Upload
wendyteosy
View
100
Download
1
Embed Size (px)
Citation preview
Measurement 4
ELEMENTAL COST ANALYSIS
SCHOOL OF ARCHITECTURE BUILDING AND DESIGNBACHELOR OF QUANTITY SURVEYING
MEMBERS OF GROUP B
MAYBELLE WANG SZE KHER 0327553
WENDY TEO SIEW YEN 0328242
ERVINNA ANAK ENDELA @ ENDELLA 0327508
AISHATH HUSSAIN 0320429
CHUANG JING 0322934
JACKSON TING SHII HANG 0324326
KONG ZHEN CHUNG 0319528
LAU CHIN SHENG 0317899
LEONG KARR KHEI 0324362
YONG SING YEW 0318766
ELLIOT PANG TIU SENG 0319438
GOH MING HANN WILLIAM 0317949HAZIM BIN ABDUL AZIZ 0315773
Job Title : Proposed 1 Block of 3 Storey Nursing Home.
BUILDING TO BE ANALYSED
NURSING HOME
Client : Synod Diocese Malaysia BaratProject : Cadangan Pembangunan 1 Blok 3
Tingkat Rumah Kebajikan (“Nursing”) Location : Lot No. PT. 3720, Jalan Besar, Kg.
Baru Sungai Buloh, Seksyen U19, 40160 Shah Alam, Selangor Darul Ehsan.
PROJECT INFO
• Contract Sum : RM 2,997,700• Date of Commencement : 14th June 2004• Date of Completion : 13th December 2005• Deflect Liability : 18 Months • LAD
TNB Substation (14th August 2005) RM 1,000 per dayBuilding Works (13th December 2005) RM 1,000 per day
• Work Programme : 7 days upon the receive of this letter.• Period of Interim Certificate : once in a month. Thirty (30)
days from the date of the architects certificate.• Period of Delay : 3 Months
CONTRACT DETAILS
Measurement 4
ELEMENTAL COST ANALYSIS:
FORM 1
A. Reinforced concrete framed construction 3-Storey building
Gross Floor Area of the building
Motor Room
Second Floor
First Floor
Ground Floor
GROSS FLOOR AREA TO BE MEASURED
Ground Floor Upper Floor
1003m2 1307m2
Total Gross Floor Area = 2310m2
SUMMARY OF GROSS FLOOR AREA
USABLE AREA CIRCULATION AREA
ANCILLARY AREA
INTERNAL DIVISION
NET FLOOR AREA
GROUND FLOOR Ancillary area = 323.63m2 Circulation area
= 248.48m2
Usable area = 392.15m2
Internal divisions= 38.87m2
FIRST FLOOR
Usable area = 426.93m2
Circulation area =
161.48m2Ancillary
area = 58.98m2 Internal
division = 27.68m2
Ancillary area = 29.11m2
Circulation area= 218.50m2
Usable area = 298.70m2
Internal divisions= 26.00m2
SECOND FLOOR
++Ancillary area
= 48.03m2
Circulation area= 11.29m2
FLOOR SPACES NOT ENCLOSED
Not enclosed space= 182.79m²
ROOF PLAN
Roof area= 997.00m²
4.15 m
Total Circulation : 639.75m2 Total Ancillary : 459.75m2 Total Usable : 1117.78m2 Total Internal Division : 92.55m2
SUMMARY OF NET FLOOR AREA FROM GROUND FLOOR TO UPPER FLOOR
Contingencies/ (Contract sum
– Contingencies)
x 100%
Preliminaries/ (Contract sum - Contingencies -Preliminaries) x
100%
Functional Unit cost = (Contract sum – external
works)/Functional Unit
Measurement 4
ELEMENTAL COST ANALYSIS:
FORM 2
Particular elemental total cost extracted from BQ
Total cost of element / GFA
Refer to manual section 16.
Eg :-For Piling, only total length of pile is taken.
Total cost of element / Element unit quantity
Element unit quantity / GFA
Convert unit from BQ to required unit
GROSS FLOOR AREA : 2444 m2 TENDER DATE :Preliminaries shown separately
Total cost Cost per m2 Element Element Element Reinforced Rein - Formworkof element GFA unit unit rate Ratio Per Concrete forcement
(RM) (RM) quantity (RM) m2 GFA m3 kg m2 2. Superstructure2.A. Frame 170416.00 69.73 2444 m2 69.73 1.000 176 39042 23402.B. Upper Floors 103743.25 42.45 1339 m2 77.48 0.548 189 12997 11792.C. Roof 178995.20 73.24 1010 m2 177.22 0.413 83 6022 10522.D. Stairs 27270.67 11.16 - - - 24 2077 2262.E. Externall Walls 63358.52 25.92 1579 m2 40.13 0.646 39 328 342.F. Windows & External Doors 57906.25 23.69 241 m2 240.27 0.099 - - -2.G. Internal Walls & Partitions 138353.00 56.61 2794 m2 49.52 1.143 16 768 802.H. Internal Doors 37652.65 15.41 272 m2 138.43 0.111 - - - Group Element Total : 777695.54 318.21 - 527 61234 4831
5 May, 2004
Convert unit from BQ to required unit.E.g. Concrete given in m2 (Quantity x height of slab)Reinforcement given in m2 (Quantity x weightage)Formwork given in m (Quantity x thickness)
GROSS FLOOR AREA : 2444 m2 TENDER DATE :Preliminaries shown separately
Total cost Cost per m2 Element Element Element Reinforced Rein - Formworkof element GFA unit unit rate Ratio Per Concrete forcement
(RM) (RM) quantity (RM) m2 GFA m3 kg m2 2. Superstructure2.A. Frame 170416.00 69.73 2444 m2 69.73 1.000 176 39042 23402.B. Upper Floors 103743.25 42.45 1339 m2 77.48 0.548 189 12997 11792.C. Roof 178995.20 73.24 1010 m2 177.22 0.413 83 6022 10522.D. Stairs 27270.67 11.16 - - - 24 2077 2262.E. Externall Walls 63358.52 25.92 1579 m2 40.13 0.646 39 328 342.F. Windows & External Doors 57906.25 23.69 241 m2 240.27 0.099 - - -2.G. Internal Walls & Partitions 138353.00 56.61 2794 m2 49.52 1.143 16 768 802.H. Internal Doors 37652.65 15.41 272 m2 138.43 0.111 - - - Group Element Total : 777695.54 318.21 - 527 61234 4831
5 May, 2004
Identify the internal door from plan.Get the total surface area of the door. (Area measured over frames)
4. Fittings and Furnishings P.C. Sums 39100.00 16.00 - - - Allowed 5. Services 5.A. Sanitary Appliances 79899.98 32.69 495 No. 161.41 - -5.B. Plumbing Installation 170000.00 69.56 - - - 170000.005.C. Refuse Disposal - - - - - -5.D. Air conditioning and 15000.00 6.14 - Tm3 15000.00 Ventilation System 5.E. Electrical Installation 365000.00 149.35 - - - 365000.00
5.F. Fire Protection Installation 124000.00 50.74 - - - 124000.00
5.G. Lift and Conveyor Installation 120000.00 49.10 - - - 120000.00
5.H. Communication Installation - - - - - -5.J Special Installation - - - - - -
5.K. Builder's Profit and Attendance - - - - - -
on Services
5.L. Builder's Work in Connection - - - - - - with Services Group Element Total : 873899.98 357.57 794000.00
Sub - total excluding External Works, 2340000.00 957.45 Priliminaries and Contingencies
Ironmongeries: RM 33,100Signages: RM 6,000
4. Fittings and Furnishings P.C. Sums 39100.00 16.00 - - - Allowed 5. Services 5.A. Sanitary Appliances 79899.98 32.69 495 No. 161.41 - -5.B. Plumbing Installation 170000.00 69.56 - - - 170000.005.C. Refuse Disposal - - - - - -5.D. Air conditioning and 15000.00 6.14 - Tm3 15000.00 Ventilation System 5.E. Electrical Installation 365000.00 149.35 - - - 365000.00
5.F. Fire Protection Installation 124000.00 50.74 - - - 124000.00
5.G. Lift and Conveyor Installation 120000.00 49.10 - - - 120000.00
5.H. Communication Installation - - - - - -5.J Special Installation - - - - - -
5.K. Builder's Profit and Attendance - - - - - -
on Services
5.L. Builder's Work in Connection - - - - - - with Services Group Element Total : 873899.98 357.57 794000.00
Sub - total excluding External Works, 2340000.00 957.45 Priliminaries and Contingencies
Extracted from Bill No.3-Building Works
Extracted from items under P.C Sum Prices for services only under P.C Sum
6. External Works
6.A. Site Work 119169.50 48.76
6.B. Drainage 167744.50 68.64
6.C. External Services 17086.00 6.99
6.D. Ancillary Buildings 7000.00 2.86
6.E. Recreational Facilities - -
Group Element Total : 311000.00 127.25
Preliminaries 141000.00 57.69 TOTAL ( less Contingencies ) 2792000.00
•Exclude Dayworks Bill total RM35700.00•Exclude Provisional Sum for future expansion of addition floor total RM 20000.00
Amount of items categorized under site works + Landscaping (P.C Sum)
Amount of items categorized under drainage + Septic tank & pump sump (P.C Sum)
Extracted from Contract Bill
Measurement 4
ELEMENTAL COST ANALYSIS:
FORM 3
Specification
Piling foundation175mm x 175mm Precast reinforced concrete piles; 15.0m depth
SpecificationRoof: BHP Lysaght "Trimdeck" colorbond Metal decking
Door: Timber skeleton framed flush door
Sanitary appliances: “Johnson Suisse” Basin
Window: Aluminium frame glazed window
Ceiling: "Brefill premix" Skim coating plastering
Floor: Vinyl tile & homogeneous tile
The Purpose of Form 3
It describes the various components in each element including the types and quality of material used
This form provides a brief picture of the building standards and quality and this information is important for cost comparison purposes