Trees and Construction Chapter 13 ISA Arborists’ Certification

Study Guide – Domains: Urban Forestry & Protection and Preservation

Mark Grueber, Urban Forester

Page 2: Isa trees and construction   mark

Objectives:Describe how trees can be injured or killed as the direct result of construction damage.

Discuss the importance of arborists’ participation in the planning stages of development if trees are to be a part of the landscape.

Explain the steps that can be taken to preserve trees on a construction site.

Discuss some techniques that can be used to preserve trees when the soil grade must be changed.

Explain the limitations for treatment of trees that have been damaged by construction.

Page 3: Isa trees and construction   mark

Key Terms

The Key Terms as listed in the Arborist’s Certification Study Guide will be defined and highlighted throughout the presentation.

Page 4: Isa trees and construction   mark

“Trees never knew complete removal of trunks, machine compaction of soils, sudden changes in water drainage patterns due to roads, pollution, and disruption of niches for soil organisms…These actions have come suddenly. They are being repeated.” – Alex Shigo, A New Tree Biology

Page 5: Isa trees and construction   mark

Construction Damage to Trees

One of the most common causes of tree death and decline in urban areasPeople want to “live in the trees” but most landowners, developers and builders don’t understand how to take advantage of the opportunity.

Page 6: Isa trees and construction   mark

The Missing Link: Trees are part of the community’s infrastructure

Trees are an important and vital part of a community’s infrastructureWhat do trees require?What do we provide in an urban/ suburban setting?Planning for trees

Page 7: Isa trees and construction   mark

What’s missing?

Page 8: Isa trees and construction   mark

Elements that affect plant growth

What we can’t impactSunlightOxygenCarbon DioxideSoil texture (sand, silt or clay)Temperature

What we can impactAvailable WaterAvailable NutrientsSoil structure (how a soil hangs together)Available space

Page 9: Isa trees and construction   mark

…and a professional arborist or forester to tell them that.

Trees CAN be protected and preserved on construction sitesA professional arborist or forester MUST be involved early – during the planning stage.

Page 10: Isa trees and construction   mark

How are Trees Damaged During Construction?

The most serious damage to trees caused by construction is underground.Root damage and soil disturbance.

Page 11: Isa trees and construction   mark

Roots…a review.

Which is a more accurate representation of a trees root system?Fine absorbing roots are concentrated in the upper few inches of the soil

Page 12: Isa trees and construction   mark

Roots…the real picture

Mark Grueber, Ecological Consulting Services

Mark Grueber, Ecological Consulting ServicesMark Grueber, Ecological Consulting Services

Page 13: Isa trees and construction   mark
Page 14: Isa trees and construction   mark

Root Damage from Construction

Root injury may show decline in a few months or several yearsRemember the mortality spiral?Common symptoms: yellowing or early fall color, watersprouts, dieback of small twigs and eventually major branches

Page 15: Isa trees and construction   mark

Construction Damage - Physical Injury to Trunk and Crown

Damage to vascular tissuesBut trees heal…don’t they?Mortality spiral…again!

Note the “tree protection fencing”

Page 16: Isa trees and construction   mark

Construction Damage - Cutting of Roots

Digging and trenching [digging to install utilities; of concern due to root damage] will likely sever rootsUsually due to misunderstanding of root growth habit (1-3x branch spread)Amount of damage depends on proximity to trunk and area of root development

Page 17: Isa trees and construction   mark

Cutting of Roots - continued

Severing 1 root can remove 15 to 25% of root systemRoot loss may increase potential for tree failure

Page 18: Isa trees and construction   mark

Construction Damage – Soil Compaction

[Compression of the soil resulting in a reduction of the total pore space, especially the macropores]Ideal soil has 50% pore space – filled with H20 and airO2 is reduced; CO2 and other gases increaseRoot growth is diminished; absorption reduced

Page 19: Isa trees and construction   mark

Construction Damage – Added Soil

90% of fine roots that absorb water and minerals are in the upper few inches of soil…got it???Additional soil – even a few inches – can dramatically alter the infiltration of water and oxygen; fine roots die within 30 minutesAltering the drainage pattern may also cause significant issues

Page 20: Isa trees and construction   mark

Construction Damage – Exposure

Trees grow in communities with other trees and/or non-turf type plantsTypes of injury: sunscald, improper taper, aforementioned root and soil issuesIt all comes back to understanding the biology of trees and “forests”

Page 21: Isa trees and construction   mark

Are there alternatives?

Tree Protection Planning and PreservationPlanting site improvements

SoilRooting space

Conservation development – preserving a portion of trees (not on exam!)

Page 22: Isa trees and construction   mark

Planning and Preservation

Tree protection planning cannot wait until constructionMust involve a professional arborist or forester who can communicate with developers and buildersArborist must be involved from beginning to end

Page 23: Isa trees and construction   mark

Considerations of Tree Protection Planning

Don’t try to save every tree!Species, size, location and conditionDon’t save a hazardYounger trees may survive the stress

Page 24: Isa trees and construction   mark

Tree Protection Planning

Arborist – evaluates, selects and maps treesLandscape Architect – assists with plan preparation to consider other parts of infrastructureDon’t just consider the trees – remember it’s an ecosystem!

Tree Number Species

Diameter (in) PROTECT?

Root Pruning Comments

1 Sweetgum 18 YES Install fence as shown

2 Sweetgum 18 YES YESRoot prune along edge of proposed driveway. Install fence as shown.

3 Sweetgum 16 YES Install fence as shown4 Gingko 18 YES Install fence as shown

5 Walnut 14 YES YESRoot prune along limit of disturbance line (or remove tree).

6 Walnut 16 YES Woodland tree within protected area7 Black Cherry 14 NO To be removed8 White Oak 14 YES Woodland tree within protected area9 Black Cherry 12 NO To be removed

10 Green Ash 18 YES YESRoot prune along limit of disturbance line (or remove tree).

TREE PROTECTION ACTION KEY (for trees >12")

Page 25: Isa trees and construction   mark

Tree Protection Planning

Consider design changes or construction procedure modifications to accommodate treesTunneling [alternative means to trenching for installation of underground utilities] instead of trenching is one of the most common

Page 26: Isa trees and construction   mark

Specifications

[detailed plans and statements of particular procedures and standards]All tree protection MUST be written into construction specificationsAll contractors (and subs!) must be made aware of these specsConsider fines (or incentives) using tree and landscape valuation methodology

Page 27: Isa trees and construction   mark

Construction Damage Avoidance

Barriers [fences or other means to establish a protection zone around trees on construction sites]Place as far away from tree as possible…or a minimum of 1’/1” dbhNo traffic or storage of building materials, waste or excess soilNO DISTURBANCE!

Page 28: Isa trees and construction   mark

Avoidance - Limit Access

Limit access to one route [means of entering and leaving a property during a construction operation] on and off property – but be realistic! Remember parking.Specify areas for storage of equipment, soil, building materials; as well as areas for burning, washout, etc.

Page 29: Isa trees and construction   mark

Avoidance – Compaction Reduction

Build a “mulch road” - six to twelve inches of wood chips.Must be CAREFULLY removed or reusedPlywood sheets

Page 30: Isa trees and construction   mark

Avoidance – Grade Changes

Terracing [method used to lower the soil grade in stages]Maintain original grade as far from tree as possibleMust be accompanied by root pruning and care where roots are exposed

Page 31: Isa trees and construction   mark

Avoidance – Grade Changes continued

Tree Island [soil or landscape surrounding a tree, such as within a paved area]Similar to terracingExcellent for retaining small groves

Page 32: Isa trees and construction   mark

Avoidance – Grade Changes continued

Aeration systems [the set of holes or trenches created in a tree’s root area to improve oxygen availability to the roots]Tree wells [wall constructed around a tree when the soil grade is raised to maintain the original soil level and provide oxygen to the root zone]Lack of supporting researchGravel or stone below fill does NOT improve water or oxygen flowConsider tree size, species, drainage patterns, soil conditions, fill depth, irrigation and future maintenance

Page 33: Isa trees and construction   mark

Avoidance – Good Communication

The arborist must be involved during all phases of buildingTake good notes and photosThis is where projects usually go wrong

Page 34: Isa trees and construction   mark

“We only took the fencing down for a moment.”

A tree protection plan without monitoring by an arborist is a waste of resourcesVery few projects result in good tree protectionPlan for post-construction tree maintenance

Page 35: Isa trees and construction   mark

Treatment of Construction Damaged Trees

Periodic inspection and monitoring (post-construction) is a mustA little turf can hide a hazardSafety first..but beware of unscrupulous contractors

Page 36: Isa trees and construction   mark

Construction Damage Treatments - Pruning

Remove only broken, damaged, or diseased limbsDuring construction limbs may have to be pruned for equipment clearanceDO NOT thin the canopy to “compensate” for root loss – why?

Page 37: Isa trees and construction   mark

Construction Damage Treatments – Cabling & Bracing

Some trees can be preserved with remedial treatmentsCables must be inspect periodicallyInherent liability for the arborist

Page 38: Isa trees and construction   mark

Construction Damage Treatments – Wound Repair

Wounding is common on construction sitesNo wound dressings and STOP telling people it will “heal!”Bark tracing [cutting away torn or injured bark to leave a smooth edge

Page 39: Isa trees and construction   mark

Construction Damage Treatment – Irrigation and Drainage

Maintain adequate but not excessive moistureMonitor for changes in drainage patternsMost irrigation systems are inadequate and cause more harm than benefit

Page 40: Isa trees and construction   mark

Construction Damage Treatments – Mulching

Inexpensive and very beneficial when applied properlyUse chipped bark, wood, or pine needles if possible – why?Mulch as much of the root width as practical for the landscapeNo volcanoes!

Page 41: Isa trees and construction   mark

Construction Damage Treatments – Aeration (Vertical Mulching)

[filling vertical drilled holes in the soil with materials such as gravel, perlite, peat or sand]Drill holes 2-4” in diameter; 1-3’ on centerDrill holes to a 12” depth unless fill has been placed over the root system

Page 42: Isa trees and construction   mark

Construction Damage Treatments – Aeration (radial trenching)

[means of aerating the soil in the root zone of a tree by removing and replacing soil in a spoke-like pattern]Air excavator [device that blows air at high force; used to remove soil from the root zone of trees]Mechanical trenchers should not operate within 4-8’ of trunkTrench at least to dripline; 1’ depth

Page 43: Isa trees and construction   mark

Construction Damage Treatments – Fertilizer? or “Let’s Feed that

Sucker!”AGH!!! (pet peeve – this is where I go off for a while, sorry)Why is this not a good idea?If used ISA recommends a slow release to minimize risk of root injury

Page 44: Isa trees and construction   mark

One More Time!

Monitor, monitor, monitor.Use your knowledge of tree biology and the site conditions to guide youObviously, this should be done by a professional…not this guy

Page 45: Isa trees and construction   mark

It’s Quiz Time!

Name 5 ways that trees can be adversely affected by construction:

1. Root injury2. Soil compaction3. Injury to trunk or

branches4. Grade change5. Excavation/

severing root system

Page 46: Isa trees and construction   mark

When soil is compacted, the ______ _______ between soil particles is reduced.

pore space

Page 47: Isa trees and construction   mark

Two detrimental effects of soil compaction are:

SuffocationRestriction of growth

Page 48: Isa trees and construction   mark

A technique used to reduce soil compaction around trees on a construction site is to spread a temporary, thick layer of _______.

Mulch

Page 49: Isa trees and construction   mark

The overriding objective of an arborist involved in a development project is to save every tree on the site (true/false).

False…but aren’t they cute?

Page 50: Isa trees and construction   mark

It is better to tunnel directly under a tree than to cut directly across the root system of a tree when excavating for utility lines (true/false).

Duh.

Page 51: Isa trees and construction   mark

An important action that should be taken at the start of a construction project is to erect _______ around all of the trees that are to remain.

Protective fencing or barriers

Page 52: Isa trees and construction   mark

Carefully cutting away loose, damaged bark is called _______ _______.

bark tracing

Page 53: Isa trees and construction   mark

Soils that have been compacted or raised in grade are good candidates for soil _______.

aeration

Page 54: Isa trees and construction   mark

There is far more than an arborist can do to treat trees that have been damaged by construction than to prevent the damage (true/false).

What a dork!

Page 55: Isa trees and construction   mark

_______ is a technique that may be employed to lower the soil grade in steps.

Terracing

Page 56: Isa trees and construction   mark

(Easy) Sample Test Questions

1. When soils are compacted by construction equipment, trees usually decline because:

a) oxygen availability is reduced

b) the ability of the roots to absorb water and minerals decreases

c) root growth and expansion may be diminished

d) all of the above

Page 57: Isa trees and construction   mark

(Easy) Sample Test Questions

2. Arborists should be involved early in the construction planning process because:

a) tree preservation measures should be in the specifications

b) once construction has begun, it may be too late to save the trees

c) there is often little arborists can do to treat construction damage

d) all of the above

Page 58: Isa trees and construction   mark

(Easy) Sample Test Questions

3. A measure that can be taken to minimize compaction on a construction site is:

a) water the site thoroughly before equipment is brought in

b) permanently raise the soil grade to protect tree rots

c) spread a temporary, thick layer of mulch over the site

d) root prune the trees in advance

Page 59: Isa trees and construction   mark

(Easy) Sample Test Questions

4. If a significant portion of a tree’s root system has been removed during building construction, a step that will help preserve the tree is:

a) pruning one-third of the crown to compensate for root loss

b) a surface application of 10 pounds of soluble nitrogen per 1,000 square feet

c) construction of a tree well

d) none of the above

Page 60: Isa trees and construction   mark

(Easy) Sample Test Questions

5. Digging trenches in a wheel-spoke pattern and backfilling with organic matter or a more porous soil is called:

a) radial aerationb) tunnel aerationc) soil fracturingd) vertical radiation

Page 61: Isa trees and construction   mark

Challenge Question

What actions can be taken if a tree is damaged by construction in violation of the written specifications?

Page 62: Isa trees and construction   mark

Challenge Question

Why may tree death and decline due to construction occur several years after construction is complete? What are some of the signs and symptoms of construction damage that an arborist can look for following construction?

Page 63: Isa trees and construction   mark

Resources

Trees and Development: A Technical Guide to Preservation of Trees During Land Development; Matheny and Clark, 1998.Root Injury and Tree Health; WatsonMissouri Department of Conservation Urban Forester: [email protected] and www.missouriconservation.org International Society of Arboriculture: www.treesaregood.com Treelink: www.treelink.org Building with Trees Workshops – The Arbor Day Foundation: www.arborday.org