Former NAS Moffett Field Site 25 Remedial Action Update Bryce Bartelma, PG Navy BRAC PMO West August 9, 2012 RAB Meeting

Moffett RAB Site 25 Update

Embed Size (px)

DESCRIPTION

Update on Site 25 stormwater retention pond clean-up by Bryce Bartelma at the August 9, 2012, meeting of the Moffett Restoration Advisory Board.

Citation preview

Page 1: Moffett RAB Site 25 Update

Former NAS Moffett Field

Site 25 Remedial Action Update

Bryce Bartelma, PG

Navy BRAC PMO West

August 9, 2012

RAB Meeting

Page 2: Moffett RAB Site 25 Update

IR Site 25

IR Site 25 encompasses approximately 230 acres and was constructed for useas part of the Moffett Field storm water management system since 1953

2

The Navy is coordinating remedial action activities with NASA as theyprepare to conduct their cleanup activities at Area of Investigation (AOI)-14

AOI-14

Page 3: Moffett RAB Site 25 Update

Remedial Design andRemedial Action Work Plan

• Final Remedial Designand Remedial ActionWork Plan (RD/RAWP)distributed on March 30

• Removal of over 32,500cubic yards of sedimentfrom nearly 32 acres

• Planned excavationdepths of 0.5 – 1.5 feetbelow ground surface

• Restore vegetatedareas with pickleweedand other native grass

3

Page 4: Moffett RAB Site 25 Update

April 2012 Conditions at IR Site 25

4

Page 5: Moffett RAB Site 25 Update

Step 1: Temporarily Re-routeStorm Water & WATS effluent

5

Catch Basin

Storm WaterSettling Vault

Page 6: Moffett RAB Site 25 Update

August 2012 Conditions at IR Site 25

6

Page 7: Moffett RAB Site 25 Update

August 2012 Conditions at IR Site 25

7

Page 8: Moffett RAB Site 25 Update

Step 2: Additional Water Management?

• No immediate plans to coffer dam the site if weather stays dry

• Water table just beneath ground surface

• Working with USFWS to potentially lower water table locally inponds adjacent to site

8

Page 9: Moffett RAB Site 25 Update

Balancing the Water Table

9

Page 10: Moffett RAB Site 25 Update

Biological Observations at Site 25

NESTING

• Alameda Song Sparrow

• Western Harrier

• Mockingbird, marsh wren, bushtit andkilldeer

OBSERVED

• Harvest Mice (unidentified subspecies)

• Deer Mice & Voles

• California Least Tern (in flight)

• Black Rail (vocalizing)

• Fox, jackrabbit, and gopher snake

NOT OBSERVED

• Western Pond Turtle (WPT)

• Western Snowy Plover

• California Clapper Rail 10

Page 11: Moffett RAB Site 25 Update

Biological Protection Measures

11

PROTECTION MEASURES

1. Visually inspect/clear vegetationprior to removal

2. Hand remove pickleweed

3. Silt fencing along access pointsand suitable habitat areas

4. Continuous biologicalmonitoring

5. Coordination with CDFG andUSFWS

Page 12: Moffett RAB Site 25 Update

Sediment Excavations

12

• Planned excavation depths of 0.5 – 1.5feet below ground surface

• Field verification for dig depth

• Grid confirmation sampling

Page 13: Moffett RAB Site 25 Update

Vegetation Restoration

Pickleweed

Salicornia

virginica

Saltgrass

Distichlis

spicata

13

• All vegetation areas removedduring Remedial Action will berestored (excludes EDM andinundated mud flats)

• Two main types of vegetation

• Minimum of two years monitoringand maintenance

• Options for irrigation services andadditional plantings

Page 14: Moffett RAB Site 25 Update

Schedule

• Vegetation Removal Prep

Nearing Completion

• Biological Surveys andSediment Excavations

Ongoing

• Vegetation Restoration

Fall 2012

• Submit Remedial ActionCompletion Report

Spring 2013

14

Page 15: Moffett RAB Site 25 Update

Questions?

15