36
King Fahd University of Petroleum & Minerals College of Engineering Sciences Mechanical Engineering Department Coop Training Program Yanbu Aramco Sinopec Refining CompanyFinal Report (Construction Activities of Newly Installed Mechanical Equipment) Submitted to Coop Advisor: Abdelaziz Bazoune Coop Coordinator: Mohammed Antar Prepared by: Name Family Name First Name Mohammed Galal KFUPM ID#: 2 0 0 9 9 3 6 9 0 Submission Date: (dd) (mm) (yyyy) 2 1 0 9 2 0 1 4

COOP REPORT

Embed Size (px)

Citation preview

Page 1: COOP REPORT

King Fahd University of Petroleum & Minerals College of Engineering Sciences

Mechanical Engineering Department

Coop Training Program

“Yanbu Aramco Sinopec Refining Company”

Final Report

(Construction Activities of Newly Installed Mechanical Equipment)

Submitted to

Coop Advisor: Abdelaziz Bazoune

Coop Coordinator: Mohammed Antar

Prepared by:

Name Family Name First Name

Mohammed Galal

KFUPM ID#: 2 0 0 9 9 3 6 9 0

Submission Date:

(dd) (mm) (yyyy)

2 1 0 9 2 0 1 4

Page 2: COOP REPORT

Summary

The report describes the knowledge and experience gained during the twenty eight weeks

of training at YASREF. Because the training was at an under construction company, the

report will mainly focus on some of the construction activities. These construction activities

can be related to plant piping construction such as pressure testing, pipes’ flange bolt

tightening and post weld heat treatment of some welding joint. They can be related to

rotating equipment such as pump alignment and motor solo run. Moreover, construction

activities can be related to other equipment such as the process of belt splicing in belt

conveyor system. Each of these construction activities encountered during the training has

been described in details with some photos and referring to some standards. At the end of

the report, three case studies have been discussed. The first one is a designed base case

study. The second and third case studies are related to problems faced during the

construction activities.

Acknowledgment

First of all, I would like to express my thanks to Allah for his guidance and support during my

whole training period. All praise to Allah that the training period went smoothly with a great

gained experience. A special thank is also goes to my parents who always stand beside me,

support me and pray for me.

Secondly, I would like to thank both the mechanical engineering department and the

training department for their collaboration to run this program successfully. Thank you for

your hard work to contact with many companies to offer training opportunities for students.

In my case, I got my training opportunity through the training department website.

Moreover, I would like to express my deep thanks to the COOP coordinator and my COOP

advisor Dr. Abdelaziz Bazoune who organize all related COOP issues in the department.

Thank you for your support and help during my training period.

Finally, I would like to express my great appreciation to the host company (YASREF) and the

project quality management department in which I have been assigned. A special thank

goes to my supervisor, Mr. Talal Mahjoub, who organized my rotation schedule in the

different packages of the project. Thank you to all quality engineers who I work with them.

Page 3: COOP REPORT

1

Table of Content

Introduction ..................................................................................................................... 4

YASREF Overview ................................................................................................................... 4

Assigned Department and COOP Work Plan ......................................................................... 4

Pressure Testing of Plant Piping ........................................................................................ 6

Hydrostatic Test ..................................................................................................................... 6

Pneumatic Test .................................................................................................................... 10

Post Weld Heat Treatment of Pipes ................................................................................ 11

Flange Bolt Tightening .................................................................................................... 14

Pump Alignment ............................................................................................................. 16

Fabric Belt Splicing ......................................................................................................... 21

Case Studies ................................................................................................................... 26

Case Study (1) ...................................................................................................................... 26

Case Study (2) ...................................................................................................................... 29

Case Study (3) ...................................................................................................................... 30

Conclusion and Recommendation ................................................................................... 33

References ..................................................................................................................... 34

Page 4: COOP REPORT

2

List of Figures

Figure 1: Hydrostatic Test Equipment .................................................................................................... 6

Figure 2: HAZ of Welding Process ......................................................................................................... 11

Figure 3: PWHT Equipment ................................................................................................................... 11

Figure 4: Sample PWHT Report ............................................................................................................. 13

Figure 5 : Tightening Sequence of 24 Bolts and Bolt Numbering for Large Number of Bolts (36-68) .. 15

Figure 6: Offset Misalignment .............................................................................................................. 16

Figure 7: Angular Misalignment ............................................................................................................ 16

Figure 8: Manufacturer Pump Information .......................................................................................... 16

Figure 9 : Potable Water Booster Pump General arrangement drawing ............................................. 17

Figure 10: Alignment Tools ................................................................................................................... 17

Figure 11: Alignment Bracket with Two Dial Indicators ........................................................................ 19

Figure 12: Tightening and Soft Foot Check of Motor ............................................................................ 19

Figure 13: Alignment Report ................................................................................................................. 20

Figure 14 : Final Alignment Steps .......................................................................................................... 21

Figure 15: Belt Conveyor ....................................................................................................................... 22

Figure 16: Belt Splicing Equipment (1) .................................................................................................. 22

Figure 17: Belt Splicing Equipment (2) .................................................................................................. 23

Figure 18: Cutting Belt Ends .................................................................................................................. 23

Figure 19: Belt Marking ......................................................................................................................... 24

Figure 20: Cover Fill in Cut and Removing Rubber Cover ..................................................................... 24

Figure 21: Final Look of Belt Ends after Cutting .................................................................................... 24

Figure 22: Cleaning and Grinding .......................................................................................................... 24

Figure 23: Installing Vulcanizing Press Machine on Belt ....................................................................... 25

Figure 24: Belt Ends after Splicing ........................................................................................................ 25

Figure 25: Effects of Insulation and Heating on Heat transfer ............................................................. 26

Figure 26: Skin Effect Electrical Heat Tracing ........................................................................................ 27

Figure 27: Electrical Heat Tracing of Sulfur Feed Drum ........................................................................ 27

Figure 28: Hot Oil Jacketed Pipes .......................................................................................................... 28

Figure 29: Hot Oil System ...................................................................................................................... 28

Figure 30: Temporary Support on Pipe ................................................................................................. 29

Figure 31: Motor Solo Run .................................................................................................................... 30

Figure 32: Vibration spectra .................................................................................................................. 32

Page 5: COOP REPORT

3

List of Tables

Table 1 : COOP Rotation Schedule ............................................................................................. 5

Table 2: Line Designation Table ................................................................................................. 7

Table 3: Requirements for PWHT ............................................................................................ 12

Table 4: Torque Values for Bolt Tightening ............................................................................. 14

Table 5: Bolt Tightening Sequence for 36 Bolts flange ............................................................ 15

Table 6: Example for Standard Tables of Belt Splicing............................................................. 23

Table 7 : Vibration Readings of Motor Solo Run at Different Condition ................................. 31

List of Abbreviations and Symbols

YASREF: Yanbu Aramco Sinopec Refining Company

KBR: Kellogg, Brown and Root, an American Engineering and Construction Company

PQMD: Project Quality Management Division

bpd: Barrel per Day

LPG: Liquefied Petroleum Gases

PWHT: Post Weld Heat Treatment

NDT: Non Destructive Testing

ASME: American Society of Mechanical Engineers

SAES: Saudi Aramco Engineering Standards

SAEP: Saudi Aramco Engineering Procedure

Ppm: Parts Per Million

DBSE: Distance between Shaft Ends

RFI: Request for Inspection

Page 6: COOP REPORT

4

Introduction

YASREF Overview

YASREF stand for Yanbu Aramco Sinopec Refining Company. It is a joint project between

Saudi Aramco and China petrochemical company (Sinopec). Saudi Aramco is one of the

leading companies in oil and gas industry in the world having 62.5 % equity share in the

company. On the other hand, Sinopec is one of the biggest companies in petrochemical

products in china having 37.5 % equity share in the company. The refinery is located in

Yanbu Industrial City on the red sea. The refinery total area is 5.2 million square meters

with a capacity to refine a 400,000 barrel per day (bpd) of Arabian heavy crude oil into final

products for export and domestic use. These products include:

Gasoline

High Quality Diesel

Liquefied Petroleum Gases (LPG)

By Product Sulfur

Petroleum Coke for Export

The agreement between Aramco and Sinopec was in May 2006. After agreement, KBR

Company with other design companies was selected for the design of the refinery. In July

2006, the design companies started the design phase of the company. In April 2009, the

construction of the refinery started and it is still ongoing. The construction of the refinery is

divided into eighteen packages with eighteen main contracts. It is expected that test runs

for the refinery to be conducted on September 2014 and the first refined products to be

exported by November 2014.

Assigned Department and COOP Work Plan

At YSREF Company, I have been assigned in the project quality management department. At

this division, the main objective of their work is to monitor all construction activities done

by contractors and ensure that the work is complying with YASREF standards. Construction

activities include piping, mechanical equipment, welding and NDT. During my training, I

have been working with a group of Mechanical engineer inspectors. As a mechanical

inspector at YASREF, You have to be familiar with the standards governing the construction

activities. It is also important that your relationship with contractor’s engineers and stuffs

does not affect your duties. What is correct and agree with standards should be accepted

and what is wrong or not complying with standards should be rejected. At the company, Mr.

Talal Mahjoub, PQMD manger, was assigned to be our main mentor during our training

program. He developed a training program for us that include the following schedule.

Page 7: COOP REPORT

5

Table 1 : COOP Rotation Schedule

Training Period

Department Name

(Package)

Tasks:

Please indicate if individual work

assignments or team assignments

will be made Wee

k #

From

(DD/MM/YYYY)

To

(DD/MM/YYYY)

1-2 26/01/2014 06/02/2014

Quality Division

Lectures on :

1. Safety

2. Overview about the

company

3. Quality

3-6 09/02/2014 06/03/2014

Tank Farm

Interconnecting System

Tasks will be assigned

based on available work

during the assigned period.

The tasks will be assigned

according to the listed

objectives.

7-11 09/03/2014 10/04/2014

Delayed Coker Unit

12-17 13/04/2014 22/05/2014

Solid Handling

18-23 25/05/2014 03/07/2014 Gasoline

24-28 06/07/2014 07/08/2014 Hydrocracker

Page 8: COOP REPORT

6

Pressure Testing of Plant Piping

After completion of all construction activities of pipes such as welding, mechanical

assembly, post weld heat treatment and non-destructive testing, pipes are subjected to

pressure testing to check that they will withstand the actual pressure and there is no

leakage. The most commonly performed pressure tests are hydrostatic and pneumatic.

1) Hydrostatic Test

Definition

It is the type of pressure test in which the pipe to be tested is pressurized using water.

Reference Standards Used at YASREF

As for any engineering work, hydrostatic test follows some standards for the correct and

safe procedure. For hydrostatic testing at YASREF, the main reference standards are:

International standard

ASME B31.3

Project specifications:

(SAES-L-150/SAES-L-

350/SAES-A-004/SAES-

A-

007/SAEP327/GI0002.

102)

Equipment and Calibration

1) Pump

2) Manifold

3) Two pressure gauges

4) Relief valve

5) Water

6) Blind flanges

7) Pipe to be tested

The test equipment must be calibrated or the calibration is still valid before the test. The

calibration certificate should be checked and compared with the one labeled on the test

equipment.

a) Pressure gauges should be calibrated monthly. Test pressure should be within

30% to 80 % of the reading ranges of these pressure gauges.

b) Relief valve should be calibrated weekly. It is set to depressurize the system in

case the test pressure exceeded 5 % of the required test pressure.

c) Manifold should be calibrated each six months.

Figure 1: Hydrostatic Test Equipment

Page 9: COOP REPORT

7

Hydrostatic Test Pressure Calculation

Based on ASME B31.3, minimum hydrostatic test pressure can be calculated with the

following formula:

Pt =

Where:

Pt: Minimum hydrostatic test pressure

P: Design pressure

St: Allowable stress at test temperature

S: Allowable stress at design temperature

Also based on ASME B31.3, maximum hydrostatic test pressure is calculated using

the following formula:

Pm =

Where:

Pm: Maximum hydrostatic test pressure

S: Minimum yield strength at test temperature

E: Quality factor

t: Pipe wall thickness minus mill tolerance

D: Outside diameter

At YASREF project, the hydrostatic test pressure is indicated on the line designation

tables of the isometric drawing of the pipelines. This table indicates also the design

pressure, design temperature and insulation requirements.

Table 2: Line Designation Table

Page 10: COOP REPORT

8

Water Quality Used for Hydrostatic Test

The quality of water to be used for the test will vary based on the material of the pipe to be

tested or the actual fluid to be processed inside the pipe. The following points summarizes

the quality of water to be used in hydrostatic test.

For carbon steel piping, fresh water that is free of contaminant and with chloride

content less 300 ppm.

For low alloy, austenitic stainless steel and nickel alloy steel piping, water to be used

should have low chloride content ( less than 50 ppm)

Potable water and utility water piping should be tested with potable water.

Sea water is not allowed to be used as a test medium unless approved by Aramco.

Hydrostatic Test Pressure Duration

It is the time required to keep the piping system under the test pressure then inspection is

carried on. The following points summarizes the duration time of hydrostatic test pressure.

For plant piping, at least half hour is required prior to inspection

For pipelines, 26 hours is the required test duration

For firewater pipes, four hours is the minimum test duration.

Factors Affecting on Hydrostatic Test Pressure Value

While performing hydrostatic test, inspectors and technicians should be aware of the

factors that affect on the hydrostatic test value. The main two factors affecting hydrostatic

test value are:

1) Temperature

Temperature is directly proportional to pressure. When temperature increase the test

pressure will increase and when temperature drop the test pressure will drop. To avoid such

problem, conducting test pressure should be carried during day time of almost constant

temperature. If this is not applicable, depressurizing and pressurizing should be carried to

avoid temperature increase or decrease

2) Elevation

Calculation of hydrostatic test pressure does not take into account the elevation of pipes

above ground. This should be done by the hydrostatic test performer and inspector. One

rule of thumb is to increase the calculated hydrostatic test pressure by one bar for each ten

meter aboveground pipes.

Page 11: COOP REPORT

9

Hydrostatic Test Pressure Steps

1) All welding, assembling, PWHT and NDT activities must be completed and checked as

per isometric drawing. Moreover, equipment that should not be included in the

hydrostatic test such as control and check valve must be removed from the line to be

tested.

2) The line to be tested must be cleaned from any foreign material. Cleanness of the

line can be achieved using compressed air.

3) Start filling the line with water from low point with the vents are open so that air will

not be trapped inside. When air is get trapped that would affect on pressure gauges

readings.

4) After removal of air inside the pipe, close all vents and pressurize the pipe with

water. Pressure should be increase with an increment of 25% of the desired test

pressure. At each increment allow some time for inspection. In case of any leak

detection, depressurize the system and solve the leak problem and retest the

system.

5) When the pressure on the pipe reach the desired test pressure, stop water pumping

and hold the test pressure for sufficient time as indicated on the test duration

paragraph.

6) Inspectors should carry on inspection for the system by one of the methods:

Visual inspection method

This method is used for plant piping in which half an hour is required for holding the test

pressure. In this method, inspector checks all weld and connections visually.

Pressure drop method

This method is used for pipelines that require more holding time. For inspection, inspectors

record the test pressure when it reach the desired test pressure and then check at the end

of the holding time. If there is a pressure drop, that is an indication of leakage.

7) Upon completion of the test, depressurize the system gradually.

Safety Requirements

1) All people involved in the test preparation and inspection must be wearing personal

protective equipment.

2) Test equipment must be positioned in a safe manner.

3) There should be warning signs closing the whole area that is under test.

4) No work is allowed for pipes that are included in the test.

5) If leakage is detected, depressurize the system to zero pressure then check the

leakage reason. No flange tightening is allowed while the system under pressure.

Page 12: COOP REPORT

11

2) Pneumatic Test

It is the type of pressure testing in which the test medium is air. All specifications discussed

in hydrostatic testing applied to pneumatic test with few differences. These differences are:

Instead of pump, air compressor will be used.

Pt =

Air used for testing does not have to meet specific quality measurement such

the one that must meet the water used in hydrostatic testing.

The time needed to keep the test pressure prior to inspection is ten minutes.

No need for vents because the test medium is air.

Inspection for leaks in the system is carried on using a solution and checking

for bubbles.

No lay up is needed

Special safety requirement is needed when conducting pneumatic testing.

Page 13: COOP REPORT

11

Post Weld Heat Treatment of Pipes

As the name of the process implies, it is a heat treatment process that is performed upon

completion of welding on the welding area and the heat affected zone. This heat treatment

removes the residual stresses developed during welding and recovers the microstructure of

the original metal. This process starts with heating the welding area up to a specific

temperature then holding that temperature for a specific time and finally cooling. The

heating and cooling rates as well as the temperature at which heating is hold for a specific

time should follow the recommended standards and practice.

PWHT Equipment

The main equipment for PWHT is:

1) Power source

2) Recorder ( Temperature and Current)

3) Ceramic pad heater

4) Insulation

Figure 3: PWHT Equipment

Figure 2: HAZ of Welding Process

Page 14: COOP REPORT

12

When PWHT Is Required for Pipes

PWHT in pipes is governed by two factors:

1) PWHT required by the thickness of the pipe to be welded.

Table (3) is taken from ASME B31.3, Table 331.1.1. This table indicates when PWHT is

required for some pipes base metals based on pipe thickness. It provides the holding

temperature and time.

2) PWHT required by the service fluid flowing on the pipe.

For carbon and alloy steel pipes, the following service fluids require PWHT

1) All caustic soda (NaOH) solutions, including conditions where caustic carryover may

occur (e.g. downstream of caustic injection points).

2) All monoethanolamine (MEA) solutions (all temperatures).

3) All diglycol amine (DGA) solutions above 138°C design temperature.

4) All rich amino diisopropanol (ADIP) solutions above 90°C design temperature

5) All lean ADIP solutions above 60°C design temperature.

6) Boiler deaerator service

7) Hydrogen service for P-No. 3, 4, and 5A/B/C base materials.

8) All diethanolamine (DEA) solutions.

Table 3: Requirements for PWHT

Page 15: COOP REPORT

13

Main Points Regarding PWHT

Maximum heating and cooling rate is 2220C/h divided by the thickness of the weld in

inches.

The minimum area to be included in the heat treatment is three times the pipe

thickness on each side of the welding joint.

At least 300 mm insulation should be applied on each side of the welding joint.

Removal of the insulation should not be done till temperature reach 1500C or below.

Number of thermocouples to be used should be as follow:

a) One thermocouple for pipe diameter 305 mm or less.

b) Two thermocouples for pipe diameter greater than 305 mm up to 610 mm.

c) Four thermocouples for pipe diameter greater than 610 mm.

Sample Report Graph

Figure 4: Sample PWHT Report

Page 16: COOP REPORT

14

Flange Bolt Tightening

Pre-Tightening Steps

1) Inspection should be carried to check that gasket, bolts and nuts are of the correct

type based on isometric drawing. It is also important to check that they are free of

damage.

2) Flange faces should be cleaned and free of any damage.

3) The torque wrench to be used must be calibrated or its calibration is still valid prior

to tightening.

4) Check correct use of lubricant.

5) Based on bolt sizes and gasket type, check the table to choose the correct torque

value for tightening. Table (4) gives the recommended torque values.

Table 4: Torque Values for Bolt Tightening

Page 17: COOP REPORT

15

Tightening Procedures

1) Flange faces should be properly aligned within acceptable limits

2) Lubricant should be applied to the bolts threads and check that the nut is moving

freely over the bolt.

3) By hand, install the bolts on the flange holes and make sure that it is freely moving

on the hole. Start tightening by hand.

4) Using torque wrench, start bolt tightening following the recommended sequence.

a) For small number of bolts (4-32), the sequence is one bolt against another.

Figure (5) to the left shows an example for the sequence for 24 bolts.

b) For large number of bolts (36-68), start numbering as shown on figure (5) to

the right then the sequence is three or four bolts against another three or

four bolts. Table (5) shows the sequence for 36 bolts.

5) The tightening of bolts should be done in two stages. The first stage with torque

value that is 30 % of the required value and the second stage with 100% of the

torque value.

Table 5: Bolt Tightening Sequence for 36 Bolts flange

Figure 5 : Tightening sequence of 24 bolts and Bolt Numbering for large Number of Bolts (36-68)

Page 18: COOP REPORT

16

Pump Alignment

Pump and motor shafts alignment is the process in which both the pump and motor are

adjusted so the two shafts are collinear. The case of 100 % collinear shafts is never the case

in real practice. However, there are acceptable tolerances for shafts misalignment. These

tolerances are based on some standards or vendor recommendation. The alignment process

is very important to rotating equipment because it improves the life of its internal

mechanical components and reduce noise and vibration during operation. In this report, the

described method is Rim and Face method and the given data and photos are for portable

water booster pump with its driving motor.

Misalignment Types

Parallel or Offset Misalignment

Angular Misalignment

The two shafts to be aligned are parallel but

at a distance from each other.

The two shafts to be aligned have an

angle to each other.

Pump and Motor Specifications

The pump and motor to be aligned have the following

specification

Pump RPM is 3540

Motor RPM is 3525

Distance between shafts end (DBSE) is 177.8 mm

Reference Documents

1) SAES -G-005 Centrifugal Pumps 24 February 2008

2) API 686 – Recommended Practices for Machinery Installation and Installation Design

1996

3) Manufacturer’s Data Sheet and Instruction

Figure 8: Manufacturer Pump Information

Figure 6: Offset Misalignment Figure 7: Angular Misalignment

Page 19: COOP REPORT

17

Figure 9 : Potable Water Booster Pump General arrangement drawing

Main Equipment Used for Alignment

1) Two dial indicators attached on alignment bracket

2) Micrometer

3) Straight edge

4) Feeler gauge

5) Shims

Figure 10: Alignment Tools

Page 20: COOP REPORT

18

Alignment process and procedure

General Requirements

1) Documents related to the alignment process such as drawings, data sheets, DBSE

and recommended tolerances should be available for review before starting the

alignment process.

2) For pump and motor alignment, the pump is the fixed reference of alignment while

the motor is the movable machine to be adjusted. For this reason, the pump and

motor baseplate is designed such that the motor is resting in a position slightly

lower than the pump. By this design of the baseplate, shims can be added or

removed under/from the support foot of the motor.

3) Shims to be used should be of 300 series stainless steel to avoid corrosion.

Maximum number of shims to be used under any foot should not be more than five

shims.

4) Tolerances to be followed for the alignment can be summarized as follow:

a) Misalignment in both radial and axial direction should not exceed 0.05 mm

b) DBSE tolerance should not exceed 0.25 mm

c) For soft foot, movement at each foot should not exceed 0.05 mm

Preliminary Alignment

The preliminary steps of alignment will be performed after the baseplate installed on the

foundation that has been built according to specific level and coordinates. At this stage the

suction and discharge pipes are not connected to pump.

1) Prior to place the pump and motor on their position on the baseplate, machined

surfaces such as foot base and flange surfaces should be checked for straightness

using calibrated level.

2) Adjust the pump on its place and tighten its bolts. Check must be done on the

straightness of the pump shaft because it will be our fixed reference.

3) With the motor placed on its adjustable place on the baseplate, start rough

alignment of the pump and motor shafts as follow:

a) Using the straight micrometer, measure the exact DBSE at 12 o’clock and 6

o’clock positions as seen from motor end. This step will reduce the angular

misalignment in the vertical plane.

b) Using an appropriate straight edge, measure how high is the pump hub from

the motor hub. Add appropriate shims for correction. This step will reduce

offset misalignment in the vertical plane.

c) Repeat step (a) for the horizontal plane. This step will reduce the angular

misalignment in the horizontal plane.

Page 21: COOP REPORT

19

d) Using straight edge, measure how the two shafts are horizontally offset from

each other. Move the motor to the left or right for correction. This step will

reduce offset misalignment in the horizontal plane.

4) The alignment bracket with the two dial indicators is installed on the hub of the

pump. Then, we rotate the shaft of the pump to take the reading of the dial

indicators at different position.

a) Zero the two dial indicators at 12

o’clock position and rotate the

shaft to 6 o’clock position and take

the reading of the two dial

indicators. Make any correction if

the misalignment exceeding the

acceptable tolerances.

b) Repeat step (a) for the positioning

of the dial indicators at 3 o’clock

and rotating to 9 o’clock

5) Tighten the motor bolts and check for soft

foot.

Figure 12: Tightening and Soft Foot Check of Motor

Final Alignment

The final alignment steps will be performed after grouting has been done according to the

approved procedure. These steps will be performed as the pipes are connected to the pump

to measure any misalignment during the connection.

1) Before starting the final alignment, check that :

a) All pipes to be connected to the pump nozzles are hydro-tested and dried.

b) All pipe supports are installed according to the isometric drawing.

c) The motor is already solo run and accepted.

2) Install the rim and face dial indicators so that the alignment bracket is fixed on the

motor hub and the two dial indicators are touching the rim and face of the pump

hub.

3) Start aligning the pipe flanges with the pump nozzles as follow :

Figure 11: Alignment Bracket with Two Dial Indicators

Page 22: COOP REPORT

21

a) The bolt holes of the flanges should be collinear with the bolt holes on the

pump nozzles. 1.5 mm offset between the hole’s centers is acceptable.

b) Using feeler gauges, adjust the distance between the pipe flanges and pump

nozzle flanges. Maximum distance should not exceed 1.5 mm plus gasket

thickness.

4) Prior to bolt tightening of pipe flanges to pump nozzles, an inspection check should

be carried as follow :

a) Gasket to be used should be inspected for correct type as per the isometric

drawing. A check for gasket damage should be carried as well.

b) Bolts, nuts and washer should be checked for correct type and for any

damage.

c) Pipe and nozzle surface flanges should be clean and dry.

5) After the inspection of step four is completed, start bolt torqueing and tightening.

The torque value and procedure should be as per Armco standard.

6) While we are tightening the bolts, keep tracking the indicators reading for any

change in the alignment. For any misalignment beyond the accepted tolerances,

correction must be carried to bring the misalignment within the acceptable limits.

The correction can be made by shimming or adjusting the pipe supports.

7) Final reading at each 90 degree must be carried and then soft foot check

8) Main contract and YASREF mechanical inspector should check the alignment

tolerances are within acceptable limits or not. Alignment report shall be approved

and signed. Figure (13) show a report for the final alignment process.

9) Coupling shall be installed and tightened.

10) Finally, coupling guard shall be installed.

The next Page show some photos for the final alignment steps

Figure 13: Alignment Report

Page 23: COOP REPORT

21

Figure 14 : Final Alignment Steps

Fabric Belt Splicing

Belt splicing is the process in which two belt ends are joined together. At YASREF project,

two types of belt (fabric and steel) are used on a conveyor to transfer coke and pelletized

sulfur from their process units to KFIP. In this report, fabric belt splicing using hot

Vulcanization method will be explained. For proper belt splicing, some factors should be

taken into consideration such as the type of belt, the speed of the belt conveyor system,

transferred material and environment.

Page 24: COOP REPORT

22

Specification

The belt to be spliced is EP630/4 which has the following specification

1) The belt reinforcement material is fabric with 4 layers

2) Ultimate tensile strength of the belt is 630 N/mm

3) Thickness of the belt is 14 mm

4) Width of the belt is 1400 mm

Belt speed is 2.03 m/s

The fabric belt is part of the belt conveyor system to be used for transferring

Petroleum Coke from the Delayed Coker Unit to King Fahd Industrial Port.

Design temperature is 750C

Reference Documents

1) DIN 22102-Part 1

2) IS - 1891- Part I

3) Manufacturer recommendations

Main Splicing Equipment

1) Vulcanizing press machine

2) Generator

3) Water tank with pumping

mechanism and pressure

recording

4) Temperature recorder

5) Hook chook

6) Cutting knives

7) Air blowers and grinding

tools

8) Splicing material

9) Cleaning solution

10) Adhesion

Figure 15: Belt Conveyor

Figure 16: Belt Splicing Equipment (1)

Page 25: COOP REPORT

23

Procedure

1) First of all, the two belt ends to be spliced and form one continuous belt should be

cut at an angle for better joining. This can be done as shown on the figure (18).

In our case: Belt width (B) = 1400 mm

0.4 B = 560 mm

So, the angle of the cut is:

θ = Arctan (0.4) = 21.800

2) Second, decide on the number of

steps for cutting the belt.

Since the belt is having four layers of fabric, the number of steps is three according

to the rule:

Number of steps = number of layers (plies) - 1

3) Decide on the splice length and step length. This can be found using standard tables.

Table (6) is an example for such tables.

Table 6: Example for Standard Tables of Belt Splicing

According to table (6):

Splice length = 600 mm Step length = 200 mm Number of steps = 3

Figure 17: Belt Splicing Equipment (2)

Figure 18: Cutting Belt Ends

Page 26: COOP REPORT

24

4) After decision have been made about the number of steps of cutting, splice length

and step length, the cutting work will start as follow:

a) Start marking the splice length, step lengths and

cover fill in cut.

b) Using the cutting knife, we start with the cover fill

in cut. This cut should be with 25 mm width and at

45 degree angle. Then, remove the rubber cover

from the whole splicing length. After that we cut

the first fabric layer a distance equal to the step

length. Then, continue cutting the second and third

layer.

Figure 20: Cover Fill in Cut and Removing Rubber Cover

c) The same cutting process will be done

for the second belt end but in

opposite direction to the first end.

After cutting is completed, the two

ends will look like as shown on figure

(21).

5) Using the grinding tool, air blower and the

cleaning solution, grind the belt ends and

clean the whole splicing area from any

contamination.

Figure 22: Cleaning and Grinding

Figure 19: Belt Marking

Figure 21: Final Look of Belt Ends after Cutting

Page 27: COOP REPORT

25

6) Apply the splicing material on one end of the belt. First of all, a layer of splicing

material should be applied to the whole area to be spliced. An additional 50 mm

splicing material should be added to the upper and bottom cover. Moreover, 25 mm

splicing material to be added to the side edge of the belt.

7) Align the two belt ends. Use clamps to keep the ends aligned with each other.

8) Install the vulcanizing press machine on the two belt ends. The spliced belt is placed

between two hot plates. The belt is protected from being sticking on the hot plates

by two silicon layers. Above the upper hot plate, there is a rubber water tank to be

used for providing the pressing pressure.

Figure 23: Installing Vulcanizing Press Machine on Belt

9) Connect the temperature recorder to the vulcanizing machine and turn on the

generator to provide electricity to the heating plates.

10) Keep heating till the temperature recorder read 70 0C then start pumping the water

to the rubber water tank. Stop pumping the water when the gauge pressure read

150 PSI.

11) Continue heating till temperature reach 145 0C. After that, additional heating time is

required. This heating time is based on belt thickness. The rule is that for each 1 mm

thickness 3 min of heating is required.

In our case:

Belt thickness is 14 mm

Additional heating time = 14 *3 = 42 min

12) When the additional time of

heating is done, the heating is

stopped and machine is left for

cooling. Finally, the vulcanizing

press machine is uninstalled and

the splicing work is done.

Figure 24: Belt Ends after Splicing

Page 28: COOP REPORT

26

Case Studies

Case Study (1)

Problem

Molten sulfur is one of the byproducts of the refining process of crude oil. It is produced at

the refinery area at 130 0C. This molten sulfur is needed to be transferred from the refinery

to King Fahd Industrial port (about 4.3 Km) where it will be solidified, stored and then

exported. The problem with molten sulfur is that it solidifies when its temperature drop

below 119 0C. If such case happened during the transferring process, it would cause

damage to pipelines and pumps and stop the production. Describe the process of Molten

sulfur transfer from the refinery to the port and how the problem being solved.

Process

Molten sulfur is produced at different stages of the refining process at temperature 130 0C.

It is then collected and stored in a two big storage tanks in the refinery area. This molten

sulfur is then transferred to sulfur feed drum via molten sulfur pipelines (about 4.3 Km). To

maintain the molten sulfur temperature within 125 to 135 0C, the molten sulfur pipelines is

being electrically heat traced via the skin effect system and insulated.

From the sulfur feed drum, molten sulfur is pumped using sulfur feed pumps to the

pelletizer building. At this stage, molten sulfur temperature is maintained within 125 to 135 0C by electrical heat tracing of the sulfur feed drum and hot oil jacketing of the pipes and

pumps. When the molten sulfur reaches the pelletizer building, it will be solidified in the

form of pellets (2-6 mm pellets). The sulfur pellets is then transported via belt conveyer to

the storage unit. At the storage area, sulfur pellets will be collected. When there is an export

process, the sulfur pellets is pushed using reclaimer to another belt conveyor to shipment

area.

Molten Sulfur Temperature

Maintenance Mechanisms

Hot liquids moving on pipes or stored in

tanks expose to continuous heat

transfer. The heat transfer mechanism

can be by conduction, convection or

radiation. In our case of molten sulfur

pipes and tanks, all three modes

contribute the process of heat transfer.

Heat transfer is directly proportional to

the temperature difference.

Figure 25: Effects of Insulation and Heating on Heat transfer

Page 29: COOP REPORT

27

Heat Transfer α Δ T

Δ T = ( TSulfur – TAmbient )

In our case, sulfur is produced at temperature 130 0C and ambient temperature is 15 0C <

Tambient < 45 0C. This implies that the temperature difference is high (85 0C < Δ T <115 0C). In

order to maintain molten sulfur temperature, there should be some mechanism to reduce

the heat transfer and a source for heat to compensate for any heat losses.

Reducing the heat transfer can be achieved by applying an appropriate insulation to the

pipe or tank. Heating sources to compensate heat losses can be achieved by different

methods. In our case of molten sulfur, the heating has been done in three stages with

different methods.

1) Skin Effect Electrical Heat Tracing

System for the 4.3 Km Sulfur Pipelines

In this method, a ferromagnetic heating tube is

welded to the sulfur pipelines that extend for

4.3 Km. Inside the tube, a special insulated type

cable is placed. The cable is connected to an AC

voltage source and end terminated to the inner

surface of the tube. The current flowing in the

tube is only within the internal thickness of the

tube such that no measurable voltage on the

outer surface of the heating tube. The heat will

be generated to sulfur pipeline as follow:

a) 80% of the heating required will be supplied to the pipeline due to I2R losses from

the current flowing on the tube attached to the pipeline

b) 20% of the heating required will be supplied due to I2R losses from the insulated

cable.

2) Electrical Heat Tracing of Sulfur Feed Drum

For the sulfur feed drum, it is being heated using

electrical heat tracing cable. This cable has been

wrapped around the drum and insulated. The cable

supply heat to drum by the I2R losses from the

insulated cable. The cable must be connected to some

controllers and regulators. These controllers and

regulators will maintain the molten sulfur within the

required temperature (125 -135) 0C. They are also help

in protecting the cable from being over heated which

can damage the cable and the sulfur inside the tank.

Figure 26: Skin Effect Electrical Heat Tracing

Figure 27: Electrical Heat Tracing of Sulfur Feed Drum

Page 30: COOP REPORT

28

3) Hot Oil Jacketing of Pipes Extending from Feed Drum to Pelletizer

Hot oil jacketed pipes have a special design to maintain molten sulfur as liquid with

temperature 131 0C. In fact, hot oil jacketed pipes consist of two coaxial pipes. The inner

pipe is for the process fluid which is here the molten sulfur. The outer pipe is for the heated

oil which will be circulated on the pipes. The hot oil which will be supplied to the pipes has a

special system. This system consists of:

Hot Oil Heaters

Hot Oil Storage Tanks

Hot Oil Circulation Pumps

Oil Loading Pumps

Expansion Tank

Figure 28: Hot Oil Jacketed Pipes

Figure 29: Hot Oil System

Page 31: COOP REPORT

29

Case Study (2)

Problem

While performing pump alignment, technicians could not approach good pump alignment

within accepted tolerances.

Problem Effects

For any construction activity, the contractor sends a request for inspection (RFI) to YASREF

quality engineer who is responsible for monitoring that type of activity. For this activity, the

RFI was raised with a specified time for inspection. When the inspector went to site to

inspect the alignment and close this work, the contract company was facing the problem

that the pump is not responding to alignment. The inspector will not wait till the problem is

solved so he rejected the RFI. This means that the contractor side should issue another RFI

when they resolve the problem. Such problem cause a time delay in the project progress

and time is money for both the contract company and the owner company.

Problem Investigation and Solution

A first suggestion was to recheck that the dial indicators and alignment bracket are in good

condition and not giving wrong readings. However, this was not the cause of the problem.

Then, the rotating equipment engineer suggested the use of a temporary pipe support at

different location and performs the alignment process. At one position of the temporary

pipe support, the alignment gives good results. Referring back to the isometric drawing,

engineers found that a permanent pipe support is not positioned on its designed location.

Due to this mistake, more stresses developed on the flange which causes the alignment not

to respond.

Figure 30: Temporary Support on Pipe

Page 32: COOP REPORT

31

Case Study (3)

Problem

During solo run test of Motor -114-GM-0007B, the motor show high vibration that is beyond

the site accepted criteria.

Figure 31: Motor Solo Run

Investigation of the Root cause of the vibration

First of all, the vibration of the motor was identified as caused due to a problem in

the bearing of the motor (Roller Bearing). As an action to solve the problem, motor

bearings were replaced. However, the vibration still exists when motor reinstalled

and tested at site.

When bearing replacement did not give positive results, YASREF requested General

Electric Company which manufactured the motor to perform more inspection to

identify the root of the vibration. The company performed the test into five steps.

1. Solo run in standard conditions

2. Solo run with the fan cover of the motor is loosened

3. Solo run while bolts of the motor are not tightened to the baseplate

4. Solo run with sof shoe shim

5. Impact test to find the natural frequency of the motor.

Page 33: COOP REPORT

31

Table 7 : Vibration Readings of Motor Solo Run at Different Condition

1. Solo run in standard conditions

Motor Tag. 114-GM-0007B

Site Readings (mm/s RMS)

Site Criteria (mm/s RMS)

Motor DE H 4.63 2.8

Motor DE V 1.2 2.8

Motor DE A 0.63 2.8

Motor NDE H 6.32 2.8

Motor NDE V 0.96 2.8

2. Solo run with the fan cover of the motor is loosened

Motor Tag. 114-GM-0007B

Site Readings (mm/s RMS)

Site Criteria (mm/s RMS)

Motor DE H 2.73 2.8

Motor DE V 1.1 2.8

Motor DE A 0.45 2.8

Motor NDE H 4.12 2.8

Motor NDE V 1.01 2.8

3. Solo run while bolts of the motor are not tightened to the baseplate

Motor Tag. 114-GM-0007B

Site Readings (mm/s RMS)

Site Criteria (mm/s RMS)

Motor DE H 0.92 2.8

Motor DE V 0.56 2.8

Motor DE A 0.46 2.8

Motor NDE H 1.08 2.8

Motor NDE V 0.96 2.8

4. Solo run with sof shoe shim

Motor Tag. 114-GM-0007B

Site Readings (mm/s RMS)

Site Criteria (mm/s RMS)

Motor DE H 1.47 2.8

Motor DE V 0.55 2.8

Motor DE A 0.27 2.8

Motor NDE H 1.72 2.8

Motor NDE V 0.57 2.8

The impact test in standard condition resulted in 129 Hz horizontal natural frequency.

The impact test with sof shoe shim resulted in 99 Hz horizontal natural frequency.

Page 34: COOP REPORT

32

Conclusion

The natural frequency at standard conditions is 129 Hz which is 7.5 % of the forcing

frequency 120 Hz as seen from spectra figure (34). While in recommended practice, natural

frequency should be 15 -20 % away of the forcing frequency. This forcing frequency excites

the natural frequency resulting in high vibration records.

In the case of sof shoe shims installation, the natural frequency recorded dropped from 129

Hz to 99 Hz. This natural frequency is 17.5% away from the forcing frequency. The drop in

natural frequency resulted in drop in the vibrations. The sof shims installed under motor

feet act as damping elements.

General electric suggested the use of the sof shoe shims as permanent solution. However,

this solution was rejected by YASREF. Now, general electric is going to perform vibration

analysis at their shop for new motors. If the new motors give good vibration results at shop

and not accepted results at site, investigation should be carried to site parts such as

foundation, grouting and land.

Figure 32: Vibration spectra

Page 35: COOP REPORT

33

Conclusion and Recommendation

The coop training program was a great opportunity in which I spent 28 weeks working in a

real engineering environment. During that period, I have been able to relate the theoretical

part studied at KFUPM University with the practical part seen in real engineering

application. For example, I have been introduced to many mechanical equipment such as

pumps, compressors, pipes, gate valves, motors and many others that I have never seen in

my academic study. It was also time for me to learn how construction activities being

conducted and organized via governing standards such as ASME and SAES. Moreover, I got

some overall idea about the scope of some units of the refinery.

In addition to the technical and engineering knowledge gained, I have been able to improve

my own skills such as communication and team work skills. There have been many

engineers and technicians from different countries that I have worked with them. Improper

communication or team work may adversely affect the progress of the project. During the

training period, I have also learned how to be patient since it was required from us to work

eight hours a day at field offices. During working hours, you have to go for inspection many

times a day. I have also learned how meetings between main contract companies and

YESREF are conducted and how they discuss the project progress and problems faced.

Page 36: COOP REPORT

34

References

1. YASREF Overview. (n.d.). Retrieved from http://www.yasref.com/about/overview

2. Project Overview. (n.d.). Retrieved from http://www.yasref.com/project/overview

3. Splicing and repair manual. Retrieved from http:// www.blairrubber.com /pdf/Blair_

Splicing Manual.pdf

4. Mullan, H. Heat tracing basics. [PowerPoint slides]. Retrieved from http:// www.

Mullanconsultants.com/pdf/heat_tracing/Heat%20Tracing%20Basics_SLIDES-HRM-

300410.ppt

5. PENTAIR. (n.d.). Skin-effect heat-tracing system (STS) [Brochure]. Retrieved from

http://www.pentairthermal.com/Images/GB-RaychemSTSskineffectTracing System

APAC-SB-H57124_tcm432-37908.pdf

6. TEMPCO. (n.d.). Heat trace cable [Brochure]. Retrieved from http://www.tempco.

com/Tempco/Section6.pdf

7. Towsley, G. (n.d.). Alignment. Retrieved from http://www.grundfos. com/ content /

dam/CBS/global/whitepapers/Whitepaper%20-%20Alignment.pdf

8. The four easy steps to good shaft alignment. Retrieved from

http://www.carlylecompressor.com/Files/Carlyle_Compressor/Local/US-en/

documents/039-185_5FHShaftAlignment_lowres.pdf

9. YASREF. (2013, October 22). Sulfur pelletizer and loading operation and maintenance

manual. Yanbu, Saudi Arabia: Author.

10. Power Piping,ASME Code for Pressure Piping, B31. (2007). New York: The American

Society of Mechanical Engineers.