RttT Closeout

March 17, 2015

Race to the Top Program Management Office

Page 2: Closeout slides

2

Presentation Overview

• Closeout Timeline Summary

• Final DSW Amendment Submissions

• Program Closeout - Activities

• Program Closeout - Monitoring

• Fiscal Closeout

• General Reminders

Page 3: Closeout slides

2015 Closeout Timeline

3

Last day for DSW

Amendments

April 15 June 1 June 30 July 31

All Invoices Must Be

Paid

All DSW Activities

Completed

Monitoring Tool Closes

Monitoring Tool Opens

Page 4: Closeout slides

Final DSW Amendment Submissions

4

• Submit any final DSW amendments by April 15

• Be sure to contact your Regional Lead or Eric Thanos prior to deadline with any potential questions related to DSW amendments

June 1 June 30 July 31April 15

Page 5: Closeout slides

DSW Amendments Approval Process

Step 1:

Download approved DSW from RttT website

Step 2:

Make the text red for any changes that are made

Step 3:

Email amended DSW to all of the following addresses

Step 4:

DPI posts approved DSW to the RttT website

Step 5:

Submit new Budget in LBAAS that aligns to the approved amended DSW

Email:

[email protected]

[email protected]

[email protected]

• Your Regional Lead

5

Step 6:

DPI reviews your new budget in LBAAS (comparing it to new approved DSW)

Page 6: Closeout slides

Program Closeout - Activities

• Complete all activities by June 30

– Specifically, all goods and services must be received no later than June 30

– Example: Computers purchased with RttT funds must actually be delivered by June 30

– Example: PD must be provided by June 30

6

June 1 June 30 July 31April 15

Page 7: Closeout slides

Program Closeout - Monitoring

7

• Progress Report Monitoring Tool opens June 1

– Notify your Regional Lead to receive feedback prior to final submission

– Bottom line: “Did you do what you said you were going to do in your state-approved DSW?”

– Submit “Progress Reports” for 2014-15 school year to NCDPI by July 31

June 1 June 30 July 31April 15

Page 8: Closeout slides

Fiscal Closeout

• Encumber all RttT funds by June 30

• Pay all invoices by July 31 (the sooner the better!)

• Ensure that RttT funds in the DSW match budget/expenditure amounts in the LBAAS for all years

• Ensure that the encumbrance account matches the account code for the expense

8

June 1 June 30 July 31April 15

Page 9: Closeout slides

General Closeout Reminders

• Travel cannot be encumbered until it has occurred

• LEAs/Charters should keep good records during the encumbrance period; expenditures during this period will be heavily scrutinized

9

Page 10: Closeout slides

Key Contacts

10

Detailed Scopes of Work

[email protected]; (919) 807-3705

Progress Report

Your Regional Lead; http://www.ncpublicschools.org/rttt/directory/

[email protected]; (919) 807-3553

[email protected]; (919) 807-3738

Page 11: Closeout slides

Questions?

11

Last day for DSW

Amendments

April 15 June 1 June 30 July 31

All Invoices Must Be

Paid

All DSW Activities

Completed

Monitoring Tool Closes

Monitoring Tool Opens