Yarra Valley Water Business Breakfast 24 November 2010 Coburg Principal Activity Centre Stormwater Harvesting and Reuse Project

Coburg a new paradigm for water supply

Embed Size (px)

Citation preview

Page 1: Coburg   a new paradigm for water supply

Yarra Valley Water Business Breakfast 24 November 2010

Coburg Principal Activity Centre Stormwater Harvesting and Reuse Project

Page 2: Coburg   a new paradigm for water supply

April 14, 2023 Yarra Valley Water Ltd 2

Page 3: Coburg   a new paradigm for water supply

April 14, 2023 3Yarra Valley Water Ltd

Background - Population

Victorian Government’s Melbourne 2030 Strategy:• 5 M population for Melbourne by 2030• 26 Principle Activity Centres (PAC) identified• Coburg identified as a PAC

Large amount of infill development expected:• 4,000 plus new residential dwellings• 65,000 m2 of commercial/retail floor space• 1400 new permanent jobs plus 10,000 temporary jobs during

construction• $900M worth of investment in local economy

Page 4: Coburg   a new paradigm for water supply

April 14, 2023 5Yarra Valley Water Ltd

Background – Stormwater

Increased urbanisation resulting in more stormwater runoff Further environmental degradation to waterways• Nutrient loading• Increased sedimentation

Run off capable (in many cases) to supply incremental increase in demand

Page 5: Coburg   a new paradigm for water supply

April 14, 2023 6Yarra Valley Water Ltd

Background (Continued)

New paradigm created:• Harnessing alternative water supplies• Sustainable principles• Long term environmental benefits

Council now pushing developers to apply ESD principles:• Focus on reducing potable consumption

Outcome - Stormwater harvesting

Page 6: Coburg   a new paradigm for water supply

April 14, 2023 7Yarra Valley Water Ltd

YVW Coburg Proposal

Harvest stormwater from two existing drains (MW and Council) which run along the boundary of the proposed site

Treat the stormwater to a very high recycled water standard

Reticulate the recycled water to:• All new houses/apartments within a designated

area for toilet flushing, laundry and outdoor uses• Nearby public open spaces for irrigation

Page 7: Coburg   a new paradigm for water supply

April 14, 2023 8Yarra Valley Water Ltd

Project Benefits

213 ML/year of potable water substituted

Much better stormwater quality than is currently the case:• Stormwater is currently untreated• Nitrogen – 22 % reduction• Phosphorous – 42 % reduction• Reduced sediment loading

Reduced urban run off to Merri Creek – 21 %

Recycled water available for open space irrigation

Page 8: Coburg   a new paradigm for water supply

April 14, 2023 Yarra Valley Water Ltd 9

Harvesting Stormwater

UndergroundLow Level

Tank(7ML)

Diversion 2

Diversion 1

Urquhart Street Drain(675mm)

Harding Street Drain(2.4m x 1.2m)

RelocatedTennisCourts

RWTP

UndergroundHigh Level

Tank(7ML)

Third Pipe

Page 9: Coburg   a new paradigm for water supply

April 14, 2023 Yarra Valley Water Ltd 10

Areas To Be Supplied With Recycled Water

Page 10: Coburg   a new paradigm for water supply

April 14, 2023 Yarra Valley Water Ltd 11

Underground tanks will use pre cast concrete culvert type sections

Proposed Underground Storage Tank Solution

Page 11: Coburg   a new paradigm for water supply

April 14, 2023 Yarra Valley Water Ltd 12

A packaged ultra-filtration treatment plant system will be used to produce Class A recycled water

Recycled Water Treatment Plant

Page 12: Coburg   a new paradigm for water supply

April 14, 2023 13Yarra Valley Water Ltd

Moving Forward

Federal Govt. grant of $6.6M approved for Project

Detailed planning with Moreland Council in progress

Design work for underground tanks/pumps etc underway Construction to start Aug 2011

Pro Active Community & Stakeholder Consultation planned to start January 2011