over

UNCLASSIFIED / FOUO

UNCLASSIFIED / FOUO

14

Perform Parallel Operations

Improve Clamping Mechanisms

One turn clamps

One motion methods

Eliminate all adjustments

Numerical Settings vs. “Feel”

Automate activities where appropriate

Reduce All Remaining Activities

Page 15: NG BB 45 Quick Change Over

UNCLASSIFIED / FOUO

UNCLASSIFIED / FOUO

15

Pit Stop Photo

Team with Pre-assigned Tasks Placement Clearly

Defined

Quick Connect &

Disconnect Devices

Tools Properly Positioned Prior

to Arrival

Page 16: NG BB 45 Quick Change Over

UNCLASSIFIED / FOUO

UNCLASSIFIED / FOUO

16

Takeaways

Remember Safety at all times!!!

Change internal to external then reduce all activities

Standards are standards, they are not flexible

Standardize all changeover operations

Page 17: NG BB 45 Quick Change Over

UNCLASSIFIED / FOUO

UNCLASSIFIED / FOUO

17

What other comments or questions