Dugway Community Meeting March 24, 2015

DWIRS public meeting 2015 March 24

Embed Size (px)

Citation preview

Dugway Community Meeting

March 24, 2015

Tonight’s presentation

• About the project

• Looking ahead and what you’ll see

• Benefits and partnerships in your community

By the numbers

• 11,000 feet3’ to 6’ sewers in tunnel

• 2,700 feet15” to 7’ sewers in open-cut

• Plus structures, regulators, modifications

Schedule

• Construction Start Jan 2014

• Substantial Completion Nov. 2016

• Final Completion Sept. 2017

Current ProgressAs of March 24, 2015

Completed Sewer

Planned Future Sewer Installation

Planned Work ActivitiesOver the Next Three Months

Structural Concrete

Shaft Construction

Microtunneled Sewer

Construction Look Ahead0 to 30 Days

Road closure summary:

• E. 110th St./Hazeldell Rd.

between Glenview Ave and

Dundee Dr.

• E. 109th St. at St. Clair Ave.

• E. 109th St. at Elk Ave.

• E. 109th St. at Helena Ave.

• Elk Ave. at E. 107th St.

• Helena at E. 107th St.

• Linn Dr. at Linn Circle (New)

Construction Look Ahead0 to 30 Days

New road closure:

– Linn Drive at Linn Circle (south of Lima Ave.)

– Open to southerly one-way traffic north of FDR driveway.

Construction Look Ahead30 to 60 Days

Road closure summary:

• E. 110th St./Hazeldell Rd. between Glenview Ave and Dundee Dr.

• E. 109th St. at St. Clair Ave.

• E. 109th St. at Elk Ave.

• E. 109th St. at Helena Ave.

• Elk Ave. at E. 107th St.

• Helena at E. 107th St.

• Linn Dr. at Linn Circle

(NO NEW CLOSURES)

Construction Look Ahead60 to 90 Days

Road closure summary:

• E. 110th St./Hazeldell Rd. between Glenview Ave and Dundee Dr.

• E. 109th St. at St. Clair Ave.

• E. 109th St. at Elk Ave.

• E. 109th St. at Helena Ave.

• Elk Ave. at E. 107th St.

• Helena at E. 107th St.

• Linn Dr. at Linn Circle

(NO NEW CLOSURES)

Dugway Storage Tunnel(DST)

Contractor Selected:

SIH JV

• Const. Start Spring 2015

• Const. Completion Summer 2019

• 24 FT diameter Storage Tunnel

• 200 FT deep with 6 Shafts

• 15,000 LF

• Storage Volume of 51 MG

• CSO reduction of 376 MG/year

• Estimated Cost $153M

Future projects

Dugway South Relief Sewer

(DS)

Est. Start March 2016

Lakeview and Ada

East 140th Relief Sewer

Est. Start May 2016

Doan Valley Tunnel (DVT)

Est. Start June 2017

Lakeview and Ada

Superior Ave

Shoreline Storage Tunnel

(SST)

Est. Start March 2023

Forest Hills Park Mining

Site

SST

E140

DugwaySouth

DST

DVT

Community benefits

• Pollution reduction– System will prevent 110 million

gallons of combined sewer overflow every year

Community benefits

• Final roadway restoration will include new pavement

• Enhanced restoration will be considered

Good Neighbor Ambassadors

• Ambassador team will support neighborhood projects, receive training, and serve as Sewer District representatives to residents

The benefit